IDOT contract 95968 bid tabulation

Project Number: 785R-503 / /, section 21-00070-00-BR. Let by Illinois DOT on January 17, 2025, Edwards, District 07. 3 bids received; low bid $425,523 by Samron Midwest Contracting, Inc..

Owner
Illinois DOT
Letting
17 JAN 2025
Pay items
20
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Samron Midwest Contracting, Inc.$425,523Low
2E. T. Simonds Construction Company$446,090+5.0%
3Kieffer Bros. Construction Co., Inc.$475,877+12%
IDOT contract 95968: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Samron Midwest Contracting, Inc.2. E. T. Simonds Construction Company3. Kieffer Bros. Construction Co., Inc.
1Seeding CL 2 SPL (X2501000)ACRE0.10$30,000$66,022$69,983
2Memb WTRPRF sys B STR (X5810103)SY83$30.00$64.88$83.95
3Traf bar term T5A SPL (X6311205)EACH1$2,400.00$2,420.00$2,565.20
4SPBGR (short radius) (X6330725)LF12.50$83.00$82.50$87.45
5Construction layout (Z0013798)LS1$7,500.00$9,535.45$5,829.02
6Earth excavation (20200100)CY65$60.00$244.63$31.80
7Porous gran embank (20700110)TON600$47.00$62.47$75.74
8Porous gran backfill (20900110)CY31$99.00$123.41$116.71
9Stone dump rip CL A4 (28100807)TON235$60.00$64.11$97.68
10Agg base cse B (35101400)TON84$45.00$64.30$72.56
11Aggregate SHLDS B (48101200)TON54$45.00$92.02$64.08
12Rem exist struct (50100100)EACH1$40,000$25,479$19,843
13Reinf bars, epoxy CTD (50800205)LB34,560$2.00$1.60$2.51
14Steel railing TY S1 (50900205)LF39$310.00$313.50$332.31
15Name plates (51500100)EACH1$575.00$699.45$1,211.05
16Conc box cul (54003000)CY136.90$1,470.00$1,370.10$1,681.37
17TR bar TRM T1 SPL tan (63100167)EACH1$4,600.00$4,620.00$4,897.20
18Guardrail remov (63200310)LF96$8.00$18.77$9.33
19Mobilization (67100100)LS1$25,000$50,561$11,819
20Terminal marker - DA (72501000)EACH4$55.00$55.00$58.30
IDOT contract 95968: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of January 17, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy