INDOT contract B-43492-A bid tabulation
BRIDGE COATING, SUBSTRUCTURE REPAIR AND REHABILITATION. Let by Indiana DOT on September 2, 2026, Delaware, Greenfield. 4 bids received; low bid $6,049,500 by E & B Paving LLC.
- Owner
- Indiana DOT
- Letting
- 02 SEP 2026
- Pay items
- 137
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | E & B Paving LLC | $6,049,500 | Low |
| 2 | Milestone Contractors LP | $7,075,791 | +17% |
| 3 | Beaty Construction Inc | $8,572,500 | +42% |
| 4 | Southern Road & Bridge, LLC | $14,812,186 | +145% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. E & B Paving LLC | 2. Milestone Contractors LP | 3. Beaty Construction Inc | 4. Southern Road & Bridge, LLC |
|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $120,255 | $26,125 | $2,000.00 | $150,000 |
| 0002 | Railroad flagging budget (107-12976) | DOL | 123,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices and markings (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, pavement traffic markings (109-09377) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0010 | Mobilization and demobilization (110-01001) | LS | 1 | $450,000 | $350,750 | $303,396 | $1,425,000 |
| 0011 | Present structure, remove portions, structure no. 01 (202-51328) | LS | 1 | $20,000 | $39,200 | $25,000 | $75,000 |
| 0012 | Present structure, remove portions, structure no. 02 (202-51328) | LS | 1 | $20,000 | $39,200 | $25,000 | $75,000 |
| 0013 | Present structure, remove portions, structure no. 03 (202-51328) | LS | 1 | $20,000 | $46,700 | $25,000 | $75,000 |
| 0014 | Present structure, remove portions, structure no. 04 (202-51328) | LS | 1 | $20,000 | $46,700 | $25,000 | $75,000 |
| 0015 | Present structure, remove portions, structure no. 05 (202-51328) | LS | 1 | $20,000 | $45,700 | $25,000 | $75,000 |
| 0016 | Present structure, remove portions, structure no. 06 (202-51328) | LS | 1 | $20,000 | $45,700 | $25,000 | $75,000 |
| 0017 | Present structure, remove portions, structure no. 07 (202-51328) | LS | 1 | $20,000 | $55,000 | $25,000 | $75,000 |
| 0018 | Present structure, remove portions, structure no. 08 (202-51328) | LS | 1 | $20,000 | $55,000 | $25,000 | $75,000 |
| 0019 | Present structure, remove portions, structure no. 09 (202-51328) | LS | 1 | $20,000 | $39,200 | $25,000 | $75,000 |
| 0020 | Present structure, remove portions, structure no. 10 (202-51328) | LS | 1 | $20,000 | $39,200 | $25,000 | $75,000 |
| 0021 | Present structure, remove portions, structure no. 11 (202-51328) | LS | 1 | $20,000 | $39,200 | $25,000 | $75,000 |
| 0022 | Present structure, remove portions, structure no. 12 (202-51328) | LS | 1 | $20,000 | $39,200 | $25,000 | $75,000 |
| 0023 | Present structure, remove portions, structure no. 13 (202-51328) | LS | 1 | $20,000 | $39,200 | $25,000 | $75,000 |
| 0024 | Present structure, remove portions, structure no. 14 (202-51328) | LS | 1 | $20,000 | $39,200 | $25,000 | $75,000 |
| 0025 | Present structure, remove portions, structure no. 15 (202-51328) | LS | 1 | $20,000 | $39,200 | $25,000 | $75,000 |
| 0026 | Present structure, remove portions, structure no. 16 (202-51328) | LS | 1 | $20,000 | $44,500 | $25,000 | $75,000 |
