INDOT contract B-42888-A bid tabulation
BRIDGE DECK REPLACEMENT. Let by Indiana DOT on July 9, 2025, Switzerland, Seymour. 4 bids received; low bid $1,920,428 by Paul H Rohe Company Inc.
- Owner
- Indiana DOT
- Letting
- 09 JUL 2025
- Pay items
- 84
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Paul H Rohe Company Inc | $1,920,428 | Low |
| 2 | Beaty Construction Inc | $2,319,319 | +21% |
| 3 | Milestone Contractors LP | $2,393,208 | +25% |
| 4 | Sunesis Construction Company | $2,577,994 | +34% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Paul H Rohe Company Inc | 2. Beaty Construction Inc | 3. Milestone Contractors LP | 4. Sunesis Construction Company |
|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $12,900 | $50,000 | $12,900 | $23,693 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Mobilization and demobilization (110-01001) | LS | 1 | $80,440 | $115,955 | $117,500 | $166,907 |
| 0010 | Clearing right-of-way (201-52370) | LS | 1 | $9,340.00 | $23,191 | $30,000 | $9,779.74 |
| 0011 | Pavement removal (202-02240) | SYS | 106 | $34.00 | $100.00 | $151.00 | $81.85 |
| 0012 | Present structure, remove portions, structure no. 1 (202-51328) | LS | 1 | $455,730 | $400,000 | $328,000 | $399,951 |
| 0013 | Excavation, common (203-02000) | CYS | 190 | $90.00 | $120.00 | $128.00 | $88.05 |
| 0014 | Stormwater management budget (205-12108) | DOL | 53,680 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0015 | Stormwater management implementation (205-12616) | LS | 1 | $2,500.00 | $35,761 | $18,000 | $24,198 |
| 0016 | Cofferdam (206-51235) | LS | 1 | $59,840 | $100,000 | $48,000 | $139,354 |
| 0017 | Subgrade treatment, type IC (207-09935) | SYS | 712 | $58.00 | $60.00 | $67.00 | $81.40 |
| 0018 | Aggregate for end bent backfill (211-06467) | CYS | 20 | $175.00 | $325.00 | $528.00 | $202.20 |
| 0019 | Geotextile for pavement, type 2B (214-12239) | SYS | 377 | $5.50 | $10.00 | $5.50 | $8.98 |
| 0020 | Compacted aggregate, no. 53 (301-12234) | CYS | 40 | $150.00 | $350.00 | $242.00 | $240.28 |
| 0021 | Subbase for PCCP (302-06464) | CYS | 31 | $150.00 | $300.00 | $565.00 | $290.62 |
| 0022 | Compacted aggregate, no. 53 (303-01180) | TON | 206 | $80.00 | $120.00 | $110.00 | $134.04 |
| 0023 | Compacted aggregate, no. 73 (303-07449) | TON | 29 | $110.00 | $300.00 | $200.00 | $124.98 |
| 0024 | Widening with HMA, type B (304-07493) | TON | 113 | $170.00 | $185.00 | $275.00 | $541.83 |
| 0025 | Milling, transition (306-08043) | SYS | 1,342 | $4.50 | $17.00 | $11.75 | $6.45 |
| 0026 | QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002) | TON | 134 | $190.00 | $205.00 | $240.00 | $206.69 |
| 0027 | QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038) | TON | 115 | $188.00 | $195.00 | $260.00 | $196.61 |
| 0028 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 124 | $186.00 | $185.00 | $242.00 | $186.52 |
| 0029 | Joint adhesive, surface (401-10258) | LFT | 1,680 | $0.50 | $0.60 | $1.35 | $0.60 |
