IDOT contract 80B26 bid tabulation
Section 2025-2007-RS. Let by Illinois DOT on April 24, 2026, Cook, District 01. 3 bids received; low bid $2,940,592 by Gallagher Asphalt Corporation.
- Owner
- Illinois DOT
- Letting
- 24 APR 2026
- Pay items
- 129
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Gallagher Asphalt Corporation | $2,940,592 | Low |
| 2 | D. Construction, Inc. | $2,975,113 | +1.0% |
| 3 | K-Five Construction Corporation | $3,324,063 | +13% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Gallagher Asphalt Corporation | 2. D. Construction, Inc. | 3. K-Five Construction Corporation |
|---|---|---|---|---|---|---|
| 1 | Constructn layout SPL (X0320050) | LS | 1 | $5,000.00 | $100,665 | $3,200.00 |
| 2 | Relocate EX mailbox (X0327301) | EACH | 1 | $500.00 | $500.00 | $750.00 |
| 3 | Ped signal post 10 FT (X1400367) | EACH | 3 | $2,850.00 | $3,135.00 | $2,850.00 |
| 4 | Ped signal post 5 FT (X1400378) | EACH | 6 | $2,650.00 | $2,915.00 | $2,650.00 |
| 5 | Temporary ramp SPL (X4060995) | SY | 390 | $0.01 | $0.01 | $12.00 |
| 6 | Detectable warn SPL (X4240800) | SF | 900 | $39.00 | $50.00 | $55.00 |
| 7 | CC&G RMVL repl < = 10 (X4400501) | LF | 200 | $55.00 | $50.00 | $60.00 |
| 8 | CC&G RMVL repl > 10FT (X4400503) | LF | 1,800 | $50.00 | $40.00 | $50.00 |
| 9 | CL D patch T2 14 SPL (X4420815) | SY | 800 | $90.00 | $137.00 | $140.00 |
| 10 | CL D patch T3 14 SPL (X4420819) | SY | 800 | $90.00 | $137.00 | $140.00 |
| 11 | CL D patch T4 14 SPL (X4420821) | SY | 200 | $80.00 | $137.00 | $140.00 |
| 12 | Abandon & fill EX SS (X5509900) | LF | 50 | $80.00 | $125.00 | $770.00 |
| 13 | Pro SS conn to EX man (X5510011) | EACH | 6 | $3,000.00 | $1,500.00 | $2,735.00 |
| 14 | SS cleaned 12 (X5537800) | LF | 1,500 | $2.00 | $1.10 | $1.00 |
| 15 | Drop man connection (X6020133) | EACH | 1 | $3,000.00 | $3,000.00 | $26,500 |
| 16 | Man san 6 dia T1F CL (X6022830) | EACH | 2 | $22,500 | $16,500 | $35,890 |
| 17 | FR & lids adjust SPL (X6030310) | EACH | 50 | $1,300.00 | $900.00 | $1,240.00 |
| 18 | Engrs FLD ofc TY A D1 (X6700407) | CAL MO | 12 | $500.00 | $5,000.00 | $3,500.00 |
| 19 | Temp info signing (X7200061) | SF | 154.20 | $35.00 | $30.00 | $35.00 |
| 20 | Accessible ped signal (X8760200) | EACH | 30 | $2,265.54 | $2,492.09 | $2,265.00 |
| 21 | Conc FDN TY A 12D (X8780012) | LF | 36 | $275.00 | $302.50 | $275.00 |
| 22 | Drainage STR cleaned (Z0018500) | EACH | 100 | $400.00 | $385.00 | $350.00 |
| 23 | RE-optimize TR sig sys 1 (Z0033044) | EACH | 4 | $1,150.00 | $1,265.00 | $1,150.00 |
| 24 | Rem & repl anch bolts (Z0050400) | EACH | 1 | $890.00 | $979.00 | $1,000.00 |
| 25 | SS 1 wat MN 12 (Z0056648) | LF | 41 | $175.00 | $230.00 | $230.00 |
| 26 | Trainees (Z0076600) | HR | 500 | $0.80 | $0.80 | $0.80 |
