INDOT contract B-43228-A bid tabulation
BRIDGE DECK OVERLAY. Let by Indiana DOT on April 9, 2025, Knox, Pike, Vincennes. 4 bids received; low bid $7,456,268 by Ragle, Inc..
- Owner
- Indiana DOT
- Letting
- 09 APR 2025
- Pay items
- 121
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Ragle, Inc. | $7,456,268 | Low |
| 2 | CLR Inc | $7,752,315 | +4.0% |
| 3 | Milestone Contractors LP | $8,749,606 | +17% |
| 4 | American Contracting & Services Inc | $8,773,196 | +18% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Ragle, Inc. | 2. CLR Inc | 3. Milestone Contractors LP | 4. American Contracting & Services Inc |
|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $40,000 | $250,000 | $47,213 | $40,000 |
| 0002 | Inspection hole, deeper than 3 FT (107-09358) | EACH | 2 | $850.00 | $790.00 | $1,200.00 | $500.00 |
| 0003 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0010 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0011 | Mobilization and demobilization (110-01001) | LS | 1 | $372,500 | $387,600 | $437,480 | $438,660 |
| 0012 | Clearing right-of-way (201-52370) | LS | 1 | $223,500 | $232,500 | $262,488 | $263,196 |
| 0013 | Pavement removal (202-02240) | SYS | 442 | $40.00 | $86.00 | $60.00 | $61.65 |
| 0014 | Present structure, remove portions, structure no. 1 (202-51328) | LS | 1 | $100,000 | $150,000 | $149,622 | $130,000 |
| 0015 | Present structure, remove portions, structure no. 2 (202-51328) | LS | 1 | $100,000 | $150,000 | $149,622 | $125,000 |
| 0016 | Excavation, common (203-02000) | CYS | 400 | $36.50 | $53.00 | $104.00 | $255.00 |
| 0017 | Linear grading (203-08607) | LFT | 1,962 | $5.25 | $4.00 | $5.00 | $6.00 |
| 0018 | Stormwater management budget (205-12108) | DOL | 119,100 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0019 | Stormwater management implementation (205-12616) | LS | 1 | $35,000 | $20,000 | $10,000 | $75,000 |
| 0020 | SWQCP preparation (205-12618) | LS | 1 | $2,500.00 | $2,100.00 | $7,500.00 | $5,000.00 |
| 0021 | Cofferdam (206-51235) | LS | 1 | $275,000 | $275,000 | $746,730 | $625,000 |
| 0022 | Subgrade treatment, type II (207-08264) | SYS | 642 | $28.50 | $35.00 | $44.00 | $65.00 |
| 0023 | Aggregate for end bent backfill (211-06467) | CYS | 23 | $140.00 | $200.00 | $201.00 | $250.00 |
| 0024 | Structure backfill, type 1 (211-09264) | CYS | 13 | $140.00 | $250.00 | $560.00 | $150.00 |
| 0025 | Geogrid, type IB (214-11796) | SYS | 1,082 | $2.50 | $3.50 | $5.00 | $4.00 |
| 0026 | Compacted aggregate, no. 2 (301-12231) | CYS | 4 | $135.00 | $600.00 | $513.00 | $300.00 |
| 0027 | Compacted aggregate, no. 53 (301-12234) | CYS | 4 | $165.00 | $600.00 | $511.00 | $300.00 |
| 0028 | Subbase for PCCP (302-06464) | CYS | 116 | $136.50 | $175.00 | $200.00 | $150.00 |
| 0029 | Compacted aggregate, no. 53 (303-01180) | TON | 417 | $46.25 | $96.00 | $73.00 | $70.00 |
| 0030 | Milling, transition (306-08043) | SYS | 1,875 | $2.25 | $9.00 | $10.00 | $15.00 |
| 0031 | QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002) | TON | 207 | $270.00 | $293.00 | $270.00 | $265.00 |
| 0032 | QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038) | TON | 87 | $320.00 | $271.00 | $320.00 | $245.00 |