| 0030 | Joint adhesive, intermediate (401-10259) | LFT | 960 | $0.70 | $0.70 | $2.90 | $0.71 |
| 0031 | Asphalt for tack coat (406-05520) | TON | 1 | $950.00 | $1,000.00 | $730.00 | $1,008.23 |
| 0032 | Terminal joint, type HMA (503-12477) | LFT | 60 | $455.00 | $650.00 | $975.00 | $475.12 |
| 0033 | Guardrail, remove (601-02241) | LFT | 528 | $6.00 | $12.75 | $6.00 | $12.85 |
| 0034 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 250 | $22.00 | $21.00 | $22.00 | $21.17 |
| 0035 | Guardrail transition, MGS without curb (601-12292) | EACH | 4 | $3,500.00 | $2,750.00 | $3,500.00 | $2,772.64 |
| 0036 | Guardrail end treatment, type OS (601-94689) | EACH | 4 | $3,200.00 | $3,000.00 | $3,200.00 | $3,024.70 |
| 0037 | Barrier delineator (602-06729) | EACH | 12 | $85.00 | $20.00 | $50.50 | $12.10 |
| 0038 | Reinforced concrete bridge approach, 12 in. (609-06259) | SYS | 157 | $290.00 | $300.00 | $448.00 | $500.30 |
| 0039 | Mailbox assembly, single (611-06497) | EACH | 1 | $325.00 | $350.00 | $325.00 | $435.56 |
| 0040 | Monument, type B (615-06505) | EACH | 2 | $1,175.00 | $1,600.00 | $1,175.00 | $804.51 |
| 0041 | Riprap, revetment (616-06405) | TON | 803 | $75.00 | $120.00 | $150.00 | $221.02 |
| 0042 | Geotextile for riprap, type 1A (616-12246) | SYS | 1,369 | $2.50 | $3.00 | $2.50 | $3.72 |
| 0043 | Clean steel bridge, partial, QP-2, bridge no. 1 (619-11050) | LS | 1 | $23,000 | $23,000 | $23,000 | $23,189 |
| 0044 | Disposal of cleaning waste, hazardous, bridge no. 1 (619-12459) | LS | 1 | $650.00 | $650.00 | $650.00 | $655.35 |
| 0045 | Clean steel bridge, top flanges, type QP-2, bridge no. 1 (619-12506) | LS | 1 | $18,000 | $18,000 | $18,000 | $18,148 |
| 0046 | Coat steel bridge, partial, bridge no. 1 (619-51860) | LS | 1 | $5,500.00 | $5,500.00 | $5,500.00 | $5,545.27 |
| 0047 | Sodding (621-06574) | SYS | 64 | $100.00 | $130.00 | $75.00 | $85.78 |
| 0048 | Computer system equipment (628-11976) | EACH | 3 | $950.00 | $600.00 | $800.00 | $1,052.02 |
| 0049 | Field office, type D (628-12683) | MOS | 12 | $3,300.00 | $6,500.00 | $5,000.00 | $2,652.50 |
| 0050 | Grates, basins, and fittings, cast iron (702-12076) | EACH | 8 | $2,050.00 | $1,500.00 | $3,200.00 | $2,699.15 |
| 0051 | Concrete, A, substructure (702-51005) | CYS | 21 | $2,260.00 | $1,800.00 | $3,200.00 | $2,729.23 |
| 0052 | Field drilled hole in concrete (702-51863) | EACH | 98 | $45.00 | $100.00 | $31.00 | $22.47 |
| 0053 | Reinforcing bars, epoxy coated (703-06029) | LBS | 72,679 | $1.10 | $1.30 | $1.90 | $1.81 |
| 0054 | Threaded tie bar assembly, epoxy coated (703-97936) | EACH | 715 | $48.00 | $65.00 | $40.50 | $82.78 |
| 0055 | Concrete, C, superstructure (704-51002) | CYS | 185.90 | $1,670.00 | $1,700.00 | $2,500.00 | $2,583.10 |
| 0056 | Railing, concrete type FC (706-11600) | CYS | 37.40 | $1,077.00 | $800.00 | $1,203.00 | $1,140.83 |
| 0057 | Concrete bridge railing transition, type TFC (706-11620) | EACH | 4 | $2,500.00 | $6,500.00 | $1,600.00 | $2,614.73 |