| 27 | Trainees TPG (Z0076604) | HR | 500 | $15.00 | $15.00 | $15.00 |
| 28 | Earth excavation (20200100) | CY | 100 | $58.00 | $60.00 | $65.00 |
| 29 | Trench backfill (20800150) | CY | 70 | $52.00 | $60.00 | $88.00 |
| 30 | Topsoil F & P 4 (21101615) | SY | 50 | $25.00 | $27.50 | $30.00 |
| 31 | Sodding salt tolerant (25200110) | SY | 50 | $25.00 | $27.50 | $30.00 |
| 32 | Supple watering (25200200) | UNIT | 1 | $446.00 | $110.00 | $500.00 |
| 33 | Bit matls tack CT (40600290) | LB | 22,200 | $0.01 | $0.01 | $0.01 |
| 34 | Long joint sealant (40600370) | LF | 19,600 | $2.90 | $2.95 | $3.00 |
| 35 | Mix CR JTS flangewys (40600400) | TON | 51 | $0.01 | $0.01 | $50.00 |
| 36 | HMA surf rem butt JT (40600982) | SY | 530 | $0.01 | $0.01 | $10.00 |
| 37 | HMA repl over patch (40601005) | TON | 493 | $100.00 | $0.01 | $160.00 |
| 38 | HMA SC IL-9.5 D N70 (40604062) | TON | 3 | $500.00 | $300.00 | $200.00 |
| 39 | P HMA BC SMA 9.5 N80 (40605005) | TON | 3,792 | $135.00 | $118.00 | $125.00 |
| 40 | P HMA SC SMA 9.5 F N80 (40605026) | TON | 3,318 | $140.00 | $118.00 | $144.00 |
| 41 | Protective coat (42001300) | SY | 850 | $1.20 | $1.00 | $1.00 |
| 42 | PCC driveway pavt 8 (42300400) | SY | 50 | $98.00 | $100.00 | $112.00 |
| 43 | PC conc sidewalk 5 (42400200) | SF | 3,261 | $7.80 | $10.00 | $10.00 |
| 44 | HMA surf rem 2 (44000157) | SY | 24 | $70.00 | $50.00 | $25.00 |
| 45 | HMA surf rem 3 3/4 (44000164) | SY | 33,855 | $5.75 | $3.65 | $5.25 |
| 46 | Drive pavement rem (44000200) | SY | 50 | $42.00 | $15.00 | $18.00 |
| 47 | Sidewalk rem (44000600) | SF | 3,110 | $4.00 | $3.00 | $2.50 |
| 48 | HMA RM OV patch 4 (44002216) | SY | 2,200 | $10.00 | $0.01 | $35.00 |
| 49 | CL D patch T2 10 (44201765) | SY | 868 | $60.00 | $98.00 | $35.00 |
| 50 | CL D patch T3 10 (44201769) | SY | 1,000 | $60.00 | $98.00 | $35.00 |
| 51 | CL D patch T4 10 (44201771) | SY | 400 | $60.00 | $98.00 | $35.00 |
| 52 | Storm sew CL A 2 12 (550A0340) | LF | 261 | $90.00 | $75.00 | $190.00 |
| 53 | Storm sewer rem 6 (55100200) | LF | 60 | $50.00 | $20.00 | $29.00 |
| 54 | Storm sewer rem 8 (55100300) | LF | 40 | $55.00 | $20.00 | $29.00 |
| 55 | Storm sewer rem 10 (55100400) | LF | 98 | $60.00 | $20.00 | $29.00 |
| 56 | CB TA 4 dia T9F&G (60200905) | EACH | 1 | $4,750.00 | $3,930.00 | $9,210.00 |
| 57 | CB TA 4 dia T11F&G (60201105) | EACH | 1 | $4,750.00 | $3,930.00 | $9,190.00 |
| 58 | CB TA 5 dia T1F CL (60203905) | EACH | 1 | $6,500.00 | $5,930.00 | $13,630 |
| 59 | CB TD 3 dia T11F&G (60211400) | EACH | 6 | $5,500.00 | $3,490.00 | $7,465.00 |
| 60 | Man TA 4 dia T1F CL (60218400) | EACH | 3 | $5,250.00 | $4,150.00 | $6,880.00 |
| 61 | CB adjust (60250200) | EACH | 24 | $550.00 | $850.00 | $575.00 |
