IDOT contract 78A89 bid tabulation
Section D9. Let by Illinois DOT on April 25, 2025, Gallatin, District 09. 2 bids received; low bid $5,244,108 by E. T. Simonds Construction Company.
- Owner
- Illinois DOT
- Letting
- 25 APR 2025
- Pay items
- 47
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | E. T. Simonds Construction Company | $5,244,108 | Low |
| 2 | Samron Midwest Contracting, Inc. | $7,144,653 | +36% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. E. T. Simonds Construction Company | 2. Samron Midwest Contracting, Inc. |
|---|---|---|---|---|---|
| 1 | PC conc sidewalk 4 SP (X4240420) | SF | 1,059 | $28.15 | $25.00 |
| 2 | HMA surf rem var DP (X4401198) | SY | 1,294 | $6.34 | $5.00 |
| 3 | Part dep rem T1 2 (X4406020) | SY | 14 | $190.00 | $150.00 |
| 4 | Part dep rem T2 2 (X4406220) | SY | 22 | $185.00 | $150.00 |
| 5 | Part dep rem T3 2 (X4406420) | SY | 50 | $180.00 | $150.00 |
| 6 | PCC surf rem 1/2 (X4406804) | SY | 10,595 | $1.64 | $10.00 |
| 7 | Partial depth patch (X4421000) | TON | 9.60 | $1,439.23 | $500.00 |
| 8 | Bit matls tack CT (40600290) | LB | 155,959 | $0.01 | $0.01 |
| 9 | Long joint sealant (40600370) | LF | 76,158 | $2.58 | $3.00 |
| 10 | Matl transfer device (40600405) | TON | 31,563 | $2.69 | $3.00 |
| 11 | HMA surf rem butt JT (40600982) | SY | 1,309 | $23.90 | $15.00 |
| 12 | Temporary ramp (40600990) | SY | 1,235 | $19.40 | $25.00 |
| 13 | HMA BC IL-9.5FG N70 (40602970) | TON | 14,500 | $91.08 | $115.00 |
| 14 | HMA SC IL-9.5 C N70 (40604052) | TON | 17,071 | $85.62 | $115.00 |
| 15 | Incidental HMA surf (40800050) | TON | 166 | $245.73 | $400.00 |
| 16 | Welded wire reinf (42000060) | SY | 312 | $10.76 | $10.00 |
| 17 | Protective coat (42001300) | SY | 23 | $0.01 | $0.01 |
| 18 | Detectable warnings (42400800) | SF | 141 | $18.45 | $35.00 |
| 19 | HMA surf rem 1 1/2 (44000155) | SY | 210,993 | $0.98 | $2.25 |
| 20 | HMA surf rem 2 3/4 (44000160) | SY | 8,805 | $1.90 | $3.50 |
| 21 | HMA surf rem 3 (44000161) | SY | 11,196 | $2.23 | $5.00 |
| 22 | Gutter rem (44000400) | LF | 89 | $39.88 | $15.00 |
| 23 | Sidewalk rem (44000600) | SF | 962 | $10.10 | $15.00 |
| 24 | CL C patch T1 12 (44201373) | SY | 132 | $192.00 | $300.00 |
| 25 | CL C patch T2 12 (44201377) | SY | 180 | $189.00 | $275.00 |
| 26 | CL C patch T2 15 (44201415) | SY | 1,864 | $214.00 | $250.00 |
| 27 | CL C patch T3 15 (44201419) | SY | 32 | $212.00 | $300.00 |
| 28 | CL C patch T4 15 (44201421) | SY | 58 | $209.00 | $275.00 |
| 29 | Agg wedge SHLD type B (48102100) | TON | 1,634 | $46.43 | $35.00 |
| 30 | HMA shoulders (48203100) | TON | 6,399 | $87.45 | $115.00 |
| 31 | Class SI conc outlet (60600095) | CY | 4.50 | $1,655.62 | $1,500.00 |
| 32 | Concrete gutter TY A (60602500) | LF | 98 | $81.07 | $75.00 |
| 33 | Engr field office A (67000400) | CAL MO | 6 | $2,200.00 | $3,000.00 |
| 34 | Mobilization (67100100) | LS | 1 | $353,378 | $400,000 |
| 35 | Traf cont-prot 701201 (70100450) | LS | 1 | $0.01 | $200,000 |
| 36 | Traf cont-prot 701306 (70100460) | LS | 1 | $111,790 | $100,000 |
| 37 | Traf cont-prot 701336 (70100600) | LS | 1 | $41,107 | $0.01 |
| 38 | TR cont & prot 701501 (70102620) | LS | 1 | $10,349 | $0.01 |
| 39 | TR cont & prot 701801 (70102640) | LS | 1 | $0.01 | $0.01 |
| 40 | Changeable message SN (70107025) | CAL DAY | 56 | $40.13 | $125.00 |
| 41 | Short term pavt mking (70300100) | LF | 56,820 | $0.01 | $1.50 |
| 42 | SHRT TRM pavt MK rem (70300150) | SF | 18,940 | $0.01 | $2.50 |
| 43 | Temp PVT MK line 4 - paint (70300221) | LF | 185,958 | $0.01 | $0.01 |
| 44 | Paint PVT MK line 4 (78001110) | LF | 185,958 | $0.13 | $0.15 |
| 45 | Raised refl pavt MKR (78100100) | EACH | 927 | $39.69 | $45.00 |
| 46 | Raised ref PVT MK rem (78300200) | EACH | 861 | $6.87 | $15.00 |
| 47 | PVT MKG rem grinding (78300201) | SF | 61,986 | $0.01 | $0.01 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of April 25, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.