IDOT contract 99763 bid tabulation
Carbondale, section 22-00151-00-BT. Let by Illinois DOT on January 16, 2026, Jackson, District 09. 2 bids received; low bid $1,263,057 by Samron Midwest Contracting, Inc..
- Owner
- Illinois DOT
- Letting
- 16 JAN 2026
- Pay items
- 65
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Samron Midwest Contracting, Inc. | $1,263,057 | Low |
| 2 | E. T. Simonds Construction Company | $1,448,601 | +15% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Samron Midwest Contracting, Inc. | 2. E. T. Simonds Construction Company |
|---|---|---|---|---|---|
| 1 | Solar-power FB as CMP (X0326899) | EACH | 4 | $8,500.00 | $12,586 |
| 2 | Wayfinding sign SP (X0327880) | LS | 1 | $10,000 | $19,785 |
| 3 | Fold down bollards (X0350805) | EACH | 7 | $2,500.00 | $1,859.07 |
| 4 | Potholing (X1700066) | EACH | 25 | $200.00 | $126.43 |
| 5 | PC conc sidewalk 6 SP (X4240440) | SF | 54,323 | $7.40 | $9.86 |
| 6 | Pipe handrail SPL (X5091765) | LF | 50 | $140.00 | $82.20 |
| 7 | Handrail removal (X5091770) | LF | 45 | $10.00 | $10.00 |
| 8 | Sanitary manhole adj (X6026050) | EACH | 2 | $500.00 | $942.66 |
| 9 | Wood rail (X6640632) | LF | 1,016 | $62.00 | $57.95 |
| 10 | Traf cont & prot SPL (X7010216) | LS | 1 | $20,000 | $19,087 |
| 11 | Handhole to BE adjust (X8140115) | EACH | 1 | $1,600.00 | $1,572.48 |
| 12 | Bollards (Z0004002) | EACH | 14 | $1,000.00 | $690.56 |
| 13 | Weld wire fab 6X6 (Z0007120) | SY | 4,633 | $6.00 | $8.99 |
| 14 | Construction layout (Z0013798) | LS | 1 | $15,000 | $24,434 |
| 15 | Trainees (Z0076600) | HR | 500 | $0.80 | $0.80 |
| 16 | Trainees TPG (Z0076604) | HR | 500 | $15.00 | $15.00 |
| 17 | Tree remov over 15 (20100210) | UNIT | 30 | $65.00 | $91.69 |
| 18 | Earth excavation (20200100) | CY | 2,397 | $38.00 | $34.52 |
| 19 | Seeding CL 2 (25000200) | ACRE | 1.25 | $4,000.00 | $3,692.00 |
| 20 | Nitrogen fert nutr (25000400) | LB | 120 | $1.80 | $1.72 |
| 21 | Phosphorus fert nutr (25000500) | LB | 120 | $1.80 | $1.72 |
| 22 | Potassium fert nutr (25000600) | LB | 120 | $1.80 | $1.72 |
| 23 | Mulch method 3 (25100125) | ACRE | 1.25 | $5,000.00 | $4,732.00 |
| 24 | Temp eros contr seed (28000250) | LB | 260 | $1.75 | $17.83 |
| 25 | Temp ditch checks (28000305) | LF | 48 | $27.00 | $46.67 |
| 26 | Perimeter eros bar (28000400) | LF | 4,077 | $2.85 | $4.14 |
| 27 | Inlet & pipe protect (28000500) | EACH | 14 | $200.00 | $156.13 |
| 28 | Stone riprap CL A4 (28100107) | SY | 157 | $64.00 | $86.64 |
| 29 | Filter fabric (28200200) | SY | 157 | $3.00 | $7.70 |
| 30 | Sub gran mat A (31100100) | TON | 1,534 | $44.00 | $59.33 |
| 31 | Aggregate-temp access (40201000) | TON | 6 | $44.00 | $310.76 |
| 32 | PCC PVT 9 jointed (42000401) | SY | 229 | $95.00 | $129.30 |
| 33 | PCC driveway pavt 8 (42300400) | SY | 192 | $90.00 | $155.76 |
| 34 | Detectable warnings (42400800) | SF | 192 | $30.00 | $19.64 |
| 35 | Pavement rem (44000100) | SY | 3,375 | $15.00 | $11.73 |
| 36 | Drive pavement rem (44000200) | SY | 161 | $15.00 | $40.68 |
| 37 | Comb curb gutter rem (44000500) | LF | 362 | $10.00 | $23.60 |
| 38 | Sidewalk rem (44000600) | SF | 12,288 | $2.50 | $2.88 |
| 39 | Pipe culvert remov (50105220) | LF | 104 | $15.00 | $47.49 |
| 40 | P cul CL D 1 12 (542D0217) | LF | 167 | $48.00 | $83.67 |
| 41 | P cul CL D 1 15 (542D0220) | LF | 49 | $57.00 | $137.34 |
| 42 | Metal FL end sec 12" (54262712) | EACH | 11 | $145.00 | $474.32 |
| 43 | Metal FL end sec 15" (54262715) | EACH | 4 | $210.00 | $508.55 |
| 44 | Inlets TA T8G (60236200) | EACH | 1 | $2,900.00 | $4,432.67 |
| 45 | Comb CC&G TB6.12 (60603800) | LF | 40 | $75.00 | $71.94 |
| 46 | Comb CC&G TB6.18 (60604400) | LF | 40 | $75.00 | $74.54 |
| 47 | Comb CC&G TY B-6.24 (60605000) | LF | 282 | $50.00 | $51.15 |
| 48 | Non SPL waste disposl (66900200) | CY | 916 | $55.00 | $57.20 |
| 49 | Soil disposal analy (66900530) | EACH | 3 | $1,200.00 | $1,040.00 |
| 50 | Reg sub P-const plan (66901001) | LS | 1 | $3,400.00 | $3,120.00 |
| 51 | Reg sub F con report (66901003) | LS | 1 | $1,200.00 | $1,040.00 |
| 52 | Reg sub mon (66901006) | CAL DAY | 2 | $1,000.00 | $936.00 |
| 53 | Mobilization (67100100) | LS | 1 | $75,000 | $29,690 |
| 54 | Sign panel T1 (72000100) | SF | 109 | $40.00 | $39.41 |
| 55 | Remov sin pan assy TA (72400100) | EACH | 4 | $100.00 | $122.39 |
| 56 | Rem & rel sign panel asmbly TA (72400205) | EACH | 4 | $500.00 | $244.78 |
| 57 | Rem & rel sign panel asmbly TB (72400210) | EACH | 2 | $500.00 | $244.78 |
| 58 | Teles STL sin support (72800100) | LF | 268 | $20.00 | $15.49 |
| 59 | Paint PVT MK line 4 (78001110) | LF | 1,498 | $2.00 | $4.82 |
| 60 | Paint PVT MK line 24 (78001180) | LF | 383 | $12.00 | $5.60 |
| 61 | PVT MKG rem WTR blast (78300202) | SF | 103 | $7.50 | $22.11 |
| 62 | LP F M 11.5BC 8 5/8X6 (83600352) | EACH | 7 | $4,800.00 | $4,426.24 |
| 63 | LP F M 15BC 8 5/8X6 (83600356) | EACH | 8 | $5,100.00 | $4,750.72 |
| 64 | Rem pole FDN (84200804) | EACH | 15 | $1,200.00 | $1,162.72 |
| 65 | Reloc EX LT unit (84400105) | EACH | 15 | $1,200.00 | $1,072.24 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of January 16, 2026. Compiled by Mirage Metrics.