IDOT contract 68J57 bid tabulation
Section (8,103)RS-5;[(103B)I]BRR. Let by Illinois DOT on February 27, 2026, Peoria, District 04. 2 bids received; low bid $5,129,210 by Advanced Asphalt Company.
- Owner
- Illinois DOT
- Letting
- 27 FEB 2026
- Pay items
- 89
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Advanced Asphalt Company | $5,129,210 | Low |
| 2 | R. A. Cullinan and Son, a div of UCM, Inc. | $5,442,603 | +6.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Advanced Asphalt Company | 2. R. A. Cullinan and Son, a div of UCM, Inc. |
|---|---|---|---|---|---|
| 1 | Constr sta layout (XZ013798) | LS | 1 | $15,850 | $2,513.58 |
| 2 | Solar-power FB as CMP (X0326899) | EACH | 6 | $10,000 | $21,520 |
| 3 | Rem ST RE snplassy SP (X2600022) | EACH | 4 | $475.00 | $230.63 |
| 4 | HMA surf rem SPL (X4400196) | SY | 4,022 | $23.80 | $13.52 |
| 5 | Class SI conc out SPL (X6060097) | CY | 37 | $457.30 | $881.50 |
| 6 | Conc median SPL (X6060714) | SF | 487 | $30.90 | $22.55 |
| 7 | Conc gutter TA SPL (X6062700) | LF | 671 | $64.50 | $82.00 |
| 8 | Linear delin panels 4 (X6350204) | EACH | 16 | $75.00 | $71.24 |
| 9 | GDRL agg eros cont (Z0001002) | TON | 167 | $83.75 | $138.38 |
| 10 | Gas valve adjusted (Z0001110) | EACH | 1 | $435.05 | $2,109.83 |
| 11 | RR prot liability ins (Z0048665) | LS | 1 | $10,265 | $8,820.40 |
| 12 | Trainees (Z0076600) | HR | 5,000 | $0.80 | $0.80 |
| 13 | Trainees TPG (Z0076604) | HR | 5,000 | $15.00 | $15.00 |
| 14 | Topsoil F & P 4 (21101615) | SY | 59 | $20.00 | $53.30 |
| 15 | Seeding CL 2A (25000210) | ACRE | 0.25 | $10,000 | $13,325 |
| 16 | Mowing (25000750) | ACRE | 29.25 | $90.00 | $92.25 |
| 17 | Agg surf course TY B (40200800) | TON | 379 | $45.65 | $51.25 |
| 18 | P bit matls tack CT (40600295) | LB | 180,714 | $0.75 | $1.25 |
| 19 | Matl transfer device (40600405) | TON | 23,058 | $2.50 | $1.90 |
| 20 | HMA surf rem butt JT (40600982) | SY | 7,136 | $14.70 | $16.08 |
| 21 | Temporary ramp (40600990) | SY | 1,633 | $26.90 | $24.16 |
| 22 | P HMA BC IL-4.75 N50 (40603200) | TON | 2,235 | $126.00 | $141.31 |
| 23 | P HMA BC IL-9.5 N50 (40603205) | TON | 7,850.70 | $107.00 | $113.91 |
| 24 | P HMA SC IL-9.5 D N50 (40604160) | TON | 12,972 | $111.00 | $113.88 |
| 25 | Incidental HMA surf (40800050) | TON | 1,315 | $172.00 | $259.75 |
| 26 | PCC driveway pavt 7 (42300300) | SY | 103 | $101.15 | $105.58 |
| 27 | PC conc sidewalk 4 (42400100) | SF | 2,879 | $15.15 | $11.28 |
| 28 | Detectable warnings (42400800) | SF | 149 | $22.30 | $41.00 |
| 29 | HMA surf rem 1 (44000153) | SY | 39,429 | $1.50 | $1.34 |
| 30 | HMA surf rem 2 (44000157) | SY | 63,022 | $2.25 | $2.38 |
| 31 | HMA surf rem 3 3/4 (44000164) | SY | 10,961 | $6.00 | $4.64 |
| 32 | Drive pavement rem (44000200) | SY | 123 | $36.30 | $25.63 |
| 33 | Gutter rem (44000400) | LF | 671 | $16.20 | $17.43 |
| 34 | Comb curb gutter rem (44000500) | LF | 2,511 | $22.00 | $16.40 |
| 35 | Sidewalk rem (44000600) | SF | 3,049 | $5.60 | $3.08 |
| 36 | Paved SHLD removal (44004250) | SY | 181 | $26.80 | $20.50 |
| 37 | CL D patch T2 15 (44201827) | SY | 143 | $328.95 | $358.75 |
| 38 | CL D patch T4 15 (44201833) | SY | 72 | $268.50 | $358.75 |
| 39 | Agg wedge SHLD type B (48102100) | TON | 3,391 | $29.20 | $34.85 |
| 40 | BR deck grooving (50300260) | SY | 228 | $40.00 | $41.00 |
| 41 | Protective coat (50300300) | SY | 242 | $11.70 | $11.99 |
| 42 | BR deck scar 3/4 (53101002) | SY | 242 | $362.00 | $371.05 |
