INDOT contract B-44942-A bid tabulation
SCOUR PROTECTION. Let by Indiana DOT on January 14, 2026, Owen, Crawfordsville. 6 bids received; low bid $201,162 by 5 Star Company Inc.
- Owner
- Indiana DOT
- Letting
- 14 JAN 2026
- Pay items
- 31
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | 5 Star Company Inc | $201,162 | Low |
| 2 | CLR Inc | $271,329 | +35% |
| 3 | Crackers Demo LLC | $278,146 | +38% |
| 4 | Yarberry Companies Inc | $340,270 | +69% |
| 5 | Morphey Construction Inc. | $343,000 | +71% |
| 6 | Collom Excavating LLC | $374,338 | +86% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. 5 Star Company Inc | 2. CLR Inc | 3. Crackers Demo LLC | 4. Yarberry Companies Inc | 5. Morphey Construction Inc. | 6. Collom Excavating LLC |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $8,000.00 | $22,500 | $1,900.00 | $10,000 | $10,000 | $16,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Mobilization and demobilization (110-01001) | LS | 1 | $20,000 | $13,750 | $37,000 | $20,000 | $17,150 | $28,000 |
| 0009 | Clearing right-of-way (201-52370) | LS | 1 | $17,500 | $5,500.00 | $6,000.00 | $25,000 | $6,860.00 | $24,000 |
| 0010 | Structures and obstructions, remove (202-01000) | LS | 1 | $2,500.00 | $2,000.00 | $2,750.00 | $20,000 | $10,000 | $15,000 |
| 0011 | Excavation, waterway (203-51223) | CYS | 67 | $65.00 | $200.00 | $160.00 | $200.00 | $250.00 | $250.00 |
| 0012 | Pump around (205-11626) | EACH | 2 | $4,500.00 | $7,500.00 | $11,000 | $20,000 | $10,000 | $16,000 |
| 0013 | Stormwater management budget (205-12108) | DOL | 18,022 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0014 | Stormwater management implementation (205-12616) | LS | 1 | $4,000.00 | $1,000.00 | $11,000 | $5,000.00 | $1,300.00 | $15,005 |
| 0015 | Compacted aggregate, no. 53 (301-12234) | CYS | 46 | $50.00 | $120.00 | $109.00 | $150.00 | $200.00 | $110.00 |
| 0016 | Guardrail, reset (601-06035) | LFT | 188 | $110.00 | $25.00 | $95.00 | $50.00 | $41.42 | $110.00 |
| 0017 | Grout for riprap (616-02281) | CYS | 8 | $400.00 | $1,500.00 | $960.00 | $300.00 | $850.00 | $5,000.00 |
| 0018 | Riprap, class 2 (616-05689) | TON | 300 | $105.00 | $125.00 | $130.00 | $250.00 | $200.00 | $165.00 |
| 0019 | Riprap, revetment (616-06405) | TON | 150 | $95.00 | $225.00 | $227.00 | $200.00 | $170.00 | $165.00 |
| 0020 | Geotextile for riprap, type 1A (616-12246) | SYS | 542 | $4.00 | $12.00 | $2.34 | $15.00 | $3.50 | $7.50 |
| 0021 | Mobilization and demobilization for seeding (621-01004) | EACH | 2 | $550.00 | $500.00 | $1,000.00 | $750.00 | $1,000.00 | $1,000.00 |
| 0022 | Seeding wetland (621-02356) | LBS | 1 | $85.00 | $765.00 | $1,000.00 | $1,100.00 | $1,000.00 | $1,000.00 |
| 0023 | Mulched seeding, type R (621-06559) | SYS | 1,385 | $2.00 | $1.90 | $3.00 | $2.00 | $16.00 | $4.00 |
| 0024 | Field office, type C (628-09403) | MOS | 6 | $2,100.00 | $1,000.00 | $5,500.00 | $2,500.00 | $3,200.00 | $1,500.00 |
| 0025 | Road closure sign assembly (801-04308) | EACH | 2 | $80.00 | $750.00 | $325.00 | $181.00 | $75.00 | $75.00 |
| 0026 | Detour route marker assembly (801-06625) | EACH | 40 | $80.00 | $75.00 | $120.00 | $187.00 | $75.00 | $75.00 |
| 0027 | Construction sign, type A (801-06640) | EACH | 34 | $135.00 | $125.00 | $185.00 | $216.00 | $125.00 | $125.00 |
| 0028 | Construction sign, type B (801-06645) | EACH | 2 | $50.00 | $50.00 | $110.00 | $152.00 | $40.00 | $40.00 |
| 0029 | Maintaining traffic (801-06775) | LS | 1 | $18,500 | $58,530 | $10,225 | $20,000 | $79,408 | $40,000 |
| 0030 | Barricade, type III-A (801-07118) | LFT | 48 | $6.00 | $25.00 | $16.00 | $12.00 | $5.00 | $5.00 |
| 0031 | Barricade, type III-B (801-07119) | LFT | 48 | $6.00 | $25.00 | $16.00 | $12.00 | $5.00 | $5.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of January 14, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.