IDOT contract 97876 bid tabulation
Collinsville, section 22-00098-02-SP. Let by Illinois DOT on January 16, 2026, Madison, District 08. 3 bids received; low bid $790,083 by Hank's Excavating & Landscaping, Inc..
- Owner
- Illinois DOT
- Letting
- 16 JAN 2026
- Pay items
- 60
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Hank's Excavating & Landscaping, Inc. | $790,083 | Low |
| 2 | Stutz Excavating, Inc. | $856,243 | +8.0% |
| 3 | DMS Contracting, Inc. | $1,098,752 | +39% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Hank's Excavating & Landscaping, Inc. | 2. Stutz Excavating, Inc. | 3. DMS Contracting, Inc. |
|---|---|---|---|---|---|---|
| 1 | Constructn layout SPL (X0320050) | LS | 1 | $3,740.62 | $23,000 | $9,270.00 |
| 2 | Brick pavers (X0540000) | SF | 172 | $49.47 | $72.00 | $100.00 |
| 3 | Conn EX DRG structure (X1200160) | EACH | 3 | $1,627.97 | $1,500.00 | $1,120.00 |
| 4 | Brick paver removal (X1700112) | SF | 60 | $18.42 | $12.00 | $39.75 |
| 5 | Rem ST RE snplassy SP (X2600022) | EACH | 12 | $472.50 | $515.00 | $440.00 |
| 6 | PC conc sidewalk 5 SP (X4240430) | SF | 749 | $64.71 | $28.15 | $63.00 |
| 7 | Trench drain (X6010302) | LF | 125 | $480.39 | $440.00 | $441.00 |
| 8 | Inlets SPL (X6024240) | EACH | 1 | $5,915.52 | $4,930.00 | $4,650.00 |
| 9 | Sanitary manhole adj (X6026050) | EACH | 1 | $908.15 | $765.00 | $555.00 |
| 10 | Comb CC&G TB SPL (X6061700) | LF | 785.50 | $133.04 | $109.30 | $129.00 |
| 11 | Traf cont & prot SPL (X7010216) | LS | 1 | $15,526 | $18,350 | $95,275 |
| 12 | Decorative sign post (X7290004) | EACH | 12 | $945.00 | $1,025.00 | $2,440.00 |
| 13 | Handhole to BE adjust (X8140115) | EACH | 1 | $6,772.50 | $7,355.00 | $6,825.00 |
| 14 | EX LT pole FDN adjust (X8360095) | EACH | 3 | $9,675.75 | $10,525 | $9,750.00 |
| 15 | Trench backfill (20800150) | CY | 41 | $55.06 | $182.25 | $70.00 |
| 16 | Seeding CL 1A (25000110) | ACRE | 0.25 | $8,251.80 | $12,000 | $7,350.00 |
| 17 | Nitrogen fert nutr (25000400) | LB | 23 | $2.30 | $22.00 | $38.00 |
| 18 | Phosphorus fert nutr (25000500) | LB | 23 | $2.30 | $22.00 | $38.00 |
| 19 | Potassium fert nutr (25000600) | LB | 23 | $2.30 | $22.00 | $38.00 |
| 20 | Mulch method 2 (25100115) | ACRE | 0.25 | $11,586 | $6,285.00 | $13,200 |
| 21 | Inlet & pipe protect (28000500) | EACH | 15 | $302.05 | $200.00 | $210.00 |
| 22 | Agg base cse B 4 (35101600) | SY | 832 | $23.23 | $23.00 | $31.50 |
| 23 | Bit matls tack CT (40600290) | LB | 173 | $15.66 | $6.30 | $15.80 |
| 24 | HMA SC IL-9.5 C N70 (40604052) | TON | 42.90 | $627.92 | $725.00 | $632.80 |
| 25 | PCC driveway pavt 8 (42300400) | SY | 4 | $448.39 | $490.00 | $885.00 |
| 26 | PC conc sidewalk 5 (42400200) | SF | 6,687 | $18.28 | $18.00 | $20.50 |
