IDOT contract 80B11 bid tabulation
Section 2025-1099-RS. Let by Illinois DOT on January 16, 2026, Will, District 01. 3 bids received; low bid $1,297,699 by Iroquois Paving Corporation.
- Owner
- Illinois DOT
- Letting
- 16 JAN 2026
- Pay items
- 81
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Iroquois Paving Corporation | $1,297,699 | Low |
| 2 | Gallagher Asphalt Corporation | $1,490,955 | +15% |
| 3 | P. T. Ferro Construction Co. | $1,560,604 | +20% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Iroquois Paving Corporation | 2. Gallagher Asphalt Corporation | 3. P. T. Ferro Construction Co. |
|---|---|---|---|---|---|---|
| 1 | Prun safety/equip CLR (K1004595) | LS | 1 | $3,150.00 | $7,050.00 | $3,000.00 |
| 2 | Constructn layout SPL (X0320050) | LS | 1 | $7,275.00 | $3,000.00 | $25,000 |
| 3 | CC&G RMVL repl < = 10 (X4400501) | LF | 100 | $77.00 | $105.00 | $75.00 |
| 4 | CC&G RMVL repl > 10FT (X4400503) | LF | 100 | $75.00 | $95.00 | $75.00 |
| 5 | SS cleaned 12 (X5537800) | LF | 150 | $10.50 | $3.80 | $1.00 |
| 6 | FR & lids adjust SPL (X6030310) | EACH | 23 | $1,500.00 | $640.00 | $950.00 |
| 7 | Engrs FLD ofc TY A D1 (X6700407) | CAL MO | 12 | $2,750.00 | $540.00 | $1.00 |
| 8 | Temp info signing (X7200061) | SF | 104 | $37.00 | $16.30 | $17.00 |
| 9 | Accessible ped signal (X8760200) | EACH | 8 | $2,175.00 | $2,230.00 | $2,056.18 |
| 10 | Drainage STR cleaned (Z0018500) | EACH | 10 | $475.00 | $460.00 | $550.00 |
| 11 | RE-optimize TR sig sys 1 (Z0033044) | EACH | 1 | $1,740.00 | $1,790.00 | $1,650.00 |
| 12 | Nitrogen fert nutr (20101400) | LB | 49 | $8.25 | $4.00 | $8.00 |
| 13 | Phosphorus fert nutr (20101500) | LB | 49 | $8.25 | $4.00 | $8.00 |
| 14 | Potassium fert nutr (20101600) | LB | 49 | $8.25 | $4.00 | $8.00 |
| 15 | Earth excavation (20200100) | CY | 1,475 | $55.00 | $130.00 | $50.00 |
| 16 | Geotech fab F/GR stab (21001000) | SY | 3,878 | $2.15 | $0.01 | $2.30 |
| 17 | Topsoil F & P 4 (21101615) | SY | 1,067 | $8.25 | $8.80 | $8.00 |
| 18 | Seeding CL 2A (25000210) | ACRE | 0.25 | $6,325.00 | $8,630.00 | $6,000.00 |
| 19 | Supple watering (25200200) | UNIT | 5 | $525.00 | $270.00 | $0.01 |
| 20 | Temp eros contr seed (28000250) | LB | 23 | $21.00 | $10.90 | $0.01 |
| 21 | Perimeter eros bar (28000400) | LF | 249 | $2.95 | $4.90 | $4.50 |
| 22 | Inlet filters (28000510) | EACH | 10 | $250.00 | $150.00 | $235.00 |
| 23 | Agg subgrade improve (30300001) | CY | 83 | $89.75 | $110.00 | $90.00 |
| 24 | Agg subgrade impr 12 (30300112) | SY | 2,514 | $35.00 | $36.00 | $25.00 |
| 25 | Bit matls PR CT (40600275) | LB | 5,666 | $0.01 | $0.01 | $0.01 |
| 26 | Bit matls tack CT (40600290) | LB | 27,497 | $0.01 | $0.01 | $0.01 |
| 27 | Long joint sealant (40600370) | LF | 19,315 | $3.00 | $3.00 | $3.20 |
| 28 | Mix CR JTS flangewys (40600400) | TON | 5 | $0.01 | $950.00 | $1,000.00 |
| 29 | HMA surf rem butt JT (40600982) | SY | 323 | $0.01 | $40.00 | $0.01 |
| 30 | P HMA BC IL-4.75 N50 (40603200) | TON | 1,392 | $103.00 | $114.00 | $110.00 |
| 31 | HMA SC IL-9.5 D N70 (40604062) | TON | 3,366 | $82.00 | $96.00 | $88.00 |
| 32 | Protective coat (42001300) | SY | 52 | $5.50 | $0.01 | $0.01 |
| 33 | PC conc sidewalk 5 (42400200) | SF | 53 | $33.75 | $48.00 | $30.00 |
| 34 | Detectable warnings (42400800) | SF | 11 | $45.00 | $38.00 | $30.00 |
| 35 | Pavement rem (44000100) | SY | 6 | $63.00 | $155.00 | $150.00 |
| 36 | HMA surf rem 1 1/2 (44000155) | SY | 6,337 | $2.50 | $4.00 | $2.70 |
| 37 | HMA surf rem 2 1/4 (44000158) | SY | 33,734 | $1.90 | $2.00 | $2.70 |