| 43 | BR DK mic C ovl 2 1/4 (53101608) | SY | 242 | $221.35 | $226.88 |
| 44 | Water valves adjust (56109210) | EACH | 1 | $169.50 | $2,260.71 |
| 45 | Inlets adjust (60260100) | EACH | 3 | $1,144.70 | $1,025.00 |
| 46 | Inlets adj new T10F&G (60261200) | EACH | 1 | $2,111.05 | $1,640.00 |
| 47 | Conc curb TB (60600605) | LF | 80 | $132.35 | $145.55 |
| 48 | Comb CC&G TY B-6.24 (60605000) | LF | 2,401 | $58.40 | $75.85 |
| 49 | Comb CC&G TB6.24 VWGF (60605500) | LF | 27 | $132.15 | $111.73 |
| 50 | SPBGR TY A 6FT posts (63000001) | LF | 475 | $45.50 | $30.19 |
| 51 | Traf bar term T6A (63100087) | EACH | 4 | $3,795.00 | $5,699.00 |
| 52 | TR bar TRM T1 SPL tan (63100167) | EACH | 4 | $4,595.00 | $3,695.13 |
| 53 | Guardrail remov (63200310) | LF | 816 | $12.50 | $15.12 |
| 54 | Sinusoidal rum STP 14 (64200214) | LF | 23,746 | $0.35 | $0.50 |
| 55 | Mobilization (67100100) | LS | 1 | $300,000 | $159,552 |
| 56 | Traf cont-prot 701321 (70100405) | EACH | 1 | $7,110.00 | $10,096 |
| 57 | Traf cont-prot 701201 (70100450) | LS | 1 | $7,110.00 | $0.01 |
| 58 | Traf cont-prot 701306 (70100460) | LS | 1 | $33,860 | $29,366 |
| 59 | Traf cont-prot 701336 (70100600) | LS | 1 | $6,710.00 | $17,399 |
| 60 | TR cont & prot 701801 (70102640) | LS | 1 | $2,085.00 | $358.75 |
| 61 | Temp BR traf signals (70106500) | EACH | 1 | $9,000.00 | $13,838 |
| 62 | Temp rumble strips (70106700) | EACH | 6 | $1,320.00 | $1,353.00 |
| 63 | Pavt MK blkout tape 5 (70107005) | LF | 2,494 | $2.90 | $2.97 |
| 64 | Changeable message SN (70107025) | CAL DAY | 28 | $125.00 | $128.13 |
| 65 | Short term pavt mking (70300100) | LF | 10,865 | $2.50 | $2.25 |
| 66 | SHRT TRM pavt MK rem (70300150) | SF | 3,622 | $2.00 | $3.78 |
| 67 | Temp PVT MK L4 T4 tape (70307120) | LF | 2,494 | $1.60 | $1.64 |
| 68 | Temp conc barrier (70400100) | LF | 237.50 | $55.65 | $74.83 |
| 69 | Rel temp conc barrier (70400200) | LF | 237.50 | $27.35 | $15.12 |
| 70 | Imp attn temp NRD TL3 (70600250) | EACH | 2 | $4,520.00 | $5,950.84 |
| 71 | Imp attn rel NRD TL3 (70600350) | EACH | 2 | $1,470.00 | $5,050.74 |
| 72 | Terminal marker - DA (72501000) | EACH | 4 | $50.00 | $51.25 |
| 73 | Mod ureth PM LTR-sym (78009000) | SF | 78 | $5.00 | $5.13 |
| 74 | Mod ureth PM line 4 (78009004) | LF | 37,476 | $0.75 | $0.77 |
| 75 | Mod ureth PM line 6 (78009006) | LF | 67,779 | $0.80 | $0.82 |
| 76 | Mod ureth PM line 8 (78009008) | LF | 956 | $1.80 | $1.85 |
| 77 | Mod ureth PM line 12 (78009012) | LF | 362 | $2.80 | $2.87 |
| 78 | Mod ureth PM line 24 (78009024) | LF | 94 | $5.00 | $5.13 |
| 79 | GRV RCSD PM LTR & sym (78011000) | SF | 90 | $3.00 | $3.08 |
| 80 | GRV RCSD PVT MRKG 5 (78011025) | LF | 37,476 | $0.60 | $0.62 |
| 81 | GRV RCSD PVT MRKG 7 (78011035) | LF | 68,171 | $0.65 | $0.67 |
| 82 | GRV RCSD PVT MRKG 9 (78011045) | LF | 956 | $1.35 | $1.38 |
| 83 | GRV RCSD PVT MRKG 13 (78011065) | LF | 362 | $2.00 | $2.05 |
| 84 | GRV RCSD PVT MRKG 25 (78011125) | LF | 94 | $3.35 | $3.43 |
| 85 | Raised refl pavt MKR (78100100) | EACH | 581 | $42.50 | $43.56 |
| 86 | Curb reflectors (78200020) | EACH | 21 | $18.00 | $56.38 |
| 87 | Raised ref PVT MK rem (78300200) | EACH | 581 | $9.85 | $36.69 |
| 88 | Remov EX handhole (89502380) | EACH | 2 | $1,745.00 | $1,413.89 |
| 89 | Rem EX FB instal comp (89502400) | EACH | 6 | $1,500.00 | $1,863.76 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of February 27, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.