IDOT contract 91631 bid tabulation
Project Number: Lkz7-044 / /, section 17-00134-00-BR. Let by Illinois DOT on June 13, 2025, Edgar, District 05. 4 bids received; low bid $1,648,370 by Big O Services, LLC.
- Owner
- Illinois DOT
- Letting
- 13 JUN 2025
- Pay items
- 41
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Big O Services, LLC | $1,648,370 | Low |
| 2 | C-Hill Civil Contractors, Inc. | $1,650,000 | 0.0% |
| 3 | Sangamo Construction Company | $1,713,745 | +4.0% |
| 4 | William Charles Construction Company, LLC | $2,139,000 | +30% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Big O Services, LLC | 2. C-Hill Civil Contractors, Inc. | 3. Sangamo Construction Company | 4. William Charles Construction Company, LLC |
|---|---|---|---|---|---|---|---|
| 1 | Seeding CL 2 SPL (X2501000) | ACRE | 0.25 | $18,000 | $17,500 | $21,088 | $19,950 |
| 2 | Stone riprap CL A4 SP (X2810208) | TON | 544 | $125.00 | $97.00 | $75.05 | $135.00 |
| 3 | Traf cont-prot BLR 21 (X7011800) | LS | 1 | $6,000.00 | $6,200.00 | $8,102.36 | $11,400 |
| 4 | Construction layout (Z0013798) | LS | 1 | $28,000 | $40,000 | $25,104 | $15,000 |
| 5 | Trainees (Z0076600) | HR | 500 | $0.80 | $0.80 | $0.80 | $0.80 |
| 6 | Trainees TPG (Z0076604) | HR | 500 | $15.00 | $15.00 | $15.00 | $15.00 |
| 7 | Earth excavation (20200100) | CY | 198 | $55.00 | $40.00 | $29.49 | $100.00 |
| 8 | Channel excavation (20300100) | CY | 657 | $65.00 | $36.00 | $30.13 | $80.00 |
| 9 | Temp eros contr seed (28000250) | LB | 19 | $9.00 | $3.00 | $3.97 | $50.00 |
| 10 | Agg base cse B (35101400) | TON | 441 | $70.00 | $41.00 | $41.22 | $65.00 |
| 11 | Bit matls PR CT (40600275) | LB | 2,090 | $2.25 | $2.00 | $2.06 | $1.95 |
| 12 | Bit matls tack CT (40600290) | LB | 209 | $9.50 | $9.00 | $9.01 | $8.52 |
| 13 | HMA BC IL-19.0 N50 (40603080) | TON | 117 | $280.00 | $268.00 | $270.06 | $255.49 |
| 14 | HMA SC IL-9.5 C N50 (40604050) | TON | 78 | $375.00 | $360.00 | $361.86 | $342.34 |
| 15 | Rem exist struct (50100100) | EACH | 1 | $35,000 | $31,500 | $19,925 | $50,000 |
| 16 | Structure excavation (50200100) | CY | 243 | $60.00 | $38.00 | $40.64 | $80.00 |
| 17 | Cofferdam excavation (50200300) | CY | 167 | $70.00 | $83.00 | $55.93 | $100.00 |
| 18 | Cofferdam typ 1 loc 1 (50201101) | EACH | 1 | $35,000 | $38,315 | $53,648 | $175,000 |
| 19 | Cofferdam typ 1 loc 2 (50201102) | EACH | 1 | $35,000 | $38,315 | $53,648 | $175,000 |
| 20 | Conc struct (50300225) | CY | 190 | $1,200.00 | $1,065.00 | $1,144.18 | $1,500.00 |
| 21 | Conc sup-STR (50300255) | CY | 120.80 | $1,900.00 | $2,895.00 | $3,048.73 | $2,000.00 |
| 22 | Protective coat (50300300) | SY | 454 | $3.00 | $4.50 | $3.39 | $7.50 |
| 23 | F & E struct steel (50500105) | LS | 1 | $221,000 | $213,750 | $252,068 | $270,775 |
| 24 | Stud shear connectors (50500505) | EACH | 3,000 | $9.23 | $5.20 | $5.25 | $5.75 |
| 25 | Reinf bars, epoxy CTD (50800205) | LB | 47,320 | $2.25 | $1.91 | $1.79 | $2.25 |
| 26 | Steel railing TY SM (50901050) | LF | 245 | $285.00 | $272.00 | $288.97 | $259.10 |
| 27 | Fur STL pile HP14X73 (51201800) | LF | 1,732 | $88.00 | $55.60 | $94.54 | $115.00 |
| 28 | Driving piles (51202305) | LF | 1,732 | $0.01 | $0.01 | $0.03 | $0.01 |
| 29 | Test pile ST HP14X73 (51203800) | EACH | 4 | $15,000 | $22,300 | $5,453.13 | $7,000.00 |
| 30 | Name plates (51500100) | EACH | 1 | $900.00 | $825.00 | $1,072.08 | $1,000.00 |
| 31 | Elast bearing assy T1 (52100010) | EACH | 15 | $2,500.00 | $1,200.00 | $1,423.59 | $1,500.00 |
| 32 | Anchor bolts 3/4 (52100510) | EACH | 40 | $150.00 | $82.00 | $84.87 | $100.00 |
| 33 | Granular backfill STR (58600101) | CY | 174 | $130.00 | $97.00 | $96.09 | $100.00 |
| 34 | Geocomposite wall DR (59100100) | SY | 104 | $23.00 | $35.00 | $26.53 | $60.00 |
| 35 | P undr for struct 4 (60146304) | LF | 210 | $13.00 | $35.00 | $28.14 | $40.00 |
| 36 | Traf bar term T6A (63100087) | EACH | 2 | $5,500.00 | $5,155.00 | $5,573.48 | $4,910.00 |
| 37 | TR bar TRM T1 SPL tan (63100167) | EACH | 2 | $4,500.00 | $4,205.00 | $4,233.38 | $4,005.00 |
| 38 | Guardrail remov (63200310) | LF | 136 | $4.00 | $11.00 | $13.13 | $30.00 |
| 39 | Mobilization (67100100) | LS | 1 | $60,000 | $95,803 | $101,111 | $128,760 |
| 40 | Terminal marker - DA (72501000) | EACH | 4 | $55.00 | $52.50 | $52.85 | $50.00 |
| 41 | Grdrail ref type B (78200006) | EACH | 8 | $20.00 | $15.75 | $15.86 | $15.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of June 13, 2025. Compiled by Mirage Metrics.