| 27 | Detectable warnings (42400800) | SF | 382 | $46.71 | $163.35 | $93.00 |
| 28 | Pavement rem (44000100) | SY | 470 | $53.82 | $13.60 | $54.00 |
| 29 | Drive pavement rem (44000200) | SY | 5 | $94.77 | $160.00 | $644.00 |
| 30 | Curb rem (44000300) | LF | 817 | $16.41 | $31.25 | $24.15 |
| 31 | Comb curb gutter rem (44000500) | LF | 55 | $30.48 | $58.00 | $36.00 |
| 32 | Sidewalk rem (44000600) | SF | 5,461 | $2.46 | $5.85 | $3.55 |
| 33 | CL C patch T1 7 (44201313) | SY | 4 | $475.48 | $585.55 | $505.00 |
| 34 | CL C patch T2 7 (44201317) | SY | 21 | $219.84 | $322.00 | $505.00 |
| 35 | CL C patch T3 7 (44201321) | SY | 23 | $276.53 | $204.00 | $505.00 |
| 36 | CL C patch T4 7 (44201323) | SY | 154 | $199.43 | $209.00 | $505.00 |
| 37 | Concrete collar (54248510) | CY | 1.60 | $3,734.43 | $750.00 | $1,700.00 |
| 38 | Storm sew CL B 1 12 (550B0050) | LF | 66 | $156.75 | $246.60 | $250.00 |
| 39 | Storm sew CL B 1 16 (550B0080) | LF | 7 | $270.48 | $150.00 | $595.00 |
| 40 | Storm sew CL B 1 24 (550B0120) | LF | 10 | $386.60 | $174.25 | $505.00 |
| 41 | Storm sew CL B 1 36 (550B0160) | LF | 10 | $657.99 | $217.50 | $700.00 |
| 42 | Water valves adjust (56109210) | EACH | 3 | $402.23 | $118.00 | $240.00 |
| 43 | Fire hydnts to BE adj (56400300) | EACH | 1 | $6,373.37 | $2,010.00 | $2,250.00 |
| 44 | Man TA 4 dia T1F CL (60218400) | EACH | 1 | $6,615.57 | $3,185.00 | $5,275.00 |
| 45 | Man TA 4 dia T24F&G (60219540) | EACH | 1 | $6,138.32 | $3,185.00 | $5,295.00 |
| 46 | Inlets TB T1F CL (60240215) | EACH | 1 | $4,068.80 | $3,455.00 | $3,700.00 |
| 47 | Inlets TB T3F&G (60240220) | EACH | 3 | $3,591.55 | $3,455.00 | $3,950.00 |
| 48 | Inlets TB T24F&G (60240328) | EACH | 4 | $2,746.74 | $3,455.00 | $3,760.00 |
| 49 | Inlets adj new T1F CL (60260400) | EACH | 1 | $1,287.37 | $1,105.00 | $1,250.00 |
| 50 | Inl recon new T1F CL (60263000) | EACH | 2 | $1,856.00 | $1,820.00 | $2,595.00 |
| 51 | Remov inlets (60500060) | EACH | 3 | $617.38 | $635.00 | $1,560.00 |
| 52 | Conc curb TB (60600605) | LF | 528 | $97.19 | $86.00 | $125.00 |
| 53 | Comb CC&G TB6.12 (60603800) | LF | 58 | $132.60 | $133.50 | $155.00 |
| 54 | Mobilization (67100100) | LS | 1 | $24,985 | $66,000 | $90,500 |
| 55 | Sign panel T1 (72000100) | SF | 12.60 | $32.55 | $36.00 | $60.00 |
| 56 | Teles STL sin support (72800100) | LF | 29 | $45.15 | $49.00 | $46.50 |
| 57 | THPL PVT MK line 4 (78000200) | LF | 92 | $6.30 | $8.40 | $6.35 |
| 58 | THPL PVT MK line 8 (78000500) | LF | 115 | $8.40 | $10.70 | $8.50 |
| 59 | THPL PVT MK line 24 (78000650) | LF | 959 | $10.76 | $13.15 | $10.85 |
| 60 | PVT MKG rem WTR blast (78300202) | SF | 600 | $6.30 | $7.80 | $6.35 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of January 16, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.