IDOT contract 93840 bid tabulation
Project Number: 8Sir-346 / /, section 24-14119-00-BR. Let by Illinois DOT on August 1, 2025, Hancock, District 06. 3 bids received; low bid $535,985 by County Contractors, Inc..
- Owner
- Illinois DOT
- Letting
- 01 AUG 2025
- Pay items
- 38
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | County Contractors, Inc. | $535,985 | Low |
| 2 | Laverdiere Construction, Inc. | $563,644 | +5.0% |
| 3 | Brandt Construction Co. | $675,882 | +26% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. County Contractors, Inc. | 2. Laverdiere Construction, Inc. | 3. Brandt Construction Co. |
|---|---|---|---|---|---|---|
| 1 | Traf cont-prot BLR 21 (X7011800) | LS | 1 | $4,500.00 | $5,200.00 | $4,000.00 |
| 2 | Construction layout (Z0013798) | LS | 1 | $4,500.00 | $7,000.00 | $9,000.00 |
| 3 | Earth excavation (20200100) | CY | 150 | $30.00 | $41.00 | $55.00 |
| 4 | Channel excavation (20300100) | CY | 136 | $18.00 | $21.00 | $55.00 |
| 5 | Geotech fab F/GR stab (21001000) | SY | 455 | $4.50 | $2.00 | $4.00 |
| 6 | Seeding CL 2 (25000200) | ACRE | 0.25 | $10,000 | $8,915.00 | $8,000.00 |
| 7 | Nitrogen fert nutr (25000400) | LB | 23 | $3.75 | $12.00 | $4.50 |
| 8 | Phosphorus fert nutr (25000500) | LB | 23 | $3.75 | $12.00 | $4.50 |
| 9 | Potassium fert nutr (25000600) | LB | 23 | $3.75 | $12.00 | $4.50 |
| 10 | Agr ground limestone (25000700) | TON | 0.50 | $1,500.00 | $125.00 | $112.00 |
| 11 | Mulch method 2 (25100115) | ACRE | 0.25 | $10,000 | $8,915.00 | $7,900.00 |
| 12 | Earth exc - eros cont (28000200) | CY | 25 | $35.00 | $41.00 | $72.00 |
| 13 | Temp eros contr seed (28000250) | LB | 50 | $1.00 | $3.00 | $4.50 |
| 14 | Perimeter eros bar (28000400) | LF | 525 | $3.50 | $4.00 | $13.00 |
| 15 | Stone riprap CL A5 (28100209) | TON | 470 | $115.00 | $104.00 | $145.00 |
| 16 | Filter fabric (28200200) | SY | 358 | $5.00 | $2.00 | $3.00 |
| 17 | Agg base cse B (35101400) | TON | 294 | $45.00 | $29.00 | $77.00 |
| 18 | Bit matls PR CT (40600275) | LB | 913 | $0.01 | $0.01 | $5.00 |
| 19 | Bit matls tack CT (40600290) | LB | 89 | $0.01 | $0.01 | $38.00 |
| 20 | HMA BC IL-19.0 N50 (40603080) | TON | 68 | $580.00 | $616.00 | $275.00 |
| 21 | HMA SC IL-9.5 C N50 (40604050) | TON | 56 | $580.00 | $605.00 | $350.00 |
| 22 | Pavement rem (44000100) | SY | 404 | $13.50 | $12.00 | $25.00 |
| 23 | Rem exist struct (50100100) | EACH | 1 | $19,000 | $22,000 | $30,000 |
| 24 | Structure excavation (50200100) | CY | 120 | $16.00 | $38.00 | $40.00 |
| 25 | Conc struct (50300225) | CY | 33 | $870.00 | $1,091.00 | $1,350.00 |
| 26 | P P conc DK BM 27 DP (50400505) | SF | 1,619 | $117.00 | $126.00 | $152.00 |
| 27 | Reinf bars, epoxy CTD (50800205) | LB | 4,040 | $2.60 | $3.00 | $3.80 |
| 28 | Steel railing TY S1 (50900205) | LF | 124 | $170.00 | $193.00 | $180.00 |
| 29 | Fur STL pile HP10X42 (51201400) | LF | 176 | $98.00 | $105.00 | $85.00 |
| 30 | Driving piles (51202305) | LF | 176 | $0.10 | $0.01 | $0.01 |
| 31 | Test pile ST HP10X42 (51203400) | EACH | 2 | $4,225.00 | $5,546.00 | $9,500.00 |
| 32 | Pile shoes (51204650) | EACH | 10 | $195.00 | $156.00 | $150.00 |
| 33 | Name plates (51500100) | EACH | 1 | $1,730.00 | $1,100.00 | $1,500.00 |
| 34 | Waterprf membrane sys (58100200) | SY | 186 | $132.00 | $135.00 | $140.00 |
| 35 | PC mortar fairing cse (58300100) | LF | 480 | $1.00 | $1.00 | $18.00 |
| 36 | Granular backfill STR (58600101) | CY | 56 | $98.00 | $89.00 | $160.00 |
| 37 | Mobilization (67100100) | LS | 1 | $32,000 | $28,500 | $40,000 |
| 38 | Terminal marker - DA (72501000) | EACH | 4 | $53.00 | $60.00 | $55.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of August 1, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.