IDOT contract 72E59 bid tabulation
Section (54-10HB-2)BDR,BP,BRR,BJR. Let by Illinois DOT on September 18, 2026, Logan, District 06. 4 bids received; low bid $1,485,400 by Otto Baum Company, Inc..
- Owner
- Illinois DOT
- Letting
- 18 SEP 2026
- Pay items
- 53
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Otto Baum Company, Inc. | $1,485,400 | Low |
| 2 | Sangamo Construction Company | $1,573,388 | +6.0% |
| 3 | Stark Excavating, Inc. | $1,591,249 | +7.0% |
| 4 | Freesen, a div of UCM, Inc. | $1,698,553 | +14% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Otto Baum Company, Inc. | 2. Sangamo Construction Company | 3. Stark Excavating, Inc. | 4. Freesen, a div of UCM, Inc. |
|---|---|---|---|---|---|---|---|
| 1 | C&D N-lead PT C RS N1 (X5060601) | LS | 1 | $1,072.56 | $1,083.70 | $150,000 | $149,347 |
| 2 | Drainage scuppers adj (X5230172) | EACH | 4 | $1,906.57 | $3,517.03 | $1,450.00 | $1,385.73 |
| 3 | Pipe drain removal (X6010003) | LF | 216 | $20.43 | $22.50 | $8.00 | $42.19 |
| 4 | Fill EX storm sewers (X6050205) | CY | 3.20 | $514.03 | $1,155.26 | $0.01 | $813.55 |
| 5 | Traf cont-prot BLR 21 (X7011800) | LS | 1 | $2,949.54 | $4,322.84 | $6,500.00 | $2,887.50 |
| 6 | Clean & PT STL BR N1 (Z0010501) | LS | 1 | $348,582 | $352,203 | $230,000 | $228,748 |
| 7 | Polymer concrete (Z0041895) | CF | 7 | $945.84 | $1,344.49 | $1,550.00 | $2,724.68 |
| 8 | Trainees (Z0076600) | HR | 1,000 | $0.80 | $0.80 | $0.80 | $0.80 |
| 9 | Trainees TPG (Z0076604) | HR | 1,000 | $15.00 | $15.00 | $15.00 | $15.00 |
| 10 | Seeding CL 2 (25000200) | ACRE | 0.10 | $16,732 | $16,906 | $16,250 | $16,380 |
| 11 | Nitrogen fert nutr (25000400) | LB | 9 | $10.73 | $10.84 | $10.00 | $10.50 |
| 12 | Phosphorus fert nutr (25000500) | LB | 9 | $10.73 | $10.84 | $10.00 | $10.50 |
| 13 | Potassium fert nutr (25000600) | LB | 9 | $10.73 | $10.84 | $10.00 | $10.50 |
| 14 | Agr ground limestone (25000700) | TON | 0.20 | $536.25 | $541.85 | $500.00 | $525.00 |
| 15 | Mulch method 2 (25100115) | ACRE | 0.10 | $16,732 | $16,906 | $16,250 | $16,380 |
| 16 | Stone dump rip CL A3 (28100805) | TON | 15 | $184.46 | $207.08 | $165.00 | $473.32 |
| 17 | Bit matls tack CT (40600290) | LB | 60 | $20.21 | $1.12 | $20.00 | $1.13 |
| 18 | HMA surf rem butt JT (40600982) | SY | 1,196 | $16.72 | $16.59 | $15.75 | $13.86 |
| 19 | HMA SC IL-9.5 C N50 (40604050) | TON | 117 | $264.75 | $288.21 | $260.00 | $380.03 |
| 20 | Median removal (44003100) | SF | 1,200 | $5.47 | $12.04 | $10.00 | $18.08 |
| 21 | Paved SHLD removal (44004250) | SY | 48 | $42.09 | $71.75 | $75.00 | $156.15 |
| 22 | Agg wedge SHLD type B (48102100) | TON | 15 | $117.03 | $115.84 | $215.00 | $209.01 |
| 23 | Conc rem (50102400) | CY | 27.30 | $2,599.03 | $2,544.25 | $3,785.00 | $4,355.18 |