| 38 | Sidewalk rem (44000600) | SF | 80 | $8.50 | $23.00 | $10.00 |
| 39 | CL D patch T1 12 (44201785) | SY | 340 | $0.01 | $60.00 | $0.01 |
| 40 | CL D patch T2 12 (44201789) | SY | 340 | $0.01 | $50.00 | $0.01 |
| 41 | CL D patch T3 12 (44201794) | SY | 340 | $30.00 | $40.00 | $50.00 |
| 42 | CL D patch T4 12 (44201796) | SY | 340 | $30.00 | $30.00 | $50.00 |
| 43 | Agg wedge SHLD type B (48102100) | TON | 285 | $34.00 | $44.00 | $50.00 |
| 44 | HMA shoulders 8 (48203029) | SY | 2,518 | $49.00 | $50.00 | $45.00 |
| 45 | Water valves adjust (56109210) | EACH | 7 | $240.00 | $280.00 | $500.00 |
| 46 | CB adjust (60250200) | EACH | 1 | $385.00 | $490.00 | $500.00 |
| 47 | FR & lids adjust (60300305) | EACH | 9 | $350.00 | $350.00 | $500.00 |
| 48 | FR & lids T1 ADA compl OL (60406001) | EACH | 1 | $610.00 | $540.00 | $1,000.00 |
| 49 | Comb CC&G TB6.12 (60603800) | LF | 58 | $76.00 | $64.00 | $100.00 |
| 50 | Box cul to BE cleaned (60905305) | LF | 56 | $79.00 | $6.50 | $110.00 |
| 51 | Non SPL waste disposl (66900200) | CY | 1,475 | $60.00 | $0.01 | $80.00 |
| 52 | Soil disposal analy (66900530) | EACH | 4 | $1,635.00 | $1,575.00 | $1,450.00 |
| 53 | Reg sub P-const plan (66901001) | LS | 1 | $2,425.00 | $3,365.00 | $3,100.00 |
| 54 | Reg sub F con report (66901003) | LS | 1 | $2,425.00 | $1,300.00 | $1,200.00 |
| 55 | Reg sub mon (66901006) | CAL DAY | 10 | $1,160.00 | $738.00 | $680.00 |
| 56 | Mobilization (67100100) | LS | 1 | $17,000 | $89,000 | $80,000 |
| 57 | TR cont & prot 701606 (70102625) | LS | 1 | $18,350 | $6,200.00 | $175,000 |
| 58 | TR cont & prot 701611 (70102634) | LS | 1 | $105.00 | $6,200.00 | $100.00 |
| 59 | TR cont & prot 701701 (70102635) | LS | 1 | $105.00 | $6,200.00 | $4,000.00 |
| 60 | TR cont & prot 701801 (70102640) | LS | 1 | $105.00 | $6,200.00 | $1.00 |
| 61 | TR cont surveillance (70103815) | CAL DAY | 45 | $0.01 | $217.00 | $1.00 |
| 62 | Short term pavt mking (70300100) | LF | 6,669 | $0.01 | $0.01 | $0.01 |
| 63 | SHRT TRM pavt MK rem (70300150) | SF | 8,932 | $0.01 | $0.01 | $0.01 |
| 64 | Temp PVT MK LTR & sym paint (70300211) | SF | 356 | $0.01 | $0.01 | $0.01 |
| 65 | Temp PVT MK line 4 - paint (70300221) | LF | 108,260 | $0.01 | $0.01 | $0.01 |
| 66 | Temp PVT MK line 6 - paint (70300241) | LF | 1,940 | $0.01 | $0.01 | $0.01 |
| 67 | Temp PVT MK line 8 - paint (70300251) | LF | 580 | $0.01 | $0.01 | $0.01 |
| 68 | Temp PVT MK line 12 - paint (70300261) | LF | 4,456 | $0.01 | $0.01 | $0.01 |
| 69 | Temp PVT MK line 24 - paint (70300281) | LF | 1,528 | $0.01 | $0.01 | $0.01 |
| 70 | Temp PVT MK L4 T4 tape (70307120) | LF | 27,065 | $0.01 | $0.01 | $0.01 |
| 71 | THPL PVT MK LTR & sym (78000100) | SF | 89 | $6.00 | $7.00 | $6.50 |
| 72 | THPL PVT MK line 4 (78000200) | LF | 27,065 | $0.90 | $0.80 | $0.73 |
| 73 | THPL PVT MK line 6 (78000400) | LF | 483 | $1.00 | $1.40 | $1.25 |
| 74 | THPL PVT MK line 8 (78000500) | LF | 145 | $2.05 | $1.60 | $1.50 |
| 75 | THPL PVT MK line 12 (78000600) | LF | 1,114 | $3.50 | $3.30 | $3.00 |
| 76 | THPL PVT MK line 24 (78000650) | LF | 382 | $6.00 | $7.00 | $6.50 |
| 77 | Raised refl pavt MKR (78100100) | EACH | 622 | $37.00 | $41.00 | $50.00 |
| 78 | Raised ref PVT MK rem (78300200) | EACH | 622 | $0.01 | $0.01 | $0.01 |
| 79 | Main EX TR sig instal (85000200) | EACH | 1 | $3,700.00 | $3,800.00 | $3,500.00 |
| 80 | Det loop T1 (88600100) | LF | 1,063 | $33.00 | $34.00 | $31.43 |
| 81 | Remov EX TS equip (89502375) | EACH | 1 | $635.00 | $650.00 | $600.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of January 16, 2026. Compiled by Mirage Metrics.