IDOT contract 70H62 bid tabulation

Section (22)BR-1,(115)BR-1. Let by Illinois DOT on February 27, 2026, Douglas, District 05. 1 bid received; low bid $926,892 by Sangamo Construction Company.

Owner
Illinois DOT
Letting
27 FEB 2026
Pay items
29
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Sangamo Construction Company$926,892Low
IDOT contract 70H62: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Sangamo Construction Company
1Base course (option) (X3550101)SY242$129.75
2Struct steel remov (X5051204)LB4,500$3.68
3Struct steel repair (X5051206)LB4,270$20.89
4Width restrict sign (X7200201)LS1$2,070.44
5Appr slab repair (PD) (Z0001800)SY25.60$1,180.06
6Jack & rem EX bearing (Z0001899)EACH10$2,357.44
7Construction layout (Z0013798)LS1$12,880
8Permnt bench marks (Z0038700)EACH1$231.26
9Earth excavation (20200100)CY54$400.72
10Conc rem (50102400)CY32.30$3,297.81
11Conc sup-STR (50300255)CY50.80$3,300.11
12Protective coat (50300300)SY95$3.85
13F & E struct steel (50500405)LB3,530$14.43
14Reinf bars, epoxy CTD (50800205)LB6,300$4.62
15Bar splicers (50800515)EACH76$51.12
16Pref JT strip seal (52000110)LF36$336.57
17Elast bearing assy T1 (52100010)EACH5$1,948.57
18Anchor bolts 1 (52100520)EACH20$186.78
19Deck slab rep (FD-T2) (53016002)SY31.20$1,253.80
20Engr field office B (67000500)CAL MO6$3,923.83
21Mobilization (67100100)LS1$53,760
22Traf cont-prot 701321 (70100405)EACH2$32,703
23Traf cont-prot 701201 (70100450)LS1$10,213
24Temp BR traf signals (70106500)EACH2$22,139
25Temp rumble strips (70106700)EACH12$1,513.02
26Temp conc barrier (70400100)LF637.50$53.20
27Rel temp conc barrier (70400200)LF637.50$10.21
28Imp attn temp NRD TL3 (70600250)EACH4$4,512.50
29Imp attn rel NRD TL3 (70600350)EACH4$530.88
IDOT contract 70H62: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of February 27, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy