IDOT contract 72406 bid tabulation
Section (1ZB1)BDR-1. Let by Illinois DOT on September 18, 2026, Adams, District 06. 3 bids received; low bid $6,962,525 by Freesen, a div of UCM, Inc..
- Owner
- Illinois DOT
- Letting
- 18 SEP 2026
- Pay items
- 54
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Freesen, a div of UCM, Inc. | $6,962,525 | Low |
| 2 | Sangamo Construction Company | $8,538,416 | +23% |
| 3 | County Contractors, Inc. | $9,458,572 | +36% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Freesen, a div of UCM, Inc. | 2. Sangamo Construction Company | 3. County Contractors, Inc. |
|---|---|---|---|---|---|---|
| 1 | R&R int tower insp LT (X0323631) | EACH | 12 | $4,404.28 | $4,652.89 | $4,325.00 |
| 2 | Rem repl exhaust fan (X0323633) | EACH | 4 | $12,191 | $12,879 | $11,950 |
| 3 | Remove luminaire, complete (X1400398) | EACH | 19 | $456.88 | $482.66 | $450.00 |
| 4 | BR deck grooving long (X5030250) | SY | 12,004 | $9.59 | $10.42 | $7.25 |
| 5 | Drainage scuppers adj (X5230172) | EACH | 50 | $839.67 | $2,169.77 | $1,450.00 |
| 6 | Traf cont & prot SPL (X7010216) | LS | 1 | $151,616 | $154,428 | $250,000 |
| 7 | Width restrict sign (X7200201) | LS | 1 | $8,949.38 | $18,066 | $9,000.00 |
| 8 | Detour signing (X7200203) | LS | 1 | $9,648.13 | $12,752 | $9,500.00 |
| 9 | Diamond grind BR sec (Z0029090) | SY | 14,005 | $11.98 | $13.01 | $10.75 |
| 10 | JT sealing (patches) (Z0032500) | LF | 64 | $14.49 | $6.39 | $15.00 |
| 11 | Modular expan JT 9 (Z0034393) | LF | 136 | $3,143.77 | $5,129.83 | $6,500.00 |
| 12 | Modular exp JT-SW 6 (Z0034806) | LF | 34 | $4,782.05 | $4,090.69 | $6,000.00 |
| 13 | Modular exp JT-SW 18 (Z0034818) | LF | 34 | $5,556.32 | $10,806 | $12,500 |
| 14 | RR prot liability ins (Z0048665) | LS | 1 | $7,787.72 | $9,760.95 | $20,000 |
| 15 | Trainees (Z0076600) | HR | 4,000 | $0.80 | $0.80 | $0.80 |
| 16 | Trainees TPG (Z0076604) | HR | 4,000 | $15.00 | $15.00 | $15.00 |
| 17 | Paved SHLD removal (44004250) | SY | 55 | $94.02 | $270.27 | $80.00 |
| 18 | PCC shoulders 8 (48300300) | SY | 55 | $232.51 | $200.70 | $250.00 |
| 19 | Conc rem (50102400) | CY | 84.80 | $3,546.84 | $3,681.73 | $8,000.00 |
| 20 | Protective shield (50157300) | SY | 253 | $214.21 | $1.00 | $120.00 |
| 21 | Conc sup-STR (50300255) | CY | 84.30 | $4,360.17 | $4,225.01 | $8,000.00 |
| 22 | Protective coat (50300300) | SY | 16,038 | $4.36 | $2.52 | $4.00 |
| 23 | Stud shear connectors (50500505) | EACH | 74 | $27.20 | $85.61 | $55.00 |
| 24 | Reinf bars, epoxy CTD (50800205) | LB | 17,080 | $2.36 | $6.14 | $4.50 |
| 25 | Bar splicers (50800515) | EACH | 173 | $49.01 | $63.63 | $75.00 |
| 26 | Mechanical splicers (50800530) | EACH | 720 | $68.19 | $79.17 | $100.00 |
| 27 | BR deck scar 3/4 (53101002) | SY | 9,543 | $56.01 | $50.94 | $110.00 |
| 28 | BR deck scar 2 1/4 (53101008) | SY | 6,309 | $68.87 | $58.92 | $115.00 |
| 29 | BR DK mic C ovl 2 1/2 (53101609) | SY | 6,309 | $151.91 | $184.62 | $150.00 |
| 30 | BR DK mic C ovl 2 3/4 (53101610) | SY | 9,543 | $155.53 | $185.28 | $155.00 |
| 31 | Engr field office A (67000400) | CAL MO | 12 | $3,900.24 | $4,130.07 | $3,500.00 |
| 32 | Mobilization (67100100) | LS | 1 | $398,242 | $503,767 | $560,000 |
| 33 | Traf cont-prot 701201 (70100450) | LS | 1 | $16,069 | $304,111 | $2,500.00 |
| 34 | Changeable message SN (70107025) | CAL DAY | 732 | $45.69 | $74.58 | $45.00 |
| 35 | Short term pavt mking (70300100) | LF | 472 | $1.96 | $3.46 | $5.00 |
| 36 | SHRT TRM pavt MK rem (70300150) | SF | 157 | $1.75 | $3.66 | $10.00 |
| 37 | Temp conc barrier (70400100) | LF | 4,637.50 | $35.21 | $64.92 | $35.00 |
| 38 | Rel temp conc barrier (70400200) | LF | 4,637.50 | $5.11 | $10.97 | $5.00 |
| 39 | Imp attn temp NRN TL2 (70600241) | EACH | 4 | $7,229.38 | $10,544 | $7,100.00 |
| 40 | Imp attn rel NRN TL2 (70600341) | EACH | 4 | $591.25 | $1,814.95 | $595.00 |
| 41 | Mod ureth PM line 5 (78009005) | LF | 10,826 | $1.88 | $2.06 | $1.85 |
| 42 | PVT MKG rem WTR blast (78300202) | SF | 10,826 | $0.59 | $0.65 | $0.60 |
| 43 | Con at ST 3/4 galvs (81100200) | LF | 60 | $91.75 | $96.93 | $90.00 |
| 44 | Con at ST 1 1/4 galvs (81100400) | LF | 125 | $110.19 | $116.41 | $108.00 |
| 45 | Jun BX SS as 8X8X6 (81300320) | EACH | 28 | $2,189.78 | $2,313.38 | $2,150.00 |
| 46 | Jun BX SS as 10X8X6 (81300420) | EACH | 19 | $2,297.28 | $2,426.95 | $2,250.00 |
| 47 | EC C XLP use 1C 12 (81702100) | LF | 1,938 | $5.91 | $6.25 | $5.80 |
| 48 | EC C XLP use 1C 6 (81702130) | LF | 958 | $11.29 | $11.92 | $11.00 |
| 49 | Lum LED rdwy G (82110007) | EACH | 19 | $1,290.00 | $1,362.82 | $1,265.00 |
| 50 | Wwowl LED 180 D R (82200608) | EACH | 8 | $7,386.33 | $7,803.27 | $7,250.00 |
| 51 | Wwowl LED 360 D G (82200609) | EACH | 4 | $7,386.33 | $7,803.27 | $7,250.00 |
| 52 | Avtn obs warn lum LED (82200705) | EACH | 4 | $39,544 | $41,776 | $38,805 |
| 53 | Rem obs WL unit (84301101) | EACH | 4 | $3,472.25 | $6,507.46 | $6,050.00 |
| 54 | Rem obs WLS (84301201) | LS | 1 | $11,739 | $26,030 | $24,175 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of September 18, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.