IDOT contract 99678 bid tabulation

Project Number: 1Fda-058 / /, section 12-00071-00-BR. Let by Illinois DOT on January 16, 2026, Pulaski, District 09. 2 bids received; low bid $4,197,074 by Samron Midwest Contracting, Inc..

Owner
Illinois DOT
Letting
16 JAN 2026
Pay items
82
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Samron Midwest Contracting, Inc.$4,197,074Low
2E. T. Simonds Construction Company$5,716,840+36%
IDOT contract 99678: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Samron Midwest Contracting, Inc.2. E. T. Simonds Construction Company
1Constructn layout SPL (X0320050)LS1$22,000$80,101
2Cros sonic log A duct (X0320051)LF251$47.00$175.50
3Cros sonic log test (X0320052)EACH6$2,900.00$1,545.50
4Clearing & grubbing (X2010510)LS1$17,690$54,289
5Stone riprap CL A5 SP (X2810110)SY3,393$29.00$62.23
6Conc wearing surf 5 (X5030305)SY200$128.00$241.85
7Prec bridge app slab (X5040100)SF1,690$66.00$64.60
8Slope wall breaking (X5110306)SY3,393$3.00$25.94
9Drainage scuppr DS-11 (X5230174)EACH4$1,900.00$3,054.43
10Traf cont & prot SPL (X7010216)LS1$24,000$26,147
11Approach slab rem (Z0004552)SY84$105.00$49.02
12Trainees (Z0076600)HR1,500$0.80$0.80
13Trainees TPG (Z0076604)HR1,500$15.00$15.00
14Earth excavation (20200100)CY1,230$25.00$39.89
15Furnished excavation (20400800)CY775$35.00$46.14
16Trench backfill (20800150)CY26$38.00$112.54
17Seeding CL 2A (25000210)ACRE0.75$7,500.00$5,362.51
18Nitrogen fert nutr (25000400)LB68$1.76$1.82
19Phosphorus fert nutr (25000500)LB68$1.76$1.82
20Potassium fert nutr (25000600)LB68$1.76$1.82
21Mulch method 2 (25100115)ACRE0.50$700.00$4,152.50
22Erosion contr blanket (25100630)SY555$1.37$2.09
23Temp eros contr seed (28000250)LB150$7.00$8.38
24Temp ditch checks (28000305)LF407$12.00$24.35
25Perimeter eros bar (28000400)LF286$6.00$12.39
26Inlet & pipe protect (28000500)EACH1$104.00$304.77
27Stone riprap CL A3 (28100205)TON41$52.00$86.56
28Filter fabric (28200200)SY76$5.00$3.89
29Sub gran mat A (31100100)TON29$63.00$51.65
30Agg base cse A (35100100)TON776$31.00$33.65
31Bit matls PR CT (40600275)LB3,830$1.50$0.01
32Bit matls tack CT (40600290)LB346$3.60$0.01
33HMA BC IL-19.0 N70 (40603085)TON388$153.00$138.68
34HMA SC IL-9.5 C N70 (40604052)TON130$207.00$143.31
35Welded wire reinf (42000060)SY74$22.50$39.11
36PVT con PCC BR app SL (42000080)SY97$172.00$239.82
37Protective coat (42001300)SY765$1.40$1.79
38Pavement rem (44000100)SY1,261$13.00$17.94
39Paved ditch removal (44004000)LF496$9.00$26.48
40Paved SHLD removal (44004250)SY275$9.00$16.76
41Aggregate SHLDS A (48100100)TON45$48.00$48.67
42HMA shoulders (48203100)TON118$86.00$128.93
43Rem exist struct (50100100)EACH1$460,000$224,562
44Slope wall remov (50104650)SY303$10.00$65.38
45Pipe culvert remov (50105220)LF50$12.00$67.09
46Structure excavation (50200100)CY162$0.01$35.39
47Floor drains (50300100)EACH10$745.00$913.77
48Conc struct (50300225)CY349.90$1,450.00$1,876.32
49Conc sup-STR (50300255)CY302.80$1,820.00$1,962.74
50BR deck grooving (50300260)SY960$13.00$14.49
51Protective coat (50300300)SY1,314$1.36$1.91
52F & E P P con I-BM 54 (50401105)LF1,077$582.00$786.70
53Reinforcement bars (50800105)LB50,530$1.50$1.88
54Reinf bars, epoxy CTD (50800205)LB187,080$1.70$2.00
55Mechanical splicers (50800530)EACH348$156.00$204.84
56Fur STL pile HP14X89 (51201900)LF564$144.00$132.34
57Driving piles (51202305)LF564$0.01$0.01
58Test pile ST HP14X89 (51203900)EACH2$4,600.00$9,544.42
59Pile shoes (51204650)EACH14$191.00$181.50
60Name plates (51500100)EACH1$925.00$1,399.93
61Permanent casing (51602000)LF167$634.00$676.62
62Drilled shaft in soil (51603000)CY122$736.00$983.51
63Drilled shaft in rock (51604000)CY49.40$4,600.00$3,650.87
64Pref JT strip seal (52000110)LF58$225.00$310.23
65P cul CL A 1 30 (542A0235)LF69$138.00$161.30
66PRC flar end sec 30 (54213675)EACH2$3,300.00$3,015.81
67Granular backfill STR (58600101)CY110$58.00$78.66
68Geocomposite wall DR (59100100)SY79$25.00$34.81
69Conc HDWL for P drain (60100060)EACH4$680.00$343.27
70P undr for struct 4 (60146304)LF135$25.00$32.61
71Paved ditch TB-30 (60617510)LF602$131.00$103.06
72SPBGR TY A 6FT posts (63000001)LF100$46.00$44.00
73Traf bar term T6 (63100085)EACH4$4,600.00$4,400.00
74TR bar TRM T1 SPL tan (63100167)EACH4$5,800.00$5,500.00
75Guardrail remov (63200310)LF291$8.75$12.04
76Mobilization (67100100)LS1$250,000$1,098,685
77Sign panel T1 (72000100)SF12$59.00$45.11
78Terminal marker - DA (72501000)EACH4$58.00$55.00
79Teles STL sin support (72800100)LF32$22.00$17.05
80Mod ureth PM line 4 (78009004)LF3,600$2.50$4.40
81Grdrail ref type A (78200005)EACH6$12.00$11.00
82Barr wall ref type C (78200011)EACH10$31.00$24.98
IDOT contract 99678: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of January 16, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy