IDOT contract 68F90 bid tabulation
Section (120,121)RS-3. Let by Illinois DOT on March 7, 2025, Putnam, District 04. 1 bid received; low bid $5,166,321 by Advanced Asphalt Company.
- Owner
- Illinois DOT
- Letting
- 07 MAR 2025
- Pay items
- 73
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Advanced Asphalt Company | $5,166,321 | Low |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Advanced Asphalt Company |
|---|---|---|---|---|
| 1 | Box culvert removal (X1200050) | LF | 4 | $2,200.00 |
| 2 | Cir-FDR emuls asphalt (X4005500) | TON | 567 | $600.00 |
| 3 | Cip recycling 4.0 (X4060221) | SY | 87,714 | $5.00 |
| 4 | HMA surf rem var DP (X4401198) | SY | 14,108 | $5.00 |
| 5 | Rem C box cul end sec (X5010520) | EACH | 1 | $2,200.00 |
| 6 | Linear delin panels 4 (X6350204) | EACH | 55 | $88.00 |
| 7 | Centerln rum strip 8 (X6420112) | LF | 2,021 | $3.00 |
| 8 | GDRL agg eros cont (Z0001002) | TON | 826 | $70.00 |
| 9 | HMA removal SPL (Z0004542) | SY | 1,832 | $15.00 |
| 10 | Construction layout (Z0013798) | LS | 1 | $20,000 |
| 11 | RR prot liability ins (Z0048665) | LS | 1 | $7,500.00 |
| 12 | Rumble strip (Z0055600) | SY | 36 | $75.00 |
| 13 | Trainees (Z0076600) | HR | 1,000 | $0.80 |
| 14 | Trainees TPG (Z0076604) | HR | 1,000 | $15.00 |
| 15 | Trench backfill (20800150) | CY | 76 | $80.00 |
| 16 | Porous gran backfill (20900110) | CY | 2 | $150.00 |
| 17 | Topsoil F & P var DP (21101600) | SY | 190 | $35.00 |
| 18 | Stone dump rip CL A4 (28100707) | SY | 262 | $85.00 |
| 19 | Stone dump rip CL B3 (28100825) | TON | 37 | $95.00 |
| 20 | Agg subgrade improve (30300001) | CY | 15 | $125.00 |
| 21 | Agg surf course TY B (40200800) | TON | 90 | $65.00 |
| 22 | P bit matls tack CT (40600295) | LB | 165,043 | $1.15 |
| 23 | Matl transfer device (40600405) | TON | 18,688 | $4.00 |
| 24 | HMA surf rem butt JT (40600982) | SY | 5,282 | $15.00 |
| 25 | Temporary ramp (40600990) | SY | 4,062 | $12.00 |
| 26 | P HMA BC IL-4.75 N50 (40603200) | TON | 5,703 | $135.00 |
| 27 | P HMA BC IL-9.5 N70 (40603208) | TON | 742 | $125.00 |
| 28 | P HMA SC IL-9.5 D N70 (40604162) | TON | 11,882 | $125.00 |
| 29 | Incidental HMA surf (40800050) | TON | 501 | $150.00 |
| 30 | HMA surf rem 3/4 (44000152) | SY | 85,865 | $2.65 |
| 31 | HMA surf rem 1 1/4 (44000154) | SY | 1,919 | $7.00 |
| 32 | HMA surf rem 2 (44000157) | SY | 11,778 | $3.50 |
| 33 | HMA surf rem 2 1/2 (44000159) | SY | 835 | $7.00 |
| 34 | HMA surf rem 2 3/4 (44000160) | SY | 3,265 | $3.50 |
| 35 | HMA surf rem 3 1/4 (44000162) | SY | 648 | $7.00 |
| 36 | Gutter rem (44000400) | LF | 659 | $15.00 |
| 37 | CL D patch T4 15 (44201833) | SY | 244 | $275.00 |
| 38 | Aggregate SHLDS B (48101200) | TON | 1,601 | $30.00 |
| 39 | Reinforcement bars (50800105) | LB | 60 | $10.00 |
| 40 | Box cul end sec C1 (54001001) | EACH | 1 | $13,000 |
| 41 | PCBC 4X3 (54010403) | LF | 8.50 | $1,500.00 |
| 42 | P cul CL C 2 18 (542C1063) | LF | 80 | $115.00 |
| 43 | Concrete collar (54248510) | CY | 1 | $3,800.00 |
| 44 | Class SI conc outlet (60600095) | CY | 6.80 | $1,400.00 |
| 45 | Concrete gutter TY A (60602500) | LF | 474 | $65.00 |
| 46 | Box cul to BE cleaned (60905305) | LF | 84 | $40.00 |
| 47 | Pipe culv cleaned 18 (60920018) | LF | 40 | $40.00 |
| 48 | Pipe culv cleaned 36 (60920036) | LF | 95 | $40.00 |
| 49 | SPBGR TY A 6FT posts (63000001) | LF | 3,525 | $33.50 |
| 50 | TR bar TRM T1 SPL tan (63100167) | EACH | 10 | $3,800.00 |
| 51 | TR bar TRM T1 SPL FLR (63100169) | EACH | 6 | $3,265.00 |
| 52 | Guardrail remov (63200310) | LF | 2,450 | $4.50 |
| 53 | Shoulder rum strip 16 (64200116) | LF | 1,181 | $3.50 |
| 54 | Engr field office A (67000400) | CAL MO | 3 | $2,500.00 |
| 55 | Mobilization (67100100) | LS | 1 | $305,000 |
| 56 | Traf cont-prot 701316 (70100100) | EACH | 1 | $40,000 |
| 57 | Traf cont-prot 701201 (70100450) | LS | 1 | $100.00 |
| 58 | Traf cont-prot 701306 (70100460) | LS | 1 | $48,000 |
| 59 | Traf cont-prot 701326 (70100500) | LS | 1 | $100.00 |
| 60 | Traf cont-prot 701336 (70100600) | LS | 1 | $100.00 |
| 61 | TR cont & prot 701501 (70102620) | LS | 1 | $100.00 |
| 62 | TR cont surveillance (70103815) | CAL DAY | 6 | $1,000.00 |
| 63 | Temp BR traf signals (70106500) | EACH | 1 | $12,000 |
| 64 | Short term pavt mking (70300100) | LF | 14,240 | $0.65 |
| 65 | SHRT TRM pavt MK rem (70300150) | SF | 3,742 | $2.25 |
| 66 | Terminal marker - DA (72501000) | EACH | 16 | $58.50 |
| 67 | Mod ureth PM line 4 (78009004) | LF | 108,674 | $0.90 |
| 68 | Mod ureth PM line 8 (78009008) | LF | 339 | $1.80 |
| 69 | GRV RCSD PVT MRKG 5 (78011025) | LF | 89,890 | $0.40 |
| 70 | GRV RCSD PVT MRKG 9 (78011045) | LF | 339 | $1.15 |
| 71 | Raised refl pavt MKR (78100100) | EACH | 343 | $42.00 |
| 72 | Grdrail ref type A (78200005) | EACH | 55 | $29.00 |
| 73 | Raised ref PVT MK rem (78300200) | EACH | 341 | $15.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of March 7, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way