INDOT contract B-43885-A bid tabulation
SMALL STRUCTURE PIPE LINING AND DRAINS CONSTRUCTION. Let by Indiana DOT on October 8, 2025, Randolph, Greenfield. 5 bids received; low bid $359,045 by Indiana Earthworks, LLC.
- Owner
- Indiana DOT
- Letting
- 08 OCT 2025
- Pay items
- 45
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Indiana Earthworks, LLC | $359,045 | Low |
| 2 | 3D Company Inc | $454,413 | +27% |
| 3 | Morphey Construction Inc. | $466,150 | +30% |
| 4 | Yarberry Companies Inc | $502,569 | +40% |
| 5 | Temple & Temple Excavating & Paving Inc | $597,693 | +66% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Indiana Earthworks, LLC | 2. 3D Company Inc | 3. Morphey Construction Inc. | 4. Yarberry Companies Inc | 5. Temple & Temple Excavating & Paving Inc |
|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $7,350.00 | $6,085.00 | $10,000 | $10,000 | $8,000.00 |
| 0002 | Inspection hole, deeper than 3 FT (107-09358) | EACH | 6 | $800.00 | $880.00 | $350.00 | $800.00 | $600.00 |
| 0003 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0010 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0011 | Mobilization and demobilization (110-01001) | LS | 1 | $20,000 | $57,800 | $40,000 | $25,000 | $55,000 |
| 0012 | Clearing right-of-way (201-52370) | LS | 1 | $5,000.00 | $7,880.00 | $8,500.00 | $20,000 | $18,000 |
| 0013 | Present structure, remove portions, structure no. 1 (202-51328) | LS | 1 | $7,600.00 | $6,925.00 | $5,000.00 | $15,000 | $20,000 |
| 0014 | Pipe, remove (202-96133) | LFT | 68 | $45.00 | $100.90 | $100.00 | $200.00 | $180.00 |
| 0015 | Excavation, unclassified (203-02020) | CYS | 4 | $65.00 | $229.00 | $150.00 | $500.00 | $800.00 |
| 0016 | Pump around (205-11626) | EACH | 1 | $5,000.00 | $15,450 | $10,000 | $45,000 | $50,000 |
| 0017 | Stormwater management budget (205-12108) | DOL | 30,680 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0018 | Stormwater management implementation (205-12616) | LS | 1 | $5,500.00 | $9,690.00 | $20,000 | $15,000 | $30,000 |
| 0019 | Flowable backfill, non- removable (213-09269) | CYS | 37 | $285.00 | $200.08 | $280.00 | $250.00 | $260.00 |
| 0020 | Compacted aggregate, no. 53 (303-01180) | TON | 3 | $106.00 | $235.00 | $220.00 | $350.00 | $800.00 |
| 0021 | Joint adhesive (401-11526) | LFT | 54 | $34.50 | $22.00 | $1.00 | $10.00 | $1.00 |
| 0022 | Asphalt for tack coat (406-05521) | SYS | 95 | $1.00 | $1.10 | $1.00 | $10.00 | $1.00 |
| 0023 | Fence, farm field, 47 in. (603-06040) | LFT | 105 | $63.00 | $50.95 | $65.00 | $35.00 | $80.00 |
| 0024 | Riprap, class 1 (616-05688) | TON | 41 | $112.00 | $135.20 | $220.00 | $250.00 | $200.00 |
| 0025 | Riprap, revetment (616-06405) | TON | 18 | $80.00 | $106.10 | $220.00 | $250.00 | $100.00 |
| 0026 | Geotextile for riprap, type 1A (616-12246) | SYS | 125 | $7.00 | $4.65 | $5.00 | $20.00 | $10.00 |
| 0027 | Mobilization and demobilization for seeding (621-01004) | EACH | 2 | $1,000.00 | $700.00 | $825.00 | $750.00 | $250.00 |
| 0028 | Erosion control blanket (621-02770) | SYS | 201 | $10.00 | $5.35 | $15.00 | $15.00 | $4.00 |
| 0029 | Mulched seeding, type R (621-06559) | SYS | 1,269 | $3.25 | $4.60 | $10.00 | $2.00 | $8.00 |
| 0030 | Pipe, type 1, circular, diameter 24 in. (715-05123) | LFT | 63 | $195.00 | $302.00 | $425.00 | $320.00 | $240.00 |
| 0031 | Pipe, type 4, circular, diameter 15 in. (715-05208) | LFT | 5 | $95.00 | $410.00 | $300.00 | $400.00 | $600.00 |
| 0032 | Concrete anchor, diameter 54 in. (715-06492) | EACH | 2 | $4,500.00 | $8,090.00 | $18,000 | $5,000.00 | $11,500 |
| 0033 | HMA for structure installation, type C (715-08306) | TON | 22 | $1,725.00 | $1,125.00 | $565.00 | $350.00 | $250.00 |
| 0034 | Pipe liner, cured-in- place, 51 in. (725-11421) | LFT | 84 | $1,800.00 | $1,625.00 | $1,750.00 | $2,083.00 | $3,000.00 |
| 0035 | Road closure sign assembly (801-04308) | EACH | 7 | $86.00 | $300.00 | $75.00 | $110.00 | $90.00 |
| 0036 | Detour route marker assembly (801-06625) | EACH | 21 | $86.00 | $175.00 | $75.00 | $110.00 | $90.00 |
| 0037 | Construction sign, type A (801-06640) | EACH | 28 | $201.00 | $237.00 | $175.00 | $220.00 | $200.00 |
| 0038 | Construction sign, type B (801-06645) | EACH | 6 | $86.00 | $120.00 | $75.00 | $110.00 | $100.00 |
| 0039 | Maintaining traffic (801-06775) | LS | 1 | $7,200.00 | $48,655 | $45,000 | $48,000 | $7,500.00 |
| 0040 | Barricade, type III-A (801-07118) | LFT | 64 | $6.00 | $17.47 | $4.00 | $8.00 | $5.00 |
| 0041 | Barricade, type III-B (801-07119) | LFT | 68 | $6.00 | $17.47 | $4.00 | $8.00 | $5.00 |
| 0042 | Portable changeable message sign (801-11642) | EACH | 4 | $1,725.00 | $3,250.00 | $1,500.00 | $1,700.00 | $1,800.00 |
| 0043 | Line, paint, broken, yellow, 4 in. (808-06712) | LFT | 3 | $57.50 | $5.75 | $50.00 | $60.00 | $60.00 |
| 0044 | Line, paint, solid, white, 4 in. (808-06713) | LFT | 18 | $29.00 | $4.65 | $25.00 | $35.00 | $30.00 |
| 0045 | Line, paint, solid, yellow, 4 in. (808-06714) | LFT | 9 | $29.00 | $4.65 | $25.00 | $35.00 | $30.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of October 8, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.