| 0033 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 204 | $305.00 | $244.00 | $305.00 | $220.00 |
| 0034 | Joint adhesive, surface (401-10258) | LFT | 1,440 | $1.50 | $1.00 | $1.50 | $1.00 |
| 0035 | Joint adhesive, intermediate (401-10259) | LFT | 360 | $2.00 | $1.00 | $2.00 | $1.00 |
| 0036 | Asphalt for tack coat (406-05521) | SYS | 3,103 | $2.50 | $0.35 | $2.50 | $0.35 |
| 0037 | Cracks and joints in asphalt pavement, rout and seal (408-07478) | TON | 2 | $1,200.00 | $1,850.00 | $1,200.00 | $1,850.00 |
| 0038 | Guardrail transition, type TGB (601-01522) | EACH | 1 | $3,750.00 | $3,000.00 | $3,750.00 | $3,750.00 |
| 0039 | Guardrail terminal system, W-beam curved, type 3 (601-01846) | EACH | 1 | $3,375.00 | $2,852.00 | $3,375.00 | $3,375.00 |
| 0040 | Guardrail terminal system, W-beam curved, type 5 (601-01848) | EACH | 1 | $3,375.00 | $3,100.00 | $3,375.00 | $3,375.00 |
| 0041 | Guardrail, remove (601-02241) | LFT | 1,950 | $5.00 | $5.00 | $5.00 | $5.00 |
| 0042 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 1,206.25 | $24.00 | $23.00 | $24.00 | $24.00 |
| 0043 | Guardrail height transition, MGS (601-12289) | EACH | 1 | $995.00 | $1,250.00 | $995.00 | $995.00 |
| 0044 | Guardrail transition, MGS without curb (601-12292) | EACH | 7 | $3,950.00 | $3,325.00 | $3,950.00 | $3,950.00 |
| 0045 | Guardrail end treatment, type OS (601-94689) | EACH | 6 | $3,475.00 | $3,325.00 | $3,475.00 | $3,475.00 |
| 0046 | Guardrail, W-beam, 6 FT 3 in. spacing (601-99105) | LFT | 13 | $32.00 | $26.00 | $32.00 | $32.00 |
| 0047 | Barrier delineator (602-06729) | EACH | 34 | $12.50 | $75.00 | $25.00 | $50.00 |
| 0048 | Reinforced concrete bridge approach, 12 in. (609-06259) | SYS | 440 | $220.00 | $285.00 | $264.00 | $260.00 |
| 0049 | Grout for riprap (616-02281) | CYS | 89 | $385.00 | $275.00 | $328.00 | $400.00 |
| 0050 | Riprap, class 1 (616-05688) | TON | 1,825 | $110.00 | $109.00 | $84.00 | $165.00 |
| 0051 | Riprap, revetment (616-06405) | TON | 1,096 | $95.00 | $215.00 | $91.00 | $100.00 |
| 0052 | Geotextile for riprap, type 1A (616-12246) | SYS | 3,406 | $4.50 | $5.00 | $5.00 | $6.00 |
| 0053 | Clean steel bridge, partial, QP-2, bridge no. 1 (619-11050) | LS | 1 | $40,000 | $27,000 | $35,000 | $35,000 |
| 0054 | Clean steel bridge, partial, QP-2, bridge no. 2 (619-11050) | LS | 1 | $40,000 | $27,000 | $35,000 | $35,000 |
| 0055 | Disposal of cleaning waste, hazardous, bridge no. 1 (619-12459) | LS | 1 | $1,000.00 | $775.00 | $1,000.00 | $1,000.00 |
| 0056 | Disposal of cleaning waste, hazardous, bridge no. 2 (619-12459) | LS | 1 | $1,000.00 | $775.00 | $1,000.00 | $1,000.00 |
| 0057 | Coat steel bridge, partial, bridge no. 1 (619-51860) | LS | 1 | $19,000 | $10,800 | $14,000 | $14,000 |
| 0058 | Coat steel bridge, partial, bridge no. 2 (619-51860) | LS | 1 | $19,000 | $10,800 | $14,000 | $14,000 |
| 0059 | Mobilization and demobilization for seeding (621-01004) | EACH | 4 | $500.00 | $500.00 | $1,150.00 | $500.00 |
| 0060 | Mulched seeding, type R (621-06559) | SYS | 6,211 | $2.30 | $2.30 | $1.18 | $2.30 |
| 0061 | Sodding (621-06574) | SYS | 230 | $25.00 | $21.00 | $31.70 | $21.00 |
| 0062 | Seed mixture, emergent wetland (621-06737) | LBS | 39 | $200.00 | $225.00 | $164.00 | $200.00 |
| 0063 | Seed mixture, floodplain (621-12612) | LBS | 30 | $125.00 | $140.00 | $159.00 | $125.00 |
| 0064 | Sign, "DO not mow or spray" (622-52436) | EACH | 4 | $110.00 | $125.00 | $133.40 | $110.00 |
| 0065 | Computer system equipment (628-11976) | EACH | 2 | $750.00 | $200.00 | $500.00 | $2,000.00 |
| 0066 | Field office, type D (628-12683) | MOS | 18 | $3,000.00 | $1,400.00 | $5,000.00 | $6,000.00 |
| 0067 | Plant growth layer (629-12029) | SYS | 9,961 | $5.00 | $5.00 | $18.57 | $5.00 |
| 0068 | Reinforcing bars, epoxy coated (703-06029) | LBS | 39,228 | $2.00 | $3.03 | $2.75 | $1.95 |
| 0069 | Threaded tie bar assembly, epoxy coated (703-97936) | EACH | 376 | $50.00 | $42.00 | $50.00 | $45.00 |
| 0070 | Concrete, C, superstructure (704-51002) | CYS | 63.60 | $2,250.00 | $3,150.00 | $4,492.00 | $2,000.00 |
| 0071 | Railing, concrete type FC (706-11600) | CYS | 1.20 | $4,100.00 | $21,000 | $28,356 | $5,000.00 |
| 0072 | Railing, concrete type FC , modified (706-11600) | CYS | 2.80 | $4,100.00 | $2,775.00 | $15,118 | $4,500.00 |
| 0073 | Concrete bridge railing transition, type TFC (706-11620) | EACH | 4 | $5,100.00 | $6,000.00 | $3,965.00 | $3,000.00 |
| 0074 | Concrete bridge railing transition, type TFC , modified (706-11620) | EACH | 4 | $5,100.00 | $6,000.00 | $4,465.00 | $3,000.00 |
| 0075 | Surface seal , bridge no. 1 (709-51821) | LS | 1 | $24,961 | $32,000 | $29,611 | $25,552 |
| 0076 | Surface seal , bridge no. 2 (709-51821) | LS | 1 | $19,871 | $26,000 | $29,611 | $23,510 |
| 0077 | Structural steel, field cut , modified (711-04297) | SQIN | 132 | $90.00 | $65.00 | $89.00 | $89.00 |
| 0078 | Drilled hole (711-51864) | EACH | 44 | $40.00 | $125.00 | $85.00 | $85.00 |
| 0079 | Jacking and supporting girders , bridge no. 1 (711-51878) | LS | 1 | $70,000 | $50,000 | $64,733 | $29,400 |
| 0080 | Jacking and supporting girders , bridge no. 2 (711-51878) | LS | 1 | $70,000 | $53,000 | $64,733 | $29,400 |
| 0081 | Temporary causeway , bridge no. 2 (713-04331) | LS | 1 | $1,275,000 | $725,000 | $1,492,693 | $1,340,000 |
| 0082 | Pipe, type 4, circular, diameter 6 in. (715-05048) | LFT | 240 | $28.50 | $20.00 | $15.00 | $35.00 |
| 0083 | Pipe, underdrain outlet, diameter 6 in. (715-05053) | LFT | 298 | $22.50 | $30.00 | $24.00 | $40.00 |
| 0084 | Pipe, end bent drain, diameter 6 in. (715-05407) | LFT | 80 | $20.00 | $90.00 | $25.00 | $40.00 |
| 0085 | Pipe, roadway drain casting extension (715-10238) | EACH | 22 | $1,350.00 | $775.00 | $735.00 | $1,300.00 |
| 0086 | Outlet protector, type 1 (718-06528) | EACH | 18 | $1,200.00 | $1,500.00 | $370.00 | $1,700.00 |
| 0087 | Geotextile for underdrains, type 1A (718-12305) | SYS | 598 | $3.50 | $3.00 | $5.00 | $5.00 |
| 0088 | Aggregate for underdrains (718-52610) | CYS | 40 | $90.00 | $150.00 | $251.00 | $150.00 |
| 0089 | Hydrodemolition (722-01066) | SYS | 10,261 | $68.25 | $105.00 | $70.00 | $100.00 |
| 0090 | Bridge deck overlay budget (722-12380) | DOL | 143,384 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0091 | Bridge deck, remove existing concrete surface (722-12464) | SYS | 10,307 | $4.50 | $4.25 | $5.00 | $10.00 |