| 24 | Protective shield (50157300) | SY | 542 | $117.64 | $144.26 | $85.00 | $127.94 |
| 25 | Conc struct (50300225) | CY | 6.90 | $1,998.53 | $1,570.19 | $1,750.00 | $3,698.04 |
| 26 | Conc sup-STR (50300255) | CY | 34.60 | $2,291.45 | $2,587.29 | $2,995.00 | $3,531.05 |
| 27 | BR deck grooving (50300260) | SY | 1,407 | $12.99 | $9.29 | $13.00 | $11.29 |
| 28 | Protective coat (50300300) | SY | 1,650 | $3.09 | $3.81 | $3.50 | $3.94 |
| 29 | Reinf bars, epoxy CTD (50800205) | LB | 6,290 | $3.45 | $3.55 | $3.75 | $4.20 |
| 30 | Pref JT strip seal (52000110) | LF | 128 | $214.62 | $327.67 | $250.00 | $270.80 |
| 31 | Deck slab rep (FD-T2) (53016002) | SY | 52 | $1,301.92 | $1,226.63 | $1,750.00 | $1,620.08 |
| 32 | BR deck scar 3/4 (53101002) | SY | 1,470 | $55.40 | $50.51 | $51.50 | $59.99 |
| 33 | BR DK mic C ovl 2 1/2 (53101609) | SY | 1,466 | $165.95 | $127.83 | $132.00 | $170.00 |
| 34 | Metal FL end sec 12" (54262712) | EACH | 4 | $745.71 | $466.45 | $550.00 | $912.05 |
| 35 | Pipe drains 12 (60100945) | LF | 440 | $39.41 | $35.11 | $62.00 | $41.56 |
| 36 | Remov inlets (60500060) | EACH | 4 | $551.74 | $1,244.94 | $500.00 | $818.94 |
| 37 | Conc med TSB6.12 (60619600) | SF | 1,200 | $22.57 | $33.61 | $35.00 | $51.06 |
| 38 | Conc thrust blocks (61000050) | EACH | 4 | $1,265.81 | $1,229.33 | $875.00 | $793.02 |
| 39 | TY E inlet box 610001 (61000115) | EACH | 4 | $4,789.92 | $9,809.14 | $7,000.00 | $5,107.09 |
| 40 | Conc SHLD curb (66201120) | LF | 48 | $122.58 | $48.61 | $40.00 | $246.23 |
| 41 | Engr field office A (67000400) | CAL MO | 6 | $1,672.43 | $3,070.02 | $2,300.00 | $4,116.39 |
| 42 | Mobilization (67100100) | LS | 1 | $116,691 | $92,830 | $95,000 | $41,636 |
| 43 | Traf cont-prot 701402 (70100207) | EACH | 2 | $13,407 | $37,089 | $28,000 | $16,505 |
| 44 | Traf cont-prot 701411 (70100420) | EACH | 2 | $804.42 | $1,652.65 | $1,000.00 | $787.50 |
| 45 | Traf cont-prot 701401 (70100800) | LS | 1 | $4,504.75 | $44,233 | $22,500 | $12,362 |
| 46 | Changeable message SN (70107025) | CAL DAY | 270 | $69.72 | $59.60 | $75.00 | $68.25 |
| 47 | Temp conc barrier (70400100) | LF | 600 | $67.94 | $54.14 | $50.00 | $55.39 |
| 48 | Rel temp conc barrier (70400200) | LF | 600 | $16.09 | $10.40 | $15.00 | $8.14 |
| 49 | Imp attn temp FRN TL3 (70600260) | EACH | 2 | $8,710.50 | $11,686 | $10,500 | $8,531.25 |
| 50 | Imp attn rel FRN TL3 (70600332) | EACH | 2 | $1,846.12 | $2,394.19 | $4,000.00 | $1,995.00 |
| 51 | PT PVT MK LTRS & symb (78001100) | SF | 17.60 | $26.81 | $14.36 | $37.00 | $13.91 |
| 52 | Paint PVT MK line 5 (78001120) | LF | 2,000 | $1.61 | $2.44 | $2.10 | $2.36 |
| 53 | Curb reflectors (78200020) | EACH | 40 | $36.94 | $13.55 | $23.00 | $61.21 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of September 18, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.