| 0027 | Present structure, remove portions, structure no. 17 (202-51328) | LS | 1 | $20,000 | $47,500 | $25,000 | $75,000 |
| 0028 | Present structure, remove portions, structure no. 18 (202-51328) | LS | 1 | $20,000 | $47,500 | $25,000 | $75,000 |
| 0029 | Slopewall, remove (202-51368) | SYS | 469 | $250.00 | $295.00 | $500.00 | $95.00 |
| 0030 | Inlet, remove (202-91385) | EACH | 4 | $500.00 | $4,200.00 | $2,000.00 | $5,000.00 |
| 0031 | Drilled hole for flowable backfill (213-08068) | EACH | 7 | $1,000.00 | $350.00 | $400.00 | $650.00 |
| 0032 | Flowable backfill, non- removable (213-09269) | CYS | 224 | $650.00 | $650.00 | $400.00 | $805.00 |
| 0033 | HMA patching, partial depth, type C (304-12626) | TON | 81 | $1,075.55 | $495.00 | $1,075.00 | $1,500.00 |
| 0034 | Milling, asphalt, 5 in. (306-11619) | SYS | 288 | $215.00 | $63.00 | $300.00 | $350.00 |
| 0035 | Joints in PCCP, filled (507-08271) | LFT | 1,728 | $10.00 | $33.00 | $24.00 | $40.00 |
| 0036 | Slopewall, concrete, 4 in. (616-51367) | SYS | 469 | $200.00 | $340.00 | $125.00 | $255.00 |
| 0037 | Clean steel bridge, QP-2, bridge no. 01 (619-11052) | LS | 1 | $105,000 | $109,000 | $105,000 | $30,000 |
| 0038 | Clean steel bridge, QP-2, bridge no. 02 (619-11052) | LS | 1 | $105,000 | $109,000 | $105,000 | $30,000 |
| 0039 | Clean steel bridge, QP-2, bridge no. 03 (619-11052) | LS | 1 | $71,000 | $74,000 | $71,000 | $30,000 |
| 0040 | Clean steel bridge, QP-2, bridge no. 04 (619-11052) | LS | 1 | $71,000 | $74,000 | $71,000 | $30,000 |
| 0041 | Clean steel bridge, QP-2, bridge no. 05 (619-11052) | LS | 1 | $76,000 | $79,000 | $76,000 | $50,000 |
| 0042 | Clean steel bridge, QP-2, bridge no. 06 (619-11052) | LS | 1 | $76,000 | $79,000 | $76,000 | $50,000 |
| 0043 | Clean steel bridge, QP-2, bridge no. 07 (619-11052) | LS | 1 | $95,000 | $99,000 | $95,000 | $35,000 |
| 0044 | Clean steel bridge, QP-2, bridge no. 08 (619-11052) | LS | 1 | $95,000 | $99,000 | $95,000 | $35,000 |
| 0045 | Clean steel bridge, QP-2, bridge no. 17 (619-11052) | LS | 1 | $155,000 | $160,000 | $155,000 | $75,000 |
| 0046 | Clean steel bridge, QP-2, bridge no. 18 (619-11052) | LS | 1 | $155,000 | $160,000 | $155,000 | $75,000 |
| 0047 | Disposal of cleaning waste, hazardous, bridge no. 01 (619-12459) | LS | 1 | $1,000.00 | $1,050.00 | $1,000.00 | $5,000.00 |
| 0048 | Disposal of cleaning waste, hazardous, bridge no. 02 (619-12459) | LS | 1 | $1,000.00 | $1,050.00 | $1,000.00 | $5,000.00 |
| 0049 | Disposal of cleaning waste, hazardous, bridge no. 03 (619-12459) | LS | 1 | $1,000.00 | $1,050.00 | $1,000.00 | $4,500.00 |
| 0050 | Disposal of cleaning waste, hazardous, bridge no. 04 (619-12459) | LS | 1 | $1,000.00 | $1,050.00 | $1,000.00 | $4,500.00 |
| 0051 | Disposal of cleaning waste, hazardous, bridge no. 05 (619-12459) | LS | 1 | $1,000.00 | $1,050.00 | $1,000.00 | $4,500.00 |
| 0052 | Disposal of cleaning waste, hazardous, bridge no. 06 (619-12459) | LS | 1 | $1,000.00 | $1,050.00 | $1,000.00 | $4,500.00 |
| 0053 | Disposal of cleaning waste, hazardous, bridge no. 07 (619-12459) | LS | 1 | $1,000.00 | $1,050.00 | $1,000.00 | $4,500.00 |
| 0054 | Disposal of cleaning waste, hazardous, bridge no. 08 (619-12459) | LS | 1 | $1,000.00 | $1,050.00 | $1,000.00 | $4,500.00 |