| 0092 | Longitudinal grooving (722-12732) | SYS | 10,752 | $3.75 | $7.50 | $5.00 | $8.00 |
| 0093 | Bridge deck patching, full depth (722-51401) | SFT | 2,783 | $50.00 | $20.00 | $7.00 | $50.00 |
| 0094 | Overlay dam (722-51874) | SFT | 191 | $50.00 | $35.00 | $42.00 | $70.00 |
| 0095 | Bridge expansion joint, type M, replace (724-12775) | LFT | 200 | $3,300.00 | $2,230.00 | $3,458.00 | $2,400.00 |
| 0096 | Construction sign, type D (801-03291) | EACH | 3 | $172.00 | $170.00 | $287.00 | $150.00 |
| 0097 | Road closure sign assembly (801-04308) | EACH | 2 | $472.00 | $300.00 | $296.00 | $200.00 |
| 0098 | Temporary pavement marking, removable, 6 in. (801-06209) | LFT | 36,700 | $1.90 | $1.90 | $1.88 | $1.90 |
| 0099 | Temporary transverse pavement marking, removable, 24 in. (801-06218) | LFT | 72 | $10.62 | $15.00 | $11.64 | $12.00 |
| 0100 | Construction sign, type A (801-06640) | EACH | 24 | $331.00 | $225.00 | $229.00 | $200.00 |
| 0101 | Construction sign, type B (801-06645) | EACH | 12 | $124.00 | $100.00 | $118.00 | $100.00 |
| 0102 | Maintaining traffic (801-06775) | LS | 1 | $75,000 | $206,085 | $74,366 | $140,000 |
| 0103 | Energy absorbing terminal, CZ, TL-3 (801-07024) | EACH | 8 | $7,500.00 | $11,500 | $11,250 | $12,000 |
| 0104 | Barricade, type III-A (801-07118) | LFT | 24 | $23.00 | $25.00 | $15.94 | $16.00 |
| 0105 | Temporary traffic barrier, type 2 (801-08401) | LFT | 3,850 | $50.00 | $45.00 | $31.00 | $70.00 |
| 0106 | Temporary traffic barrier, anchored, type 2 (801-08508) | LFT | 240 | $55.00 | $160.00 | $60.00 | $75.00 |
| 0107 | Portable signal (801-12081) | LS | 1 | $70,000 | $50,000 | $25,619 | $40,000 |
| 0108 | Portable signal , bridge no. 2 (801-12081) | LS | 1 | $70,000 | $80,000 | $25,619 | $25,000 |
| 0109 | Driveway assistance device (801-12482) | EACH | 3 | $15,000 | $3,000.00 | $2,628.00 | $3,000.00 |
| 0110 | Temporary worksite speed limit sign assembly, continuous (801-12883) | EACH | 3 | $455.00 | $445.00 | $1,351.00 | $400.00 |
| 0111 | Temporary buzz strips (801-97643) | LFT | 1,728 | $25.31 | $22.50 | $19.80 | $20.00 |
| 0112 | Reference post (802-04893) | EACH | 4 | $275.00 | $250.00 | $275.00 | $275.00 |
| 0113 | Sign, ground mounted, reset (802-91122) | EACH | 9 | $375.00 | $150.00 | $375.00 | $375.00 |
| 0114 | Line, remove (808-06716) | LFT | 10,069 | $1.05 | $0.50 | $0.64 | $0.50 |
| 0115 | Line, paint, broken, yellow, 6 in. (808-12764) | LFT | 983 | $0.85 | $0.85 | $1.88 | $0.75 |
| 0116 | Line, paint, solid, white, 6 in. (808-75007) | LFT | 10,498 | $0.38 | $0.60 | $0.64 | $0.60 |
| 0117 | Line, paint, solid, yellow, 6 in. (808-75047) | LFT | 486 | $5.56 | $0.75 | $0.64 | $0.60 |
| 0118 | Snowplowable raised pavement marker, remove (808-75996) | EACH | 36 | $20.00 | $25.00 | $34.43 | $30.00 |
| 0119 | Snowplowable raised pavement marker (808-75998) | EACH | 22 | $125.00 | $75.00 | $78.00 | $125.00 |
| 0120 | Bridge deck overlay, latex modified (722-51842) | SYS | 10,337 | $100.00 | |||
| 0121 | Bridge deck overlay, silica fume modified (722-01061) | SYS | 10,337 | $82.00 | $90.00 | $105.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of April 9, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.