| 0058 | Surface seal , STR. no. 1 (709-51821) | LS | 1 | $3,910.00 | $1.00 | $5,825.00 | $17.54 |
| 0059 | Drilled hole (711-51864) | EACH | 36 | $95.00 | $95.00 | $95.00 | $95.78 |
| 0060 | Jacking and supporting steel beams (711-95291) | LS | 1 | $10,750 | $60,000 | $19,000 | $14,259 |
| 0061 | Stud shear connectors (711-96800) | EACH | 5,796 | $3.90 | $3.90 | $3.90 | $4.38 |
| 0062 | Pipe extension, circular, diameter 6 in. , thermosetting (715-06566) | LFT | 28 | $92.00 | $250.00 | $98.00 | $337.54 |
| 0063 | Geotextile for underdrains, type 2B (718-12308) | SYS | 28 | $12.00 | $50.00 | $30.00 | $65.62 |
| 0064 | Longitudinal grooving (722-12732) | SYS | 792 | $8.90 | $9.00 | $16.00 | $12.00 |
| 0065 | Bearing assembly, elastomeric (726-92406) | EACH | 12 | $650.00 | $1,600.00 | $2,300.00 | $2,737.17 |
| 0066 | Construction sign, type D (801-03291) | EACH | 3 | $184.00 | $183.67 | $200.00 | $201.65 |
| 0067 | Temporary pavement marking, removable, 6 in. (801-06209) | LFT | 8,684 | $1.80 | $1.78 | $2.00 | $2.02 |
| 0068 | Temporary transverse pavement marking, removable, 24 in. (801-06218) | LFT | 34 | $9.70 | $9.67 | $10.00 | $10.08 |
| 0069 | Construction sign, type A (801-06640) | EACH | 51 | $218.00 | $217.49 | $200.00 | $201.65 |
| 0070 | Construction sign, type B (801-06645) | EACH | 2 | $112.00 | $110.43 | $100.00 | $100.83 |
| 0071 | Maintaining traffic (801-06775) | LS | 1 | $13,985 | $48,218 | $12,000 | $12,203 |
| 0072 | Energy absorbing terminal, CZ, TL-3 (801-07024) | EACH | 2 | $7,250.00 | $10,000 | $7,250.00 | $5,041.16 |
| 0073 | Barricade, type III-A (801-07118) | LFT | 48 | $19.00 | $18.69 | $20.00 | $20.16 |
| 0074 | Temporary traffic barrier, anchored, type 2 (801-08508) | LFT | 710 | $64.75 | $64.75 | $109.33 | $69.34 |
| 0075 | Portable signal (801-12081) | LS | 1 | $20,080 | $26,000 | $25,000 | $25,206 |
| 0076 | Temporary pavement marking, removable, 7 in. (801-12390) | LFT | 3,222 | $3.10 | $3.04 | $3.00 | $3.02 |
| 0077 | Driveway assistance device (801-12482) | EACH | 3 | $8,200.00 | $10,000 | $7,500.00 | $2,520.58 |
| 0078 | Temporary worksite speed limit sign assembly, continuous (801-12883) | EACH | 4 | $770.00 | $769.59 | $400.00 | $403.29 |
| 0079 | Line, multi-component, solid, white, 6 in. (808-10049) | LFT | 1,324 | $4.25 | $4.25 | $5.00 | $5.04 |
| 0080 | Line, multi-component, solid, yellow, 6 in. (808-10057) | LFT | 13 | $4.25 | $4.25 | $5.00 | $5.04 |
| 0081 | Grooving for pavement markings (808-12032) | LFT | 958 | $6.12 | $6.12 | $2.50 | $2.52 |
| 0082 | Line, multi-component, broken, yellow, 6 in. (808-12841) | LFT | 166 | $4.25 | $4.25 | $5.00 | $5.04 |
| 0083 | Snowplowable raised pavement marker, remove (808-75996) | EACH | 10 | $24.00 | $25.00 | $150.00 | $17.61 |
| 0084 | Snowplowable raised pavement marker (808-75998) | EACH | 4 | $856.00 | $100.00 | $150.00 | $252.06 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of July 9, 2025. Compiled by Mirage Metrics.