| 0055 | Disposal of cleaning waste, hazardous, bridge no. 17 (619-12459) | LS | 1 | $1,000.00 | $1,050.00 | $1,000.00 | $8,500.00 |
| 0056 | Disposal of cleaning waste, hazardous, bridge no. 18 (619-12459) | LS | 1 | $1,000.00 | $1,050.00 | $1,000.00 | $8,500.00 |
| 0057 | Coat steel bridge, bridge no. 01 (619-51859) | LS | 1 | $51,000 | $53,000 | $51,000 | $350,000 |
| 0058 | Coat steel bridge, bridge no. 02 (619-51859) | LS | 1 | $51,000 | $53,000 | $51,000 | $350,000 |
| 0059 | Coat steel bridge, bridge no. 03 (619-51859) | LS | 1 | $40,000 | $41,000 | $40,000 | $350,000 |
| 0060 | Coat steel bridge, bridge no. 04 (619-51859) | LS | 1 | $40,000 | $41,000 | $40,000 | $350,000 |
| 0061 | Coat steel bridge, bridge no. 05 (619-51859) | LS | 1 | $40,000 | $41,000 | $40,000 | $375,000 |
| 0062 | Coat steel bridge, bridge no. 06 (619-51859) | LS | 1 | $40,000 | $41,000 | $40,000 | $375,000 |
| 0063 | Coat steel bridge, bridge no. 07 (619-51859) | LS | 1 | $48,000 | $50,000 | $48,000 | $375,000 |
| 0064 | Coat steel bridge, bridge no. 08 (619-51859) | LS | 1 | $48,000 | $50,000 | $48,000 | $375,000 |
| 0065 | Coat steel bridge, bridge no. 17 (619-51859) | LS | 1 | $80,000 | $83,000 | $80,000 | $850,000 |
| 0066 | Coat steel bridge, bridge no. 18 (619-51859) | LS | 1 | $80,000 | $83,000 | $80,000 | $850,000 |
| 0067 | Clean drains (619-98427) | EACH | 42 | $400.00 | $1,550.00 | $600.00 | $650.00 |
| 0068 | Field office, type C (628-09403) | MOS | 15 | $3,200.00 | $3,800.00 | $3,800.00 | $4,000.00 |
| 0069 | Field drilled hole in concrete (702-51863) | EACH | 1,101 | $35.00 | $130.00 | $115.00 | $185.00 |
| 0070 | Patching concrete structures (710-09158) | SFT | 155 | $184.00 | $210.00 | $250.00 | $345.00 |
| 0071 | Repair , steel beam (711-05728) | EACH | 2 | $50,000 | $28,000 | $21,000 | $32,500 |
| 0072 | Repair , steel core (711-05728) | EACH | 3 | $500.00 | $4,200.00 | $600.00 | $8,500.00 |
| 0073 | Repair , uplift restraints (711-05728) | EACH | 5 | $5,000.00 | $3,500.00 | $1,100.00 | $12,500 |
| 0074 | Jacking and supporting structural steel , bridge no. 01 (711-93035) | LS | 1 | $20,000 | $12,600 | $96,000 | $70,000 |
| 0075 | Jacking and supporting structural steel , bridge no. 02 (711-93035) | LS | 1 | $20,000 | $12,600 | $86,000 | $70,000 |
| 0076 | Jacking and supporting structural steel , bridge no. 03 (711-93035) | LS | 1 | $11,900 | $13,800 | $96,000 | $70,000 |
| 0077 | Jacking and supporting structural steel , bridge no. 04 (711-93035) | LS | 1 | $11,900 | $13,800 | $96,000 | $70,000 |
| 0078 | Jacking and supporting structural steel , bridge no. 05 (711-93035) | LS | 1 | $13,600 | $14,600 | $91,000 | $70,000 |
| 0079 | Jacking and supporting structural steel , bridge no. 06 (711-93035) | LS | 1 | $13,600 | $14,600 | $91,000 | $70,000 |
| 0080 | Jacking and supporting structural steel , bridge no. 07 (711-93035) | LS | 1 | $20,000 | $14,000 | $97,000 | $70,000 |
| 0081 | Jacking and supporting structural steel , bridge no. 08 (711-93035) | LS | 1 | $20,000 | $14,000 | $97,000 | $70,000 |
| 0082 | Jacking and supporting structural steel , bridge no. 09 (711-93035) | LS | 1 | $21,250 | $15,700 | $104,000 | $70,000 |
| 0083 | Jacking and supporting structural steel , bridge no. 10 (711-93035) | LS | 1 | $14,450 | $13,800 | $96,000 | $70,000 |