| 62 | CB reconst (60252800) | EACH | 11 | $1,100.00 | $1,500.00 | $2,385.00 |
| 63 | Man adjust (60255500) | EACH | 13 | $550.00 | $850.00 | $650.00 |
| 64 | Man reconst (60257900) | EACH | 5 | $1,100.00 | $1,500.00 | $2,385.00 |
| 65 | VV adjust (60265700) | EACH | 1 | $550.00 | $800.00 | $650.00 |
| 66 | Valve box adj (60266600) | EACH | 3 | $550.00 | $400.00 | $435.00 |
| 67 | FR & lids adjust (60300305) | EACH | 59 | $550.00 | $850.00 | $650.00 |
| 68 | FR & lids T1 OL (60406000) | EACH | 10 | $550.00 | $600.00 | $900.00 |
| 69 | FR & lids T1 ADA compl OL (60406001) | EACH | 1 | $750.00 | $600.00 | $900.00 |
| 70 | FR & lids T1 CL (60406100) | EACH | 3 | $550.00 | $600.00 | $900.00 |
| 71 | Remov manholes (60500040) | EACH | 1 | $900.00 | $1,000.00 | $1,600.00 |
| 72 | Remov inlets (60500060) | EACH | 4 | $550.00 | $750.00 | $620.00 |
| 73 | Non SPL waste disposl (66900200) | CY | 100 | $102.00 | $100.00 | $85.00 |
| 74 | Soil disposal analy (66900530) | EACH | 1 | $1,450.00 | $1,750.00 | $1,745.00 |
| 75 | Reg sub P-const plan (66901001) | LS | 1 | $3,100.00 | $2,250.00 | $3,400.00 |
| 76 | Reg sub F con report (66901003) | LS | 1 | $1,200.00 | $2,250.00 | $500.00 |
| 77 | Reg sub mon (66901006) | CAL DAY | 3 | $680.00 | $1,000.00 | $715.00 |
| 78 | Mobilization (67100100) | LS | 1 | $177,000 | $92,000 | $211,450 |
| 79 | TR cont & prot 701501 (70102620) | LS | 1 | $500.00 | $0.01 | $500.00 |
| 80 | TR cont & prot 701606 (70102625) | LS | 1 | $14,000 | $102,600 | $50,000 |
| 81 | TR cont & prot 701602 (70102632) | LS | 1 | $500.00 | $0.01 | $500.00 |
| 82 | TR cont & prot 701701 (70102635) | LS | 1 | $1,100.00 | $0.01 | $1,100.00 |
| 83 | TR cont & prot 701801 (70102640) | LS | 1 | $650.00 | $0.01 | $650.00 |
| 84 | Short term pavt mking (70300100) | LF | 65,285 | $0.01 | $0.01 | $0.01 |
| 85 | SHRT TRM pavt MK rem (70300150) | SF | 21,762 | $0.01 | $0.01 | $0.01 |
| 86 | Temp PVT MK LTR & sym paint (70300211) | SF | 194 | $0.01 | $0.01 | $0.01 |
| 87 | Temp PVT MK line 4 - paint (70300221) | LF | 24,550 | $0.33 | $0.01 | $0.01 |
| 88 | Temp PVT MK line 6 - paint (70300241) | LF | 640 | $0.33 | $0.01 | $0.01 |
| 89 | Temp PVT MK line 8 - paint (70300251) | LF | 417 | $0.33 | $0.01 | $0.01 |
| 90 | Temp PVT MK line 12 - paint (70300261) | LF | 350 | $1.00 | $0.01 | $0.01 |
| 91 | Temp PVT MK line 24 - paint (70300281) | LF | 9,565 | $2.00 | $0.01 | $0.01 |
| 92 | THPL PVT MK LTR & sym (78000100) | SF | 194 | $6.00 | $6.60 | $6.75 |
| 93 | THPL PVT MK line 4 (78000200) | LF | 14,900 | $0.85 | $0.94 | $1.00 |
| 94 | THPL PVT MK line 6 (78000400) | LF | 585 | $2.00 | $2.20 | $2.25 |
| 95 | THPL PVT MK line 8 (78000500) | LF | 417 | $2.50 | $2.75 | $2.85 |
| 96 | THPL PVT MK line 12 (78000600) | LF | 350 | $3.00 | $3.30 | $3.40 |
