IDOT contract 68K20 bid tabulation

Section 123RS-7;(123RA)RS. Let by Illinois DOT on April 24, 2026, Stark, District 04. 1 bid received; low bid $2,839,793 by Advanced Asphalt Company.

Owner
Illinois DOT
Letting
24 APR 2026
Pay items
76
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Advanced Asphalt Company$2,839,793Low
IDOT contract 68K20: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Advanced Asphalt Company
1Constr sta layout (XZ013798)LS1$16,777
2Solar-power FB as CMP (X0326899)EACH1$9,355.16
3Conc curb TB SPL (X6061005)LF60$59.04
4Linear delin panels 4 (X6350204)EACH16$91.66
5GDRL agg eros cont (Z0001002)TON61$111.46
6HMA removal SPL (Z0004542)SY1,891$22.60
7Trainees (Z0076600)HR1,500$0.80
8Trainees TPG (Z0076604)HR1,500$15.00
9Earth excavation (20200100)CY769$80.00
10Trench backfill (20800150)CY34$95.00
11Topsoil F & P 4 (21101615)SY1,190$22.50
12Erosion contr blanket (25100630)SY1,497$10.00
13Temp eros contr seed (28000250)LB31$30.00
14Temp ditch checks (28000305)LF2$300.00
15Inlet & pipe protect (28000500)EACH3$1,000.00
16Stone riprap CL A4 (28100207)TON27$300.00
17Filter fabric (28200200)SY41$22.91
18Sub gran mat B (31101000)TON193$76.80
19Bit matls PR CT (40600275)LB827$1.76
20P bit matls tack CT (40600295)LB77,995$1.01
21Matl transfer device (40600405)TON9,094$5.29
22HMA surf rem butt JT (40600982)SY1,517$29.46
23Temporary ramp (40600990)SY324$46.96
24P HMA BC IL-9.5 N50 (40603205)TON282$195.00
25P HMA SC IL-9.5 D N50 (40604160)TON8,812$140.00
26Incidental HMA surf (40800050)TON89$280.25
27HMA surf rem 3/4 (44000152)SY98,727$3.00
28HMA surf rem 2 (44000157)SY2,508$12.50
29HMA surf rem 3 3/4 (44000164)SY368$30.00
30Sidewalk rem (44000600)SF39$26.68
31Paved ditch removal (44004000)LF124$24.21
32Paved SHLD removal (44004250)SY41$72.85
33CL D patch T2 6 (44201717)SY12$383.33
34CL D patch T4 6 (44201723)SY27$330.92
35Aggregate SHLDS B (48101200)TON2,759$42.48
36HMA shoulders (48203100)TON123$479.50
37Pipe culvert remov (50105220)LF144$35.00
38P cul CL D 1 15 (542D0220)LF60$50.00
39P cul CL D 1 21 (542D0226)LF106$65.00
40Metal FL end sec 15" (54262715)EACH2$500.00
41Metal FL end sec 21" (54262721)EACH4$600.00
42Paved ditch TA-15 (60615400)LF10$200.00
43SPBGR TY A 6FT posts (63000001)LF625$51.33
44Traf bar term T6 (63100085)EACH4$4,882.28
45TR bar TRM T1 SPL FLR (63100169)EACH4$4,705.08
46Guardrail remov (63200310)LF933$9.17
47Sinusoidal rum STP 14 (64200214)LF34,165$0.39
48Mobilization (67100100)LS1$160,000
49Traf cont-prot 701201 (70100450)LS1$2,302.19
50Traf cont-prot 701306 (70100460)LS1$21,362
51Changeable message SN (70107025)CAL DAY28$61.11
52Short term pavt mking (70300100)LF3,428$6.59
53SHRT TRM pavt MK rem (70300150)SF1,143$3.47
54Temp PVT MK LTR & sym paint (70300211)SF31$3.67
55Temp PVT MK line 4 - paint (70300221)LF22,480$0.17
56Temp PVT MK line 6 - paint (70300241)LF68,852$0.27
57Temp PVT MK line 8 - paint (70300251)LF348$0.43
58Temp PVT MK line 12 - paint (70300261)LF227$0.59
59Temp PVT MK line 24 - paint (70300281)LF31$3.97
60Sign panel T1 (72000100)SF2$91.66
61Terminal marker - DA (72501000)EACH4$61.11
62Teles STL sin support (72800100)LF14$46.44
63Mod ureth PM LTR-sym (78009000)SF34$5.50
64Mod ureth PM line 4 (78009004)LF22,726$0.94
65Mod ureth PM line 6 (78009006)LF70,866$1.42
66Mod ureth PM line 8 (78009008)LF348$1.88
67Mod ureth PM line 12 (78009012)LF227$2.82
68Mod ureth PM line 24 (78009024)LF31$5.80
69GRV RCSD PM LTR & sym (78011000)SF31$7.64
70GRV RCSD PVT MRKG 5 (78011025)LF22,480$0.49
71GRV RCSD PVT MRKG 7 (78011035)LF68,852$0.73
72GRV RCSD PVT MRKG 9 (78011045)LF348$1.10
73GRV RCSD PVT MRKG 13 (78011065)LF227$3.67
74GRV RCSD PVT MRKG 25 (78011125)LF31$7.33
75Raised refl pavt MKR (78100100)EACH427$45.85
76Raised ref PVT MK rem (78300200)EACH427$20.11
IDOT contract 68K20: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of April 24, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy