IDOT contract 78A79 bid tabulation

Section (97-2)R-1. Let by Illinois DOT on January 16, 2026, White, District 09. 3 bids received; low bid $5,633,260 by E. T. Simonds Construction Company.

Owner
Illinois DOT
Letting
16 JAN 2026
Pay items
56
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1E. T. Simonds Construction Company$5,633,260Low
2Samron Midwest Contracting, Inc.$5,954,553+6.0%
3Kieffer Bros. Construction Co., Inc.$9,586,060+70%
IDOT contract 78A79: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. E. T. Simonds Construction Company2. Samron Midwest Contracting, Inc.3. Kieffer Bros. Construction Co., Inc.
1Mowing (X2503100)UNIT134$24.00$20.00$212.00
2Prof DMD GRND con PVT (X4202010)SY15,476$9.91$10.00$8.89
3Temp pavt removal (X4400110)SY4,106$13.21$11.00$30.53
4Island removal (X4402805)SF1,358$4.13$5.00$15.26
5Traf cont & prot SPL (X7010216)LS1$98,558$75,000$95,400
6Detour signing (X7200203)LS1$27,225$14,000$64,660
7Construction layout (Z0013798)LS1$43,573$25,000$101,866
8Temp pavement (Z0062456)SY4,106$69.25$75.00$160.27
9Earth excavation (20200100)CY6,867$16.28$27.00$28.20
10Furnished excavation (20400800)CY1,449$32.70$24.00$32.86
11Seeding CL 2A (25000210)ACRE0.43$7,672.51$6,000.00$16,536
12Seeding CL 7 (25000350)ACRE0.43$704.65$10,000$16,536
13Nitrogen fert nutr (25000400)LB41$1.82$2.00$14.10
14Phosphorus fert nutr (25000500)LB41$1.82$2.00$14.10
15Potassium fert nutr (25000600)LB41$1.82$2.00$14.10
16Agr ground limestone (25000700)TON0.86$385.00$1,000.00$5,946.60
17Mulch method 2 (25100115)ACRE0.43$5,472.51$8,000.00$9,381.00
18Agg subgrade impr 12 (30300112)SY28,864$27.71$21.00$52.10
19Sub gran mat C (31102000)CY454$104.13$75.00$93.70
20Stab subbase 4 (31200100)SY18,047$25.53$34.00$29.77
21PCC PVT 9 1/2 jointd (42000411)SY16,976$104.31$100.00$170.77
22Protective coat (42001300)SY24,127$1.11$2.00$0.38
23Pavement rem (44000100)SY15,405$13.55$15.00$30.53
24Curb rem (44000300)LF3,608$20.04$17.00$15.58
25Paved SHLD removal (44004250)SY6,647$10.01$15.00$30.53
26Dowel bars 1 1/4 (44201298)EACH134$31.71$30.00$30.95
27Agg wedge SHLD type B (48102100)TON150$90.97$80.00$67.31
28PCC shoulders 9 1/2 (48300410)SY6,791$98.55$119.00$160.27
29Comb CC&G TB6.06 (60603500)LF3,238$59.69$55.00$61.37
30Comb CC&G TM4.06 (60608552)LF2,410$56.60$85.00$61.37
31Comb CC&G TM4.24 (60608582)LF467$73.45$65.00$77.70
32SPBGR TY A 6FT posts (63000001)LF625$35.97$32.00$48.16
33TR bar TRM T1 SPL tan (63100167)EACH4$4,202.00$5,800.00$5,784.02
34Guardrail remov (63200310)LF512$8.97$8.00$16.76
35Engr field office A (67000400)CAL MO6$2,000.00$2,000.00$3,180.00
36Mobilization (67100100)LS1$181,230$352,000$465,552
37Traf cont-prot 701201 (70100450)LS1$0.01$8,000.00$159,350
38Traf cont-prot 701451 (70100820)LS1$9,807.74$5,000.00$37,630
39TR cont surveillance (70103815)CAL DAY30$0.01$0.01$2,385.00
40Changeable message SN (70107025)CAL DAY28$87.26$90.00$145.75
41Short term pavt mking (70300100)LF408$0.99$2.00$11.34
42SHRT TRM pavt MK rem (70300150)SF141$17.00$3.00$13.67
43Temp PVT MK LTR & sym paint (70300211)SF135.20$0.01$0.01$4.66
44Temp PVT MK line 4 - paint (70300221)LF7,983$0.01$0.01$0.55
45Temp PVT MK line 24 - paint (70300281)LF98$0.01$0.01$5.25
46Terminal marker - DA (72501000)EACH4$55.00$55.00$30.71
47Teles STL sin support (72800100)LF55$13.75$25.00$94.97
48Base tel STL sin supp (73100100)EACH4$129.88$500.00$1,159.45
49Mod ureth PM LTR-sym (78009000)SF135.20$6.05$6.50$6.41
50Mod ureth PM line 4 (78009004)LF7,983$2.00$2.00$2.12
51Mod ureth PM line 24 (78009024)LF98$11.00$12.00$11.66
52GRV RCSD PM LTR & sym (78011000)SF135.20$4.40$4.80$4.66
53GRV RCSD PVT MRKG 5 (78011025)LF7,983$1.45$1.40$1.54
54GRV RCSD PVT MRKG 25 (78011125)LF98$6.60$7.00$7.00
55Grdrail ref type B (78200006)EACH8$16.50$12.00$23.03
56PVT MKG rem grinding (78300201)SF3,002$2.93$0.01$2.33
IDOT contract 78A79: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of January 16, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy