IDOT contract 78B55 bid tabulation
Section (12,12-2)R-1,RS-3. Let by Illinois DOT on September 18, 2026, Jackson, District 09. 2 bids received; low bid $2,308,150 by Samron Midwest Contracting, Inc..
- Owner
- Illinois DOT
- Letting
- 18 SEP 2026
- Pay items
- 134
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Samron Midwest Contracting, Inc. | $2,308,150 | Low |
| 2 | E. T. Simonds Construction Company | $3,141,516 | +36% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Samron Midwest Contracting, Inc. | 2. E. T. Simonds Construction Company |
|---|---|---|---|---|---|
| 1 | Prof DMD GRND con PVT (X4202010) | SY | 3,653 | $14.00 | $15.57 |
| 2 | PC conc sidewalk 4 SP (X4240420) | SF | 469 | $11.00 | $40.89 |
| 3 | HMA surf rem var DP (X4401198) | SY | 63 | $6.50 | $18.09 |
| 4 | Island removal (X4402805) | SF | 146 | $6.15 | $13.33 |
| 5 | STR refl CR CTRL TRTMT (X4430200) | LF | 10,099 | $2.75 | $1.37 |
| 6 | Area ref CR CTRL TRMT (X4430201) | SY | 4,163 | $5.00 | $5.17 |
| 7 | Traf cont & prot SPL (X7010216) | LS | 1 | $5,000.00 | $10,828 |
| 8 | Detour signing (X7200203) | LS | 1 | $7,500.00 | $20,420 |
| 9 | Construction layout (Z0013798) | LS | 1 | $22,400 | $52,989 |
| 10 | Earth excavation (20200100) | CY | 2,006 | $22.00 | $50.00 |
| 11 | Trench backfill (20800150) | CY | 35 | $57.00 | $111.11 |
| 12 | Seeding CL 1B (25000115) | ACRE | 0.80 | $4,200.00 | $11,111 |
| 13 | Seeding CL 7 (25000350) | ACRE | 0.80 | $785.00 | $8,888.90 |
| 14 | Nitrogen fert nutr (25000400) | LB | 72 | $2.00 | $4.44 |
| 15 | Phosphorus fert nutr (25000500) | LB | 72 | $2.00 | $4.44 |
| 16 | Potassium fert nutr (25000600) | LB | 72 | $2.00 | $4.44 |
| 17 | Agr ground limestone (25000700) | TON | 1.60 | $395.00 | $388.89 |
| 18 | Mulch method 2 (25100115) | ACRE | 0.80 | $3,900.00 | $11,111 |
| 19 | Erosion contr blanket (25100630) | SY | 105 | $2.50 | $11.11 |
| 20 | Temp eros contr seed (28000250) | LB | 80 | $4.50 | $27.78 |
| 21 | Temp ditch checks (28000305) | LF | 24 | $16.00 | $94.44 |
| 22 | Perimeter eros bar (28000400) | LF | 627 | $3.75 | $8.89 |
| 23 | Inlet & pipe protect (28000500) | EACH | 11 | $200.00 | $388.89 |
| 24 | Stone riprap CL A4 (28100107) | SY | 43 | $70.00 | $133.33 |
| 25 | Filter fabric (28200200) | SY | 43 | $1.50 | $1.11 |
| 26 | Agg subgrade impr 12 (30300112) | SY | 4,750 | $19.00 | $28.89 |
| 27 | Sub gran mat C (31101900) | TON | 42 | $28.00 | $111.11 |
| 28 | Stab subbase 4 (31200100) | SY | 4,750 | $22.00 | $28.21 |
| 29 | Agg surf cse A 6 (40200500) | SY | 13 | $25.00 | $111.11 |
| 30 | Bit matls PR CT (40600275) | LB | 10,692 | $0.01 | $0.01 |
| 31 | Bit matls tack CT (40600290) | LB | 16,118 | $0.01 | $0.01 |
| 32 | Long joint sealant (40600370) | LF | 11,229 | $4.25 | $4.88 |
| 33 | Matl transfer device (40600405) | TON | 3,585 | $2.00 | $5.61 |
| 34 | Temporary ramp (40600990) | SY | 771 | $15.00 | $35.80 |
| 35 | HMA BC IL-9.5FG N70 (40602970) | TON | 1,671 | $108.00 | $107.70 |
| 36 | HMA SC IL-9.5 C N70 (40604052) | TON | 1,914 | $100.00 | $106.17 |
| 37 | Incidental HMA surf (40800050) | TON | 21 | $650.00 | $367.76 |
| 38 | PCC PVT 9 jointed (42000401) | SY | 3,653 | $90.00 | $120.45 |
| 39 | Protective coat (42001300) | SY | 4,501 | $1.25 | $2.56 |
| 40 | PCC driveway pavt 7 (42300300) | SY | 30 | $170.00 | $249.90 |
