IDOT contract 70024 bid tabulation
Section (74-68VB)B. Let by Illinois DOT on August 1, 2025, Piatt, District 05. 3 bids received; low bid $8,849,135 by Stark Excavating, Inc..
- Owner
- Illinois DOT
- Letting
- 01 AUG 2025
- Pay items
- 102
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Stark Excavating, Inc. | $8,849,135 | Low |
| 2 | Sangamo Construction Company | $8,906,936 | +1.0% |
| 3 | William Charles Construction Company, LLC | $8,979,000 | +1.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Stark Excavating, Inc. | 2. Sangamo Construction Company | 3. William Charles Construction Company, LLC |
|---|---|---|---|---|---|---|
| 1 | BR deck grooving long (X5030250) | SY | 1,528 | $10.00 | $11.72 | $12.00 |
| 2 | Structural STL removl (X5051204) | LB | 4,204 | $1.75 | $0.94 | $2.00 |
| 3 | Struct steel repair (X5051206) | LB | 1,552 | $38.00 | $27.89 | $35.00 |
| 4 | Bar terminators (X5080530) | EACH | 484 | $20.00 | $30.80 | $25.00 |
| 5 | Pipe underdrn rem SPL (X6013700) | LF | 3,880 | $18.00 | $3.25 | $8.00 |
| 6 | Remov inlets SPL (X6050065) | EACH | 7 | $2,165.00 | $753.82 | $2,200.00 |
| 7 | Fence rem & reinstall (X6640108) | LF | 200 | $80.00 | $70.74 | $30.00 |
| 8 | Width restrict sign (X7200201) | LS | 1 | $6,000.00 | $6,129.54 | $5,800.00 |
| 9 | Approach slab rem (Z0004552) | SY | 580 | $58.00 | $58.27 | $80.00 |
| 10 | HMA surface RM (deck) (Z0004556) | SY | 948 | $13.75 | $12.70 | $20.00 |
| 11 | STR rep con DP = < 5 (Z0012754) | SF | 247 | $145.00 | $169.52 | $145.00 |
| 12 | STR rep con DP over 5 (Z0012755) | SF | 38 | $195.00 | $283.21 | $225.00 |
| 13 | Construction layout (Z0013798) | LS | 1 | $65,000 | $60,898 | $50,000 |
| 14 | Deck slab rep (FD-T2) (Z0016002) | SY | 225 | $1,195.00 | $865.54 | $1,400.00 |
| 15 | Deck slab rep (part) (Z0016200) | SY | 74 | $650.00 | $583.19 | $800.00 |
| 16 | Diamond grind BR sec (Z0029090) | SY | 2,268 | $15.00 | $14.48 | $17.75 |
| 17 | Permnt bench marks (Z0038700) | EACH | 2 | $475.00 | $942.21 | $425.00 |
| 18 | RR prot liability ins (Z0048665) | LS | 1 | $7,200.00 | $22,012 | $25,000 |
| 19 | Rock fill - embank (Z0054404) | CY | 174 | $150.00 | $321.63 | $150.00 |
| 20 | Trainees (Z0076600) | HR | 3,000 | $0.80 | $0.80 | $0.80 |
| 21 | Trainees TPG (Z0076604) | HR | 3,000 | $15.00 | $15.00 | $15.00 |
| 22 | Seeding CL 2 (25000200) | ACRE | 0.50 | $6,250.00 | $3,334.26 | $3,155.00 |
| 23 | Nitrogen fert nutr (25000400) | LB | 45 | $3.00 | $10.57 | $10.00 |
| 24 | Phosphorus fert nutr (25000500) | LB | 45 | $3.00 | $10.57 | $10.00 |
| 25 | Potassium fert nutr (25000600) | LB | 45 | $3.00 | $10.57 | $10.00 |
| 26 | Mulch method 2 (25100115) | ACRE | 0.50 | $2,115.00 | $3,334.26 | $3,155.00 |
| 27 | Temp eros contr seed (28000250) | LB | 50 | $5.00 | $5.08 | $10.00 |
| 28 | Stab subbase 4 (31200100) | SY | 756 | $82.00 | $80.64 | $92.85 |
| 29 | Bit matls tack CT (40600290) | LB | 3,332 | $3.15 | $11.73 | $3.00 |
