KYTC contract 25-1014 bid tabulation
ASPHALT SURFACE WITH GRADE & DRAIN CHESTNUT RIDGE ROAD. Let by Kentucky Transportation Cabinet on July 24, 2025. 2 bids received; low bid $7,472,773 by Frederick & May Construction Co, -36% against the engineer's estimate of $11,716,254.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 24 JUL 2025
- Pay items
- 88
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Frederick & May Construction Co | $7,472,773 | Low | -36% |
| 2 | Bizzack Construction LLC | $7,790,818 | +4.0% | -34% |
Engineer's estimate: $11,716,254.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Frederick & May Construction Co | 2. Bizzack Construction LLC |
|---|---|---|---|---|---|
| 0010 | Crushed stone base | TON A A | 15,567 | $48.25 | $47.21 |
| 0020 | Geogrid reinforcement for subgrade | SQYD A A | 22,506 | $2.85 | $2.18 |
| 0030 | CL2 asph base 1.00D PG64-22 | TON A A | 1,614 | $149.65 | $149.65 |
| 0040 | CL2 asph base 0.75D PG64-22 | TON A A | 4,365 | $156.85 | $156.85 |
| 0050 | Asphalt prime coat | TON A A | 15.40 | $10.00 | $10.00 |
| 0060 | CL2 asph surf 0.38D PG64-22 | TON A A | 1,320 | $177.25 | $177.25 |
| 0070 | Asphalt material for tack | TON A A | 15.40 | $10.00 | $10.00 |
| 0080 | JPC pavement-8 in | SQYD A A | 142 | $160.75 | $163.83 |
| 0090 | Fabric-geotextile class 1 | SQYD A A | 23,966 | $2.25 | $2.14 |
| 0190 | Inspect & certify edge drain system | LS A A | 1 | $8,000.00 | $7,500.00 |
| 0200 | Standard integral curb | LF A A | 202 | $35.16 | $35.89 |
| 0210 | Barricade-type III | EACH A A | 2 | $150.00 | $200.00 |
| 0220 | Temp ditch | LF A A | 3,103 | $1.00 | $1.34 |
| 0230 | Clean temp ditch | LF A A | 1,551 | $0.10 | $0.01 |
| 0240 | Roadway excavation | CUYD A A | 231,100 | $6.90 | $7.27 |
| 0250 | Granular embankment | CUYD A A | 3,667 | $61.00 | $67.00 |
| 0260 | Water | MGAL A A | 60 | $1.00 | $5.00 |
| 0270 | Guardrail-steel W beam-S face | LF A A | 37.50 | $65.50 | $65.50 |
| 0280 | Guardrail terminal section no 1 | EACH A A | 2 | $150.00 | $150.00 |
| 0290 | Witness post | EACH A A | 10 | $110.00 | $100.00 |
| 0300 | Channel lining class II | TON A A | 1,074 | $51.50 | $54.78 |
| 0310 | Clearing and grubbing | LS A A | 1 | $75,000 | $65,000 |
| 0320 | Temporary signs | SQFT A A | 150 | $17.00 | $16.96 |
| 0330 | Edge key | LF A A | 10 | $85.75 | $85.75 |
| 0340 | Fabric-geotextile class 2 | SQYD A A | 8,000 | $2.00 | $2.19 |
| 0350 | Maintain & control traffic | LS A A | 1 | $6,000.00 | $9,750.00 |
| 0360 | Temp silt fence | LF A A | 3,103 | $2.25 | $3.75 |
| 0370 | Silt trap type A | EACH A A | 59 | $50.00 | $85.00 |
| 0380 | Silt trap type B | EACH A A | 59 | $50.00 | $107.00 |
| 0390 | Silt trap type C | EACH A A | 59 | $50.00 | $290.00 |
| 0400 | Clean silt trap type A | EACH A A | 59 | $10.00 | $0.01 |
| 0410 | Clean silt trap type B | EACH A A | 59 | $10.00 | $0.01 |
| 0420 | Clean silt trap type C | EACH A A | 59 | $10.00 | $0.01 |
| 0430 | Sidewalk-4 in concrete | SQYD A A | 5,505 | $57.98 | $59.71 |
| 0440 | Staking | LS A A | 1 | $36,000 | $50,000 |
| 0450 | Erosion control blanket | SQYD A A | 1,582 | $2.95 | $2.95 |
| 0460 | Temp mulch | SQYD A A | 192,201 | $0.31 | $0.31 |
| 0470 | Temp seeding and protection | SQYD A A | 143,433 | $0.33 | $0.33 |
| 0480 | Initial fertilizer | TON A A | 9 | $975.00 | $975.00 |
| 0490 | Maintenance fertilizer | TON A A | 14.80 | $1,100.00 | $1,100.00 |
| 0500 | Seeding and protection | SQYD A A | 286,867 | $0.45 | $0.45 |