| 41 | PC conc sidewalk 4 (42400100) | SF | 4,922 | $10.00 | $11.99 |
| 42 | Detectable warnings (42400800) | SF | 130 | $40.00 | $45.79 |
| 43 | Pavement rem (44000100) | SY | 3,469 | $13.00 | $38.52 |
| 44 | HMA surf rem 2 1/2 (44000159) | SY | 4,163 | $4.00 | $4.81 |
| 45 | HMA surf rem 2 3/4 (44000160) | SY | 14,627 | $2.50 | $3.66 |
| 46 | HMA surf rem 3 (44000161) | SY | 5,053 | $3.75 | $4.54 |
| 47 | Comb curb gutter rem (44000500) | LF | 809 | $10.00 | $18.89 |
| 48 | Sidewalk rem (44000600) | SF | 4,779 | $4.00 | $2.22 |
| 49 | Paved SHLD removal (44004250) | SY | 125 | $15.00 | $27.78 |
| 50 | Dowel bars 1 1/4 (44201298) | EACH | 92 | $30.00 | $29.39 |
| 51 | Dowel bars 1 1/2 (44201299) | EACH | 30 | $32.00 | $31.91 |
| 52 | CL C patch T1 12 (44201373) | SY | 4 | $195.00 | $260.00 |
| 53 | CL C patch T2 12 (44201377) | SY | 245 | $190.00 | $250.00 |
| 54 | CL C patch T3 12 (44201381) | SY | 154 | $185.00 | $245.00 |
| 55 | CL C patch T4 12 (44201383) | SY | 227 | $180.00 | $230.00 |
| 56 | CL C patch T1 14 (44201398) | SY | 26 | $220.00 | $290.00 |
| 57 | CL C patch T2 14 (44201403) | SY | 313 | $218.00 | $268.00 |
| 58 | CL C patch T3 14 (44201407) | SY | 55 | $210.00 | $261.00 |
| 59 | CL C patch T4 14 (44201409) | SY | 28 | $185.00 | $257.00 |
| 60 | CL C patch T1 15 (44201411) | SY | 8 | $200.00 | $260.00 |
| 61 | CL C patch T2 15 (44201415) | SY | 332 | $195.00 | $250.00 |
| 62 | CL C patch T3 15 (44201419) | SY | 41 | $190.00 | $240.00 |
| 63 | CL C patch T4 15 (44201421) | SY | 318 | $185.00 | $230.00 |
| 64 | Tie bars 3/4 (44213204) | EACH | 195 | $17.00 | $4.39 |
| 65 | Agg wedge SHLD type B (48102100) | TON | 11 | $56.00 | $87.26 |
| 66 | HMA shoulders (48203100) | TON | 163 | $95.00 | $124.76 |
| 67 | PCC shoulders 9 (48300400) | SY | 626 | $54.00 | $142.03 |
| 68 | Conc headwall removal (50104400) | EACH | 4 | $350.00 | $2,222.22 |
| 69 | Pipe culvert remov (50105220) | LF | 84 | $8.00 | $18.89 |
| 70 | Bicycle railing (50901720) | LF | 110 | $350.00 | $217.80 |
| 71 | PRC flar end sec 12 (54213657) | EACH | 2 | $200.00 | $2,777.78 |
| 72 | PRC flar end sec 18 (54213663) | EACH | 2 | $2,300.00 | $3,888.89 |
| 73 | PRC flar end sec 24 (54213669) | EACH | 3 | $2,600.00 | $4,444.44 |
| 74 | Storm sew CL A 1 12 (550A0050) | LF | 55 | $64.00 | $111.11 |
| 75 | Storm sew CL A 1 18 (550A0090) | LF | 40 | $95.00 | $127.78 |
| 76 | Storm sew CL A 1 24 (550A0120) | LF | 30 | $130.00 | $138.89 |
| 77 | Storm sew CL A 2 24 (550A0410) | LF | 131 | $89.00 | $138.89 |
| 78 | Storm sewer rem 12 (55100500) | LF | 55 | $10.00 | $20.00 |
| 79 | Storm sewer rem 24 (55101200) | LF | 79 | $12.00 | $27.78 |
| 80 | Water valves adjust (56109210) | EACH | 3 | $250.00 | $388.89 |
| 81 | Man TA 4 dia T1F CL (60218400) | EACH | 1 | $3,200.00 | $5,833.33 |
| 82 | Man TA 4 dia T3F&G (60218500) | EACH | 2 | $3,500.00 | $5,944.45 |
| 83 | Man TA 6 dia T1F CL (60223800) | EACH | 1 | $5,100.00 | $6,944.44 |
| 84 | Inlets TA T8G (60236200) | EACH | 1 | $2,600.00 | $5,000.00 |
| 85 | Man adjust (60255500) | EACH | 2 | $250.00 | $2,222.22 |
| 86 | Remov catch bas (60500050) | EACH | 1 | $450.00 | $4,166.67 |
| 87 | Remov inlets (60500060) | EACH | 2 | $500.00 | $2,222.22 |
| 88 | Comb CC&G TB6.12 (60603800) | LF | 55 | $115.00 | $100.81 |
| 89 | Comb CC&G TY B-6.24 (60605000) | LF | 701 | $55.00 | $71.02 |