| 30 | Long joint sealant (40600370) | LF | 1,982 | $11.50 | $13.84 | $10.87 |
| 31 | HMA surf rem butt JT (40600982) | SY | 533 | $35.00 | $42.06 | $20.00 |
| 32 | HMA BC IL-19.0 N90 (40603090) | TON | 152 | $575.00 | $436.25 | $550.00 |
| 33 | HMA SC IL-9.5 D N70 (40604062) | TON | 105 | $450.00 | $530.21 | $430.00 |
| 34 | HMA SC IL-9.5 E N90 (40604074) | TON | 127 | $595.00 | $506.00 | $560.00 |
| 35 | Welded wire reinf (42000060) | SY | 501 | $30.00 | $19.73 | $30.00 |
| 36 | PVT con PCC BR app SL (42000080) | SY | 838 | $225.00 | $277.32 | $280.00 |
| 37 | Protective coat (42001300) | SY | 838 | $3.50 | $3.40 | $3.00 |
| 38 | Pavement rem (44000100) | SY | 243 | $50.00 | $54.23 | $80.00 |
| 39 | HMA surf rem 1 1/2 (44000155) | SY | 1,667 | $21.00 | $23.09 | $8.50 |
| 40 | Curb rem (44000300) | LF | 1,022 | $7.00 | $3.29 | $12.00 |
| 41 | Paved SHLD removal (44004250) | SY | 4,042 | $16.50 | $19.55 | $27.50 |
| 42 | Aggregate SHLDS B (48101200) | TON | 86 | $220.00 | $412.53 | $135.00 |
| 43 | HMA shoulders (48203100) | TON | 2,277 | $215.00 | $215.59 | $205.00 |
| 44 | Rem exist sup-STR N1 (50101700) | EACH | 1 | $365,000 | $267,336 | $176,000 |
| 45 | Rem exist sup-STR N2 (50101800) | EACH | 1 | $365,000 | $267,336 | $176,000 |
| 46 | Conc rem (50102400) | CY | 109.60 | $1,850.00 | $2,058.20 | $2,250.00 |
| 47 | Slope wall remov (50104650) | SY | 261 | $82.00 | $48.15 | $60.00 |
| 48 | Protective shield (50157300) | SY | 794 | $75.00 | $105.90 | $100.00 |
| 49 | Structure excavation (50200100) | CY | 623 | $50.00 | $39.86 | $50.00 |
| 50 | Floor drains (50300100) | EACH | 18 | $475.00 | $636.30 | $700.00 |
| 51 | Conc struct (50300225) | CY | 100.90 | $1,525.00 | $1,812.00 | $1,750.00 |
| 52 | Conc sup-STR (50300255) | CY | 758.40 | $1,800.00 | $1,914.91 | $1,750.00 |
| 53 | Protective coat (50300300) | SY | 2,992 | $3.50 | $3.42 | $2.00 |
| 54 | Conc supstr app slab (50301350) | CY | 238 | $770.00 | $752.13 | $800.00 |
| 55 | F & E struct steel (50500105) | LS | 1 | $1,930,000 | $1,959,450 | $2,185,000 |
| 56 | F & E struct steel (50500405) | LB | 4,204 | $8.80 | $9.37 | $10.00 |
| 57 | Stud shear connectors (50500505) | EACH | 13,140 | $5.10 | $5.20 | $4.75 |
| 58 | Reinf bars, epoxy CTD (50800205) | LB | 281,040 | $1.65 | $1.70 | $1.75 |
| 59 | Bar splicers (50800515) | EACH | 2,216 | $47.00 | $54.63 | $50.00 |
| 60 | Slope wall 4 (51100100) | SY | 261 | $200.00 | $261.02 | $200.00 |
| 61 | Name plates (51500100) | EACH | 2 | $1,500.00 | $1,064.08 | $1,000.00 |
| 62 | Pref JT strip seal (52000110) | LF | 112 | $325.00 | $348.24 | $300.00 |
| 63 | Elast bearing assy T1 (52100010) | EACH | 36 | $2,285.00 | $2,456.33 | $2,000.00 |
| 64 | Anchor bolts 1 (52100520) | EACH | 48 | $195.00 | $196.57 | $125.00 |
| 65 | Anchor bolts 1 1/4 (52100530) | EACH | 48 | $250.00 | $251.42 | $175.00 |
| 66 | Temp SHT piling (52200010) | SF | 1,545 | $60.00 | $58.59 | $75.00 |