| 0510 | Agricultural limestone | TON A A | 177.80 | $85.00 | $85.00 |
| 0520 | Topsoil furnished and placed | CUYD A A | 40 | $100.00 | $75.00 |
| 0530 | SBM alum sheet signs .080 in | SQFT A A | 122 | $35.00 | $35.00 |
| 0540 | Steel post type 1 | LF A A | 216.50 | $25.00 | $25.00 |
| 0550 | Pave striping-perm paint-4 in | LF A A | 6,957 | $0.35 | $0.35 |
| 0560 | Pave marking-thermo X-walk-12 in | LF A A | 380 | $6.50 | $6.50 |
| 0570 | Pave marking-thermo stop bar-24IN | LF A A | 25 | $12.00 | $12.00 |
| 0580 | Pave marking-thermo comb arrow | EACH A A | 6 | $140.00 | $140.00 |
| 0590 | Fuel adjustment | DOLL A A | 56,978 | $1.00 | $1.00 |
| 0600 | Asphalt adjustment | DOLL A A | 28,657 | $1.00 | $1.00 |
| 0610 | Rolled curb and gutter | LF A A | 8,558 | $20.15 | $21.23 |
| 0620 | Rolled curb and gutter | LF A A | 3,150 | $20.15 | $21.23 |
| 0630 | Pave marking-thermo yield bar-36 in | LF A A | 72 | $50.00 | $50.00 |
| 0640 | Detectable warnings | SQFT A A | 208 | $47.06 | $48.51 |
| 0650 | Enhanced silt trap | EACH A A | 11 | $250.00 | $295.00 |
| 0660 | Island curb and gutter(modified) | LF A A | 276 | $33.17 | $33.81 |
| 0670 | R/W monument type 3 | EACH A A | 10 | $110.00 | $125.00 |
| 0680 | Barcode sign inventory | EACH A A | 25 | $30.00 | $30.00 |
| 0690 | Impermeable detention basin lining | SQYD A A | 7,313 | $14.02 | $20.00 |
| 0700 | Pipeline inspection | LF A A | 10,760 | $2.35 | $2.35 |
| 0710 | Utility coordination | LS A A | 1 | $1,000.00 | $9,000.00 |
| 0720 | Electronic delivery MGMT system - agg | LS A A | 1 | $100.00 | $1.00 |
| 1270 | Culvert pipe-24 in | LF A A | 103 | $112.00 | $139.00 |
| 1280 | Culvert pipe-30 in | LF A A | 261 | $155.00 | $156.00 |
| 1290 | Culvert pipe-36 in | LF A A | 283 | $218.00 | $170.00 |
| 1300 | Storm sewer pipe-15 in | LF A A | 1,804 | $78.00 | $94.00 |
| 1310 | Storm sewer pipe-18 in | LF A A | 5,824 | $84.00 | $106.00 |
| 1320 | Storm sewer pipe-24 in | LF A A | 1,943 | $149.00 | $136.00 |
| 1330 | Storm sewer pipe-30 in | LF A A | 365 | $132.00 | $156.00 |
| 1340 | Storm sewer pipe-36 in | LF A A | 177 | $155.00 | $181.00 |
| 1350 | Perforated pipe-4 in | LF A A | 150 | $12.00 | $15.00 |
| 1360 | Perforated pipe edge drain-4 in | LF A A | 11,087 | $12.58 | $12.58 |
| 1370 | Pipe culvert headwall-18 in | EACH A A | 1 | $1,400.00 | $1,100.00 |
| 1380 | Pipe culvert headwall-24 in | EACH A A | 3 | $1,500.00 | $1,300.00 |
| 1390 | Pipe culvert headwall-30 in | EACH A A | 3 | $2,425.00 | $2,400.00 |
| 1400 | Pipe culvert headwall-36 in | EACH A A | 2 | $2,450.00 | $2,700.00 |
| 1410 | Curb box inlet type A mod | EACH A A | 69 | $5,700.00 | $5,300.00 |
| 1420 | Drop box inlet type 3 | EACH A A | 8 | $3,750.00 | $9,400.00 |
| 1430 | Drop box inlet type 4 | EACH A A | 3 | $5,200.00 | $10,200 |
| 1440 | Drop box inlet type 14 | EACH A A | 49 | $2,600.00 | $2,400.00 |
| 1450 | Cored hole drainage box con-4 in | EACH A A | 80 | $10.00 | $20.00 |
| 1460 | Manhole type A | EACH A A | 1 | $2,800.00 | $3,400.00 |
| 1470 | Manhole type B | EACH A A | 4 | $6,500.00 | $6,200.00 |
| 1480 | Manhole type C | EACH A A | 1 | $6,500.00 | $7,400.00 |
| 1490 | Fabric-geotextile class 2 for pipe | SQYD A A | 33,441 | $2.00 | $2.00 |
| 1710 | Mobilization | LS A A | 1 | $224,977 | $200,000 |
| 1720 | Demobilization | LS A A | 1 | $110,436 | $111,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of July 24, 2025. Compiled by Mirage Metrics.