| 90 | Comb CC&G TM6.06 (60608600) | LF | 56 | $60.00 | $95.48 |
| 91 | Conc median surf 4 (60618300) | SF | 81 | $30.00 | $72.45 |
| 92 | Engr field office A (67000400) | CAL MO | 4 | $1,900.00 | $2,250.00 |
| 93 | Mobilization (67100100) | LS | 1 | $138,000 | $191,135 |
| 94 | TR cont & prot 701501 (70102620) | LS | 1 | $48,000 | $64,063 |
| 95 | TR cont & prot 701502 (70102622) | LS | 1 | $12,000 | $20,984 |
| 96 | TR cont & prot 701701 (70102635) | LS | 1 | $500.00 | $2,568.50 |
| 97 | TR cont & prot 701801 (70102640) | LS | 1 | $500.00 | $2,032.80 |
| 98 | Changeable message SN (70107025) | CAL DAY | 306 | $70.00 | $53.38 |
| 99 | Short term pavt mking (70300100) | LF | 6,639 | $1.85 | $0.01 |
| 100 | SHRT TRM pavt MK rem (70300150) | SF | 2,213 | $2.50 | $0.01 |
| 101 | Temp PVT MK LTR & sym paint (70300211) | SF | 557 | $0.01 | $0.01 |
| 102 | Temp PVT MK line 4 - paint (70300221) | LF | 25,469 | $0.01 | $0.01 |
| 103 | Temp PVT MK line 6 - paint (70300241) | LF | 153 | $0.01 | $0.01 |
| 104 | Temp PVT MK line 12 - paint (70300261) | LF | 640 | $0.01 | $0.01 |
| 105 | Temp PVT MK line 24 - paint (70300281) | LF | 85 | $0.01 | $0.01 |
| 106 | Sign panel T1 (72000100) | SF | 75 | $30.00 | $110.86 |
| 107 | Teles STL sin support (72800100) | LF | 33 | $41.00 | $39.25 |
| 108 | Wood sin support (73000100) | LF | 63 | $61.00 | $30.34 |
| 109 | PT PVT MK LTRS & symb (78001100) | SF | 506 | $15.00 | $5.57 |
| 110 | Paint PVT MK line 4 (78001110) | LF | 22,249 | $0.35 | $1.56 |
| 111 | Paint PVT MK line 12 (78001150) | LF | 283 | $13.30 | $3.34 |
| 112 | Paint PVT MK line 24 (78001180) | LF | 24 | $15.50 | $6.68 |
| 113 | Mod ureth PM LTR-sym (78009000) | SF | 51 | $50.00 | $27.85 |
| 114 | Mod ureth PM line 4 (78009004) | LF | 3,220 | $4.00 | $6.13 |
| 115 | Mod ureth PM line 6 (78009006) | LF | 153 | $13.00 | $7.80 |
| 116 | Mod ureth PM line 12 (78009012) | LF | 357 | $22.00 | $11.14 |
| 117 | Mod ureth PM line 24 (78009024) | LF | 61 | $32.00 | $27.85 |
| 118 | GRV RCSD PM LTR & sym (78011000) | SF | 51 | $1.00 | $6.68 |
| 119 | GRV RCSD PVT MRKG 5 (78011025) | LF | 3,200 | $0.25 | $5.29 |
| 120 | GRV RCSD PVT MRKG 7 (78011035) | LF | 153 | $0.60 | $5.57 |
| 121 | GRV RCSD PVT MRKG 13 (78011065) | LF | 357 | $0.85 | $7.80 |
| 122 | GRV RCSD PVT MRKG 25 (78011125) | LF | 61 | $1.15 | $8.91 |
| 123 | Raised refl pavt MKR (78100100) | EACH | 239 | $60.00 | $88.75 |
| 124 | Raised ref PVT MK rem (78300200) | EACH | 161 | $14.00 | $14.37 |
| 125 | PVT MKG rem grinding (78300201) | SF | 9,934 | $0.01 | $0.01 |
| 126 | Locate undergr cable (80300100) | LF | 100 | $9.00 | $8.89 |
| 127 | UD 2#10#10GXLPUSE 3/4 (81603010) | LF | 1,500 | $17.00 | $16.80 |
| 128 | Lum LED rdwy H (82110008) | EACH | 2 | $1,500.00 | $1,451.39 |
| 129 | LT P A 45MH 15MA-TW (83009601) | EACH | 1 | $11,000 | $11,214 |
| 130 | LP F M 15BC 8 5/8X6 (83600356) | EACH | 1 | $2,600.00 | $2,659.72 |
| 131 | Bkwy dev TR B 15BC (83800205) | EACH | 1 | $2,200.00 | $2,206.67 |
| 132 | Rem LT unit salv (84200500) | EACH | 1 | $910.00 | $916.66 |
| 133 | Rem pole FDN (84200804) | EACH | 1 | $1,300.00 | $1,250.00 |
| 134 | Rem elcbl FR con (89502300) | LF | 4,500 | $0.75 | $0.66 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of September 18, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.