INDOT contract R-43031-A bid tabulation
HMA OVERLAY, PREVENTIVE MAINTENANCE. Let by Indiana DOT on February 11, 2026, Porter, LaPorte. 2 bids received; low bid $629,419 by Rieth-Riley Construction Co., Inc..
- Owner
- Indiana DOT
- Letting
- 11 FEB 2026
- Pay items
- 71
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Rieth-Riley Construction Co., Inc. | $629,419 | Low |
| 2 | Milestone Contractors LP | $794,489 | +26% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Rieth-Riley Construction Co., Inc. | 2. Milestone Contractors LP |
|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $14,000 | $10,667 |
| 0002 | Inspection hole, deeper than 3 FT (107-09358) | EACH | 10 | $350.00 | $910.00 |
| 0003 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 |
| 0004 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 |
| 0005 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 |
| 0006 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 |
| 0007 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 |
| 0008 | Quality adjustments, pavement traffic markings (109-09377) | DOL | 1 | $1.00 | $1.00 |
| 0009 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 |
| 0010 | Mobilization and demobilization (110-01001) | LS | 1 | $53,150 | $39,500 |
| 0011 | Clearing right-of-way (201-52370) | LS | 1 | $5,000.00 | $23,750 |
| 0012 | Sign, remove (202-74035) | EACH | 10 | $35.00 | $35.00 |
| 0013 | Post, remove (202-94747) | EACH | 6 | $70.00 | $70.00 |
| 0014 | Excavation, common (203-02000) | CYS | 10 | $200.00 | $245.00 |
| 0015 | Subgrade treatment, type IC (207-09935) | SYS | 773 | $40.00 | $66.00 |
| 0016 | B borrow (211-02050) | CYS | 5 | $100.00 | $375.00 |
| 0017 | Geogrid, type IB (214-11796) | SYS | 773 | $2.00 | $4.50 |
| 0018 | Compacted aggregate, no. 73 , recycled asphalt pavement (303-07449) | TON | 213 | $45.00 | $90.00 |
| 0019 | HMA patching, full depth, type B (304-12623) | TON | 511 | $160.00 | $214.00 |
| 0020 | HMA patching, full depth, type B , trail (304-12623) | TON | 15 | $160.00 | $300.00 |
| 0021 | HMA patching, partial depth, type B (304-12624) | TON | 48 | $220.00 | $340.00 |
| 0022 | Milling, asphalt, 1 1/2 in. (306-08034) | SYS | 12,557 | $2.05 | $2.90 |
| 0023 | Milling, approach (306-08432) | SYS | 127 | $6.00 | $32.00 |
| 0024 | QC/QA-HMA, 2, 58S, surface, 9.5 MM (401-000001) | TON | 1,037 | $98.00 | $102.00 |
| 0025 | Inertial profiler, HMA (401-12169) | LS | 1 | $500.00 | $4,000.00 |
| 0026 | Void reducing asphalt membrane for HMA (401-12439) | LFT | 6,889 | $3.27 | $3.60 |
| 0027 | Asphalt for tack coat (406-05520) | TON | 6 | $0.01 | $900.00 |
| 0028 | Guardrail, reset (601-06035) | LFT | 30 | $125.00 | $125.00 |
| 0029 | HMA for approaches, type B (610-07487) | TON | 11 | $125.00 | $290.00 |
| 0030 | Monument, RE-establish (615-06520) | EACH | 3 | $1,202.00 | $1,202.00 |
| 0031 | Mobilization and demobilization for seeding (621-01004) | EACH | 1 | $475.00 | $475.00 |
| 0032 | Mulched seeding, type U (621-06560) | SYS | 48 | $18.75 | $18.75 |
| 0033 | Topsoil (621-06570) | CYS | 5 | $200.00 | $375.00 |
| 0034 | Field office, type C (628-09403) | MOS | 12 | $2,000.00 | $2,000.00 |
| 0035 | Computer system equipment (628-11976) | EACH | 2 | $500.00 | $950.04 |
| 0036 | Temporary pavement message marking, lane indication arrow (801-01504) | EACH | 1 | $145.00 | $145.00 |
