IDOT contract 89865 bid tabulation
Chillicothe, section 23-00042-00-BT. Let by Illinois DOT on January 17, 2025, Peoria, District 04. 5 bids received; low bid $473,305 by Advanced Asphalt Company.
- Owner
- Illinois DOT
- Letting
- 17 JAN 2025
- Pay items
- 43
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Advanced Asphalt Company | $473,305 | Low |
| 2 | Otto Baum Company, Inc. | $526,000 | +11% |
| 3 | Phoenix Corporation of the Quad Cities | $546,937 | +16% |
| 4 | Stark Excavating, Inc. | $598,224 | +26% |
| 5 | R. A. Cullinan and Son, a div of UCM, Inc. | $945,409 | +100% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Advanced Asphalt Company | 2. Otto Baum Company, Inc. | 3. Phoenix Corporation of the Quad Cities | 4. Stark Excavating, Inc. | 5. R. A. Cullinan and Son, a div of UCM, Inc. |
|---|---|---|---|---|---|---|---|---|
| 1 | Solar-power FB as CMP (X0326899) | EACH | 4 | $13,200 | $12,222 | $19,000 | $14,000 | $13,914 |
| 2 | Comb C&G remov SPL (X4400500) | LF | 110 | $20.00 | $15.17 | $52.50 | $30.50 | $50.51 |
| 3 | Sanitary manhole adj (X6026050) | EACH | 6 | $1,000.00 | $4,383.12 | $1,100.00 | $2,200.00 | $4,273.69 |
| 4 | Traf cont & prot SPL (X7010216) | LS | 1 | $6,950.00 | $7,386.05 | $19,000 | $11,100 | $15,854 |
| 5 | Handhole to BE adjust (X8140115) | EACH | 1 | $3,550.00 | $3,772.73 | $3,500.00 | $3,800.00 | $3,905.00 |
| 6 | Construction layout (Z0013798) | LS | 1 | $15,500 | $16,508 | $13,600 | $16,900 | $17,050 |
| 7 | Earth excavation (20200100) | CY | 325 | $25.00 | $55.99 | $46.50 | $49.50 | $290.66 |
| 8 | Furnished excavation (20400800) | CY | 975 | $40.00 | $72.94 | $53.00 | $70.00 | $127.45 |
| 9 | Seeding CL 2 (25000200) | ACRE | 1 | $3,130.00 | $4,091.56 | $3,130.00 | $5,200.00 | $3,443.00 |
| 10 | Nitrogen fert nutr (25000400) | LB | 100 | $3.00 | $6.11 | $3.75 | $1.60 | $3.30 |
| 11 | Phosphorus fert nutr (25000500) | LB | 100 | $3.00 | $6.11 | $3.75 | $1.60 | $3.30 |
| 12 | Potassium fert nutr (25000600) | LB | 100 | $3.00 | $6.11 | $3.75 | $1.60 | $3.30 |
| 13 | Mulch method 2 (25100115) | ACRE | 1 | $3,130.00 | $2,231.76 | $3,130.00 | $3,000.00 | $3,443.00 |
| 14 | Temp eros contr seed (28000250) | LB | 220 | $5.00 | $3.07 | $6.50 | $2.70 | $10.59 |
| 15 | Temp ditch checks (28000305) | LF | 117 | $15.00 | $11.66 | $65.00 | $12.00 | $40.33 |
| 16 | Perimeter eros bar (28000400) | LF | 2,902 | $4.20 | $4.28 | $4.00 | $4.00 | $11.73 |
| 17 | Inlet & pipe protect (28000500) | EACH | 10 | $150.00 | $306.98 | $370.00 | $150.00 | $637.39 |
| 18 | Stone riprap CL A4 (28100107) | SY | 9 | $200.00 | $175.49 | $174.00 | $300.00 | $168.34 |
| 19 | Filter fabric (28200200) | SY | 9 | $25.00 | $20.78 | $35.00 | $2.10 | $34.87 |
| 20 | Agg base cse B (35101400) | TON | 1,460 | $33.75 | $35.87 | $33.75 | $60.00 | $110.80 |
| 21 | PCC bse cse 7 (35300200) | SY | 38 | $70.00 | $183.04 | $160.00 | $160.00 | $214.88 |
| 22 | Bit matls PR CT (40600275) | LB | 8,445 | $1.00 | $1.06 | $1.00 | $0.90 | $1.19 |
| 23 | Bit matls tack CT (40600290) | LB | 17 | $15.00 | $15.94 | $15.00 | $10.50 | $95.60 |
| 24 | HMA SC IL-9.5L C N30 (40604090) | TON | 414 | $155.00 | $164.72 | $155.00 | $240.00 | $290.94 |
| 25 | Incidental HMA surf (40800050) | TON | 4 | $350.00 | $371.96 | $350.00 | $260.00 | $1,211.95 |
| 26 | PCC driveway pavt 6 (42300200) | SY | 61 | $90.00 | $76.03 | $164.00 | $150.00 | $149.76 |
| 27 | PC conc sidewalk 4 (42400100) | SF | 1,800 | $23.00 | $15.08 | $16.50 | $21.00 | $19.06 |
| 28 | Detectable warnings (42400800) | SF | 202 | $21.00 | $41.42 | $32.00 | $39.00 | $39.35 |
| 29 | Drive pavement rem (44000200) | SY | 61 | $35.00 | $15.37 | $26.00 | $20.50 | $75.77 |
| 30 | Sidewalk rem (44000600) | SF | 3,238 | $4.50 | $1.33 | $3.75 | $1.90 | $2.15 |
| 31 | P cul CL A 1 12 (542A0217) | LF | 26 | $115.00 | $114.02 | $110.00 | $150.00 | $140.99 |
| 32 | P cul CL A 1 15 (542A0220) | LF | 330 | $85.00 | $73.46 | $100.00 | $65.00 | $123.56 |
| 33 | PRC flar end sec 12 (54213657) | EACH | 2 | $1,100.00 | $1,248.55 | $1,350.00 | $1,700.00 | $1,600.46 |
| 34 | PRC flar end sec 15 (54213660) | EACH | 10 | $1,800.00 | $1,308.64 | $1,600.00 | $1,800.00 | $1,678.05 |
| 35 | Inlets TA T8G (60236200) | EACH | 1 | $1,500.00 | $2,806.14 | $1,800.00 | $1,900.00 | $2,353.30 |
| 36 | Inlets adj new T3F&G (60260500) | EACH | 1 | $1,300.00 | $3,709.15 | $2,200.00 | $2,000.00 | $3,537.79 |
| 37 | Comb CC&G TB6.12 (60603800) | LF | 237 | $90.00 | $74.38 | $77.50 | $100.00 | $151.29 |
| 38 | Mobilization (67100100) | LS | 1 | $28,650 | $43,295 | $27,700 | $34,500 | $53,554 |
| 39 | Sign panel T1 (72000100) | SF | 79 | $40.00 | $29.76 | $28.00 | $31.50 | $32.93 |
| 40 | Reloc sin pan assy TA (72400500) | EACH | 5 | $50.00 | $159.41 | $200.00 | $110.00 | $110.00 |
| 41 | Teles STL sin support (72800100) | LF | 154 | $20.00 | $24.44 | $39.00 | $20.50 | $21.45 |
| 42 | Paint PVT MK line 4 (78001110) | LF | 832 | $1.85 | $1.33 | $8.00 | $1.30 | $2.04 |
| 43 | Paint PVT MK line 24 (78001180) | LF | 669 | $11.00 | $4.25 | $18.00 | $4.20 | $12.10 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of January 17, 2025. Compiled by Mirage Metrics.