| 67 | End sections 12 (54213447) | EACH | 4 | $500.00 | $311.92 | $1,000.00 |
| 68 | Granular backfill STR (58600101) | CY | 623 | $100.00 | $105.66 | $125.00 |
| 69 | Concrete sealer (58700300) | SF | 1,806 | $3.75 | $2.65 | $2.00 |
| 70 | Geocomposite wall DR (59100100) | SY | 228 | $40.00 | $32.73 | $50.00 |
| 71 | Pipe drains 12 (60100945) | LF | 140 | $80.00 | $41.42 | $70.00 |
| 72 | Pipe underdr T 3 (60108501) | LF | 3,880 | $21.00 | $31.65 | $5.00 |
| 73 | P undr for struct 4 (60146304) | LF | 340 | $52.00 | $32.27 | $35.00 |
| 74 | Conc curb TB (60600605) | LF | 989 | $80.00 | $49.45 | $50.00 |
| 75 | TY E inlet box 610001 (61000115) | EACH | 7 | $5,785.00 | $7,144.03 | $6,000.00 |
| 76 | SPBGR TY A 6FT posts (63000001) | LF | 1,237.50 | $36.00 | $37.00 | $45.70 |
| 77 | Traf bar term T6 (63100085) | EACH | 5 | $6,000.00 | $6,204.64 | $6,149.68 |
| 78 | TR bar TRM T1 SPL tan (63100167) | EACH | 3 | $4,475.00 | $4,570.66 | $4,799.75 |
| 79 | Guardrail remov (63200310) | LF | 1,363 | $7.00 | $5.44 | $10.48 |
| 80 | R&R rail elem EX GDRL (63300575) | LF | 2,206 | $15.50 | $16.32 | $20.00 |
| 81 | Shoulder rum strip 16 (64200116) | LF | 3,346 | $3.15 | $4.64 | $2.80 |
| 82 | Engr field office B (67000500) | CAL MO | 15 | $2,350.00 | $3,525.01 | $3,000.00 |
| 83 | Mobilization (67100100) | LS | 1 | $530,000 | $525,509 | $539,000 |
| 84 | Traf cont-prot 701401 (70100205) | EACH | 8 | $0.01 | $1.00 | $1.00 |
| 85 | Traf cont-prot 701402 (70100207) | EACH | 8 | $0.01 | $1.00 | $1.00 |
| 86 | Traf cont-prot 701406 (70100700) | LS | 1 | $1,000.00 | $1,979.06 | $73,965 |
| 87 | TR cont surveillance (70103815) | CAL DAY | 35 | $0.01 | $1.24 | $1.00 |
| 88 | Pavt MK blkout tape 5 (70107005) | LF | 13,899 | $2.85 | $2.85 | $2.70 |
| 89 | Short term pavt mking (70300100) | LF | 184 | $1.60 | $1.59 | $1.50 |
| 90 | SHRT TRM pavt MK rem (70300150) | SF | 7,465 | $1.20 | $1.16 | $1.10 |
| 91 | Temp PVT MK L4 T4 tape (70307120) | LF | 13,519 | $1.50 | $1.59 | $1.50 |
| 92 | Temp conc barrier (70400100) | LF | 1,775 | $44.00 | $52.26 | $60.00 |
| 93 | Pin temp conc barrier (70400125) | EACH | 198 | $45.00 | $47.69 | $5.00 |
| 94 | Rel temp conc barrier (70400200) | LF | 3,600 | $7.50 | $9.54 | $15.00 |
| 95 | Imp attn temp NRD TL3 (70600250) | EACH | 2 | $5,200.00 | $4,491.48 | $5,600.00 |
| 96 | Imp attn rel NRD TL3 (70600350) | EACH | 6 | $825.00 | $475.57 | $1,500.00 |
| 97 | Terminal marker - DA (72501000) | EACH | 3 | $50.00 | $54.41 | $28.39 |
| 98 | Polyurea PM T2 LN 4 (78008310) | LF | 2,813 | $3.40 | $3.43 | $3.25 |
| 99 | GRV RCSD PVT MRKG 5 (78011025) | LF | 2,813 | $3.40 | $3.43 | $3.25 |
| 100 | Raised refl pavt MKR (78100100) | EACH | 12 | $435.00 | $449.15 | $425.00 |
| 101 | Grdrail ref type A (78200005) | EACH | 24 | $10.00 | $10.88 | $7.81 |
| 102 | Raised ref PVT MK rem (78300200) | EACH | 12 | $40.00 | $12.37 | $75.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of August 1, 2025. Compiled by Mirage Metrics.