| 0037 | Temporary pavement marking, removable, 6 in. (801-06209) | LFT | 5,764 | $1.65 | $1.65 |
| 0038 | Temporary pavement marking, removable, 24 in. (801-06577) | LFT | 12 | $8.45 | $8.45 |
| 0039 | Construction sign, type A (801-06640) | EACH | 27 | $196.00 | $196.00 |
| 0040 | Construction sign, type B (801-06645) | EACH | 9 | $110.00 | $110.00 |
| 0041 | Maintaining traffic (801-06775) | LS | 1 | $34,335 | $78,501 |
| 0042 | Energy absorbing terminal, CZ, TL-2 (801-07023) | EACH | 2 | $5,779.00 | $5,779.00 |
| 0043 | Barricade, type III-B (801-07119) | LFT | 96 | $15.67 | $15.67 |
| 0044 | Temporary traffic barrier, type 2 (801-08401) | LFT | 30 | $101.00 | $100.00 |
| 0045 | Temporary pedestrian channelizer (801-12862) | LFT | 274 | $14.00 | $35.50 |
| 0046 | Temporary worksite speed limit sign assembly, continuous (801-12883) | EACH | 4 | $1,158.00 | $1,158.00 |
| 0047 | Sign post, square, type 1, unreinforced anchor base (802-05704) | LFT | 11 | $34.00 | $34.00 |
| 0048 | Sign, panel, with legend (802-07057) | SFT | 268 | $37.00 | $37.00 |
| 0049 | Sign, sheet, with legend, 0.080 in. thickness (802-09838) | SFT | 60 | $35.00 | $35.00 |
| 0050 | Sign, sheet, with legend, 0.100 in. thickness (802-09840) | SFT | 18 | $37.00 | $37.00 |
| 0051 | Sign post, timber, 4 in. X 6 in. (802-96994) | LFT | 153 | $44.00 | $44.00 |
| 0052 | Delineator post, flexible, type II (804-11921) | EACH | 17 | $175.00 | $378.00 |
| 0053 | Signal cantilever structure, single arm 45 FT (805-11379) | EACH | 1 | $31,478 | $31,478 |
| 0054 | Signal cantilever structure, single arm 50 FT (805-11380) | EACH | 1 | $32,972 | $32,972 |
| 0055 | Signal cantilever structure, drilled shaft foundation, type B (805-11384) | EACH | 2 | $12,500 | $12,500 |
| 0056 | Line, remove (808-06716) | LFT | 545 | $0.66 | $0.66 |
| 0057 | Retro-reflectivity testing (808-09381) | LS | 1 | $2,500.00 | $2,500.00 |
| 0058 | Transverse marking, multi-component, crosshatch line, yellow, 12 in. (808-10042) | LFT | 438 | $7.31 | $7.31 |
| 0059 | Line, multi-component, solid, white, 6 in. (808-10049) | LFT | 7,618 | $0.90 | $0.90 |
| 0060 | Pavement message marking, multi- component, only (808-10052) | EACH | 2 | $315.00 | $315.00 |
| 0061 | Line, multi-component, solid, yellow, 6 in. (808-10057) | LFT | 9,312 | $0.90 | $0.90 |
| 0062 | Line, multi-component, broken, white, 6 in. (808-10071) | LFT | 570 | $0.90 | $0.90 |
| 0063 | Pavement message marking, multi- component, lane indication arrow (808-10077) | EACH | 5 | $145.00 | $145.00 |
| 0064 | Pavement message marking, multi- component, bike symbol (808-10192) | EACH | 1 | $235.00 | $235.00 |
| 0065 | Pavement message marking, multi- component, ped xing (808-11516) | EACH | 1 | $415.00 | $415.00 |
| 0066 | Grooving for pavement markings (808-12032) | LFT | 16,884 | $0.58 | $0.58 |
| 0067 | Line, multi-component, dotted, white, 6 in. (808-12353) | LFT | 40 | $0.90 | $0.90 |
| 0068 | Line, multi-component, solid, white, 10 in. (808-12781) | LFT | 245 | $1.25 | $1.25 |
| 0069 | Line, multi-component, dotted, white, 10 in. (808-12851) | LFT | 195 | $1.25 | $1.25 |
| 0070 | Snowplowable raised pavement marker, remove (808-75996) | EACH | 145 | $1.00 | $17.85 |
| 0071 | Snowplowable raised pavement marker (808-75998) | EACH | 136 | $36.55 | $36.55 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of February 11, 2026. Compiled by Mirage Metrics.