IDOT contract 99761 bid tabulation
City Of Marion, section 24-00133-00-SP. Let by Illinois DOT on April 24, 2026, Williamson, District 09. 2 bids received; low bid $979,828 by Samron Midwest Contracting, Inc..
- Owner
- Illinois DOT
- Letting
- 24 APR 2026
- Pay items
- 66
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Samron Midwest Contracting, Inc. | $979,828 | Low |
| 2 | E. T. Simonds Construction Company | $1,072,946 | +10% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Samron Midwest Contracting, Inc. | 2. E. T. Simonds Construction Company |
|---|---|---|---|---|---|
| 1 | Pavt removal SPL (X4404400) | SY | 1,835 | $22.00 | $41.58 |
| 2 | Box culvert removal (X5400005) | LF | 27 | $300.00 | $607.63 |
| 3 | San MH rec new T1F CL (X6026057) | EACH | 3 | $3,000.00 | $4,831.78 |
| 4 | Traf cont & prot SPL (X7010216) | LS | 1 | $115,000 | $44,221 |
| 5 | Tree remov acres (20100500) | ACRE | 0.10 | $0.01 | $73,981 |
| 6 | Earth excavation (20200100) | CY | 2,000 | $31.00 | $49.00 |
| 7 | Porous gran embank (20700220) | CY | 179 | $37.00 | $80.63 |
| 8 | Trench backfill (20800150) | CY | 93 | $44.00 | $51.39 |
| 9 | Seeding CL 2A (25000210) | ACRE | 1 | $6,400.00 | $4,265.65 |
| 10 | Nitrogen fert nutr (25000400) | LB | 90 | $2.00 | $6.81 |
| 11 | Phosphorus fert nutr (25000500) | LB | 90 | $2.00 | $6.81 |
| 12 | Potassium fert nutr (25000600) | LB | 90 | $2.00 | $6.81 |
| 13 | Agr ground limestone (25000700) | TON | 2 | $415.00 | $570.36 |
| 14 | Mulch method 2 (25100115) | ACRE | 1 | $1,500.00 | $4,133.01 |
| 15 | Erosion contr blanket (25100630) | SY | 1,030 | $2.50 | $2.30 |
| 16 | Temp eros contr seed (28000250) | LB | 300 | $5.00 | $5.61 |
| 17 | Temp ditch checks (28000305) | LF | 60 | $11.00 | $21.44 |
| 18 | Perimeter eros bar (28000400) | LF | 676 | $3.50 | $7.40 |
| 19 | Inlet & pipe protect (28000500) | EACH | 4 | $153.00 | $227.26 |
| 20 | Agg base cse B (35101400) | TON | 1,376 | $40.00 | $53.41 |
| 21 | Agg surf course TY B (40200800) | TON | 106 | $38.00 | $53.82 |
| 22 | Bit matls PR CT (40600275) | LB | 7,333 | $0.01 | $0.01 |
| 23 | Bit matls tack CT (40600290) | LB | 1,975 | $0.01 | $0.01 |
| 24 | P bit matls tack CT (40600295) | LB | 691 | $0.01 | $0.01 |
| 25 | HMA surf rem butt JT (40600982) | SY | 154 | $37.00 | $36.92 |
| 26 | HMA BC IL-9.5 N90 (40602990) | TON | 741 | $140.00 | $125.12 |
| 27 | P HMA BC IL-9.5 N90 (40603209) | TON | 344 | $168.00 | $135.94 |
| 28 | Incidental HMA surf (40800050) | TON | 41 | $650.00 | $387.03 |
| 29 | PC conc sidewalk 5 (42400200) | SF | 64 | $65.00 | $78.16 |
| 30 | Detectable warnings (42400800) | SF | 10 | $22.00 | $26.72 |
| 31 | Comb curb gutter rem (44000500) | LF | 79 | $7.00 | $19.40 |
| 32 | Sidewalk rem (44000600) | SF | 98 | $4.00 | $5.75 |
| 33 | Welded wire reinf (44200050) | SY | 26 | $11.00 | $17.20 |
| 34 | Pavt patch T4 6 (44200071) | SY | 52 | $133.00 | $275.29 |
| 35 | Pavt patch T4 12 (44200150) | SY | 25 | $144.00 | $251.15 |
| 36 | CL B patch T4 8 (44200944) | SY | 26 | $305.00 | $358.27 |
| 37 | Dowel bars 1 1/4 (44201298) | EACH | 10 | $33.00 | $8.28 |
| 38 | Saw cuts (44213200) | LF | 98 | $0.01 | $20.87 |
| 39 | Tie bars 3/4 (44213204) | EACH | 20 | $20.00 | $7.18 |
| 40 | HMA shoulders 8 (48203029) | SY | 1,558 | $70.00 | $66.77 |
| 41 | Conc headwall removal (50104400) | EACH | 1 | $300.00 | $982.01 |
| 42 | Pipe culvert remov (50105220) | LF | 65 | $6.00 | $17.33 |
| 43 | Box cul end sec C1 (54001001) | EACH | 2 | $17,800 | $19,571 |
| 44 | PCBC 10X4 (54011004) | LF | 44 | $2,000.00 | $2,835.26 |
| 45 | P cul CL A 1 15 (542A0220) | LF | 68 | $96.00 | $99.28 |
| 46 | PRC flar end sec 15 (54213660) | EACH | 4 | $2,600.00 | $1,783.49 |
| 47 | PRC flar end sec 24 (54213669) | EACH | 1 | $3,500.00 | $2,336.62 |
| 48 | Concrete collar (54248510) | CY | 0.88 | $608.00 | $2,008.14 |
| 49 | Storm sew CL A 1 24 (550A0120) | LF | 20 | $185.00 | $138.23 |
| 50 | Inlets TA T15F&L (60237000) | EACH | 2 | $3,100.00 | $2,573.47 |
| 51 | Inlets TB T1F OL (60240210) | EACH | 1 | $3,600.00 | $3,705.58 |
| 52 | Inlets TB T1F CL (60240215) | EACH | 1 | $4,500.00 | $3,705.58 |
| 53 | Man adjust (60255500) | EACH | 2 | $450.00 | $224.11 |
| 54 | Remov inlets (60500060) | EACH | 2 | $100.00 | $924.73 |
| 55 | Class SI conc outlet (60600095) | CY | 7 | $1,150.00 | $1,554.53 |
| 56 | Comb CC&G TB6.18 (60604400) | LF | 1,283 | $53.00 | $49.16 |
| 57 | Guardrail remov (63200310) | LF | 859 | $10.00 | $12.39 |
| 58 | Shoulder rum strip 8 (64200108) | LF | 816 | $8.00 | $8.28 |
| 59 | Mobilization (67100100) | LS | 1 | $54,200 | $79,358 |
| 60 | Changeable message SN (70107025) | CAL DAY | 84 | $80.00 | $41.40 |
| 61 | Short term pavt mking (70300100) | LF | 114 | $2.00 | $1.31 |
| 62 | SHRT TRM pavt MK rem (70300150) | SF | 38 | $85.00 | $63.82 |
| 63 | Paint PVT MK line 4 (78001110) | LF | 2,612 | $2.50 | $1.88 |
| 64 | Paint PVT MK line 24 (78001180) | LF | 11 | $16.00 | $11.32 |
| 65 | Raised refl pavt MKR (78100100) | EACH | 32 | $117.00 | $186.59 |
| 66 | Raised ref PVT MK rem (78300200) | EACH | 32 | $13.00 | $17.42 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of April 24, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.