| 0084 | Jacking and supporting structural steel , bridge no. 11 (711-93035) | LS | 1 | $18,750 | $13,800 | $97,000 | $70,000 |
| 0085 | Jacking and supporting structural steel , bridge no. 12 (711-93035) | LS | 1 | $18,750 | $13,800 | $91,000 | $70,000 |
| 0086 | Jacking and supporting structural steel , bridge no. 13 (711-93035) | LS | 1 | $20,000 | $13,800 | $97,000 | $70,000 |
| 0087 | Jacking and supporting structural steel , bridge no. 14 (711-93035) | LS | 1 | $20,000 | $13,800 | $97,000 | $70,000 |
| 0088 | Jacking and supporting structural steel , bridge no. 15 (711-93035) | LS | 1 | $20,000 | $13,800 | $97,000 | $70,000 |
| 0089 | Jacking and supporting structural steel , bridge no. 16 (711-93035) | LS | 1 | $20,000 | $13,800 | $91,000 | $70,000 |
| 0090 | Jacking and supporting structural steel , bridge no. 17 (711-93035) | LS | 1 | $17,500 | $12,800 | $91,000 | $70,000 |
| 0091 | Jacking and supporting structural steel , bridge no. 18 (711-93035) | LS | 1 | $17,500 | $12,800 | $91,000 | $70,000 |
| 0092 | Concrete for patching bridge expansion joint (724-12461) | SFT | 2,156 | $125.00 | $165.00 | $225.00 | $295.00 |
| 0093 | Bridge expansion joint, type PCF (724-12773) | LFT | 1,854 | $45.00 | $160.00 | $95.00 | $85.00 |
| 0094 | Bearing assembly, elastomeric (726-92406) | EACH | 274 | $3,500.00 | $4,500.00 | $3,500.00 | $7,150.00 |
| 0095 | Epoxy injection, epoxy injection adhesive (727-000188) | GAL | 100 | $55.00 | $58.00 | $72.36 | $85.00 |
| 0096 | Epoxy injection, crack preparation (727-90308) | LFT | 960 | $40.00 | $42.00 | $52.63 | $135.00 |
| 0097 | Epoxy injection, furnishing equipment , bridge no. 01 (727-93560) | LS | 1 | $200.00 | $210.00 | $263.14 | $1,000.00 |
| 0098 | Epoxy injection, furnishing equipment , bridge no. 02 (727-93560) | LS | 1 | $200.00 | $210.00 | $263.14 | $1,000.00 |
| 0099 | Epoxy injection, furnishing equipment , bridge no. 03 (727-93560) | LS | 1 | $200.00 | $210.00 | $263.14 | $1,000.00 |
| 0100 | Epoxy injection, furnishing equipment , bridge no. 04 (727-93560) | LS | 1 | $200.00 | $210.00 | $263.14 | $1,000.00 |
| 0101 | Epoxy injection, furnishing equipment , bridge no. 05 (727-93560) | LS | 1 | $200.00 | $210.00 | $263.14 | $1,000.00 |
| 0102 | Epoxy injection, furnishing equipment , bridge no. 06 (727-93560) | LS | 1 | $200.00 | $210.00 | $263.14 | $1,000.00 |
| 0103 | Epoxy injection, furnishing equipment , bridge no. 07 (727-93560) | LS | 1 | $200.00 | $210.00 | $263.14 | $1,000.00 |
| 0104 | Epoxy injection, furnishing equipment , bridge no. 08 (727-93560) | LS | 1 | $200.00 | $210.00 | $263.14 | $1,000.00 |
| 0105 | Epoxy injection, furnishing equipment , bridge no. 09 (727-93560) | LS | 1 | $200.00 | $210.00 | $263.14 | $1,000.00 |
| 0106 | Epoxy injection, furnishing equipment , bridge no. 10 (727-93560) | LS | 1 | $200.00 | $210.00 | $263.14 | $1,000.00 |
| 0107 | Epoxy injection, furnishing equipment , bridge no. 11 (727-93560) | LS | 1 | $200.00 | $210.00 | $263.14 | $1,000.00 |
| 0108 | Epoxy injection, furnishing equipment , bridge no. 12 (727-93560) | LS | 1 | $200.00 | $210.00 | $263.14 | $1,000.00 |