| 97 | THPL PVT MK line 24 (78000650) | LF | 3,577 | $6.00 | $6.60 | $6.75 |
| 98 | Mod ureth PM LTR-sym (78009000) | SF | 745 | $5.00 | $5.50 | $5.65 |
| 99 | Mod ureth PM line 4 (78009004) | LF | 16,295 | $0.50 | $0.55 | $0.55 |
| 100 | Mod ureth PM line 6 (78009006) | LF | 6,121 | $0.85 | $0.94 | $1.00 |
| 101 | Mod ureth PM line 8 (78009008) | LF | 146 | $1.50 | $1.65 | $1.75 |
| 102 | Mod ureth PM line 12 (78009012) | LF | 503 | $3.75 | $4.13 | $4.25 |
| 103 | Mod ureth PM line 24 (78009024) | LF | 11,914 | $5.00 | $5.50 | $5.70 |
| 104 | Raised refl pavt MKR (78100100) | EACH | 540 | $45.00 | $49.50 | $50.00 |
| 105 | Raised ref PVT MK rem (78300200) | EACH | 450 | $0.01 | $9.00 | $10.00 |
| 106 | PVT MKG rem WTR blast (78300202) | SF | 150 | $15.00 | $16.50 | $25.00 |
| 107 | Undrgrd C galvs 2 (81028200) | LF | 103 | $51.25 | $56.38 | $52.00 |
| 108 | Undrgrd C galvs 3 (81028220) | LF | 23 | $57.25 | $62.98 | $58.00 |
| 109 | Main EX TR sig instal (85000200) | EACH | 5 | $4,000.00 | $4,400.00 | $4,000.00 |
| 110 | Elcbl C signal 14 2C (87301215) | LF | 2,435 | $5.30 | $5.83 | $5.50 |
| 111 | Elcbl C signal 14 3C (87301225) | LF | 2,070 | $5.50 | $6.05 | $5.75 |
| 112 | Elcbl C signal 14 5C (87301245) | LF | 1,040 | $5.70 | $6.27 | $6.00 |
| 113 | Elcbl C signal 14 7C (87301255) | LF | 260 | $5.90 | $6.49 | $6.25 |
| 114 | Elcbl C lead 14 1PR (87301305) | LF | 2,365 | $5.30 | $5.83 | $6.25 |
| 115 | Elcbl C egrdc 6 1C (87301900) | LF | 315 | $6.70 | $7.37 | $7.00 |
| 116 | TS post 16 (87501200) | EACH | 5 | $3,425.65 | $3,768.22 | $3,500.00 |
| 117 | Conc FDN TY A (87800100) | LF | 16 | $375.50 | $413.05 | $375.00 |
| 118 | Drill EX handhole (87900200) | EACH | 12 | $225.00 | $247.50 | $225.00 |
| 119 | Ped SH LED 1F BM CDT (88102717) | EACH | 14 | $1,055.85 | $1,161.44 | $1,100.00 |
| 120 | Inductive loop detect (88500100) | EACH | 4 | $245.00 | $269.50 | $250.00 |
| 121 | Det loop T1 (88600100) | LF | 2,274 | $43.75 | $48.13 | $45.00 |
| 122 | Reloc EX sig head (89500100) | EACH | 8 | $500.00 | $550.00 | $500.00 |
| 123 | Mod EX contr (89502200) | EACH | 2 | $3,650.00 | $4,015.00 | $3,650.00 |
| 124 | Rem elcbl FR con (89502300) | LF | 4,460 | $1.30 | $1.43 | $1.30 |
| 125 | Remov EX TS equip (89502375) | EACH | 4 | $480.00 | $528.00 | $480.00 |
| 126 | Rebuild EX handhole (89502376) | EACH | 11 | $2,025.45 | $2,228.00 | $2,025.00 |
| 127 | Rebld EX HH to HD HH (89502378) | EACH | 1 | $2,236.50 | $2,460.15 | $2,240.00 |
| 128 | Remov EX handhole (89502380) | EACH | 4 | $540.00 | $594.00 | $540.00 |
| 129 | Remov EX conc FDN (89502385) | EACH | 4 | $650.00 | $715.00 | $650.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of April 24, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.