| 0109 | Epoxy injection, furnishing equipment , bridge no. 13 (727-93560) | LS | 1 | $200.00 | $210.00 | $263.14 | $1,000.00 |
| 0110 | Epoxy injection, furnishing equipment , bridge no. 14 (727-93560) | LS | 1 | $200.00 | $210.00 | $263.14 | $1,000.00 |
| 0111 | Epoxy injection, furnishing equipment , bridge no. 15 (727-93560) | LS | 1 | $200.00 | $210.00 | $263.14 | $1,000.00 |
| 0112 | Epoxy injection, furnishing equipment , bridge no. 16 (727-93560) | LS | 1 | $200.00 | $210.00 | $263.14 | $1,000.00 |
| 0113 | Epoxy injection, furnishing equipment , bridge no. 17 (727-93560) | LS | 1 | $200.00 | $210.00 | $263.14 | $1,000.00 |
| 0114 | Epoxy injection, furnishing equipment , bridge no. 18 (727-93560) | LS | 1 | $200.00 | $210.00 | $263.14 | $1,000.00 |
| 0115 | Construction sign, type C (801-03290) | EACH | 2 | $495.00 | $519.00 | $300.00 | $300.00 |
| 0116 | Construction sign, type D (801-03291) | EACH | 2 | $495.00 | $519.00 | $300.00 | $400.00 |
| 0117 | Road closure sign assembly (801-04308) | EACH | 24 | $195.00 | $205.00 | $400.00 | $315.00 |
| 0118 | Temporary pavement marking, removable, 6 in. (801-06209) | LFT | 140,546 | $0.95 | $2.05 | $2.00 | $2.80 |
| 0119 | Detour route marker assembly (801-06625) | EACH | 125 | $125.00 | $132.00 | $250.00 | $220.00 |
| 0120 | Construction sign, type A (801-06640) | EACH | 43 | $150.00 | $158.00 | $300.00 | $300.00 |
| 0121 | Construction sign, type B (801-06645) | EACH | 6 | $120.00 | $125.00 | $150.00 | $145.00 |
| 0122 | Flashing arrow sign (801-06710) | DAY | 360 | $10.00 | $11.00 | $20.00 | $22.00 |
| 0123 | Maintaining traffic (801-06775) | LS | 1 | $616,900 | $425,461 | $1,247,758 | $625,000 |
| 0124 | Barricade, type III-A (801-07118) | LFT | 168 | $12.00 | $13.00 | $25.00 | $22.00 |
| 0125 | Barricade, type III-B (801-07119) | LFT | 24 | $12.00 | $13.00 | $25.00 | $22.00 |
| 0126 | Portable changeable message sign (801-11642) | EACH | 2 | $8,000.00 | $8,385.00 | $7,000.00 | $7,000.00 |
| 0127 | Truck mounted attenuator (801-12042) | DAY | 180 | $500.00 | $700.00 | $560.00 | $300.00 |
| 0128 | Temporary pedestrian channelizer (801-12862) | LFT | 48 | $35.00 | $50.00 | $95.00 | $105.00 |
| 0129 | Temporary worksite speed limit sign assembly, continuous (801-12883) | EACH | 12 | $750.00 | $790.00 | $1,200.00 | $1,250.00 |
| 0130 | Line, remove (808-06716) | LFT | 54,085 | $0.25 | $0.70 | $1.00 | $1.00 |
| 0131 | Retro-reflectivity testing (808-09381) | LS | 1 | $8,500.00 | $8,900.00 | $4,000.00 | $5,500.00 |
| 0132 | Line, multi-component, solid, white, 6 in. (808-10049) | LFT | 25,934 | $1.00 | $1.20 | $0.79 | $1.00 |
| 0133 | Line, multi-component, solid, yellow, 6 in. (808-10057) | LFT | 16,289 | $1.00 | $1.20 | $0.79 | $1.00 |
| 0134 | Line, multi-component, broken, white, 6 in. (808-10071) | LFT | 9,865 | $1.00 | $1.40 | $0.84 | $1.20 |
| 0135 | Grooving for pavement markings (808-12032) | LFT | 54,286 | $0.25 | $0.50 | $0.69 | $1.00 |
| 0136 | Line, multi-component, dotted, white, 6 in. (808-12353) | LFT | 966 | $1.50 | $3.00 | $1.94 | $3.00 |
| 0137 | Line, multi-component, solid, white, 10 in. (808-12781) | LFT | 1,232 | $3.00 | $6.75 | $2.04 | $3.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of September 2, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.