KYTC contract 25-1015 bid tabulation
GRADE & DRAIN WITH ASPHALT SURFACE EAST MAIN STREET(US-68). Let by Kentucky Transportation Cabinet on October 23, 2025. 3 bids received; low bid $5,463,310 by Rame Contracting LLC, -12% against the engineer's estimate of $6,237,739.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 23 OCT 2025
- Pay items
- 138
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Rame Contracting LLC | $5,463,310 | Low | -12% |
| 2 | Cleary Construction Inc | $6,400,000 | +17% | +3.0% |
| 3 | Louisville Paving Company Inc | $6,554,644 | +20% | +5.0% |
Engineer's estimate: $6,237,739.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Rame Contracting LLC | 2. Cleary Construction Inc | 3. Louisville Paving Company Inc |
|---|---|---|---|---|---|---|
| 0010 | Crushed stone base | TON A A | 12,532 | $40.00 | $36.00 | $41.49 |
| 0020 | Asphalt seal aggregate | TON A A | 135 | $75.00 | $97.97 | $94.11 |
| 0030 | Asphalt seal coat | TON A A | 19 | $275.00 | $1,091.89 | $911.00 |
| 0040 | Leveling & wedging PG64-22 | TON A A | 2,689 | $116.92 | $116.92 | $108.00 |
| 0050 | CL3 asph base 1.00D PG64-22 | TON A A | 6,291 | $99.84 | $99.84 | $115.50 |
| 0060 | Asphalt material for tack | TON A A | 19.90 | $743.82 | $743.82 | $1.00 |
| 0070 | CL3 asph surf 0.38B PG76-22 | TON A A | 244 | $122.53 | $122.53 | $120.00 |
| 0080 | CL3 asph surf 0.38B PG64-22 | TON A A | 2,718 | $105.63 | $105.63 | $108.00 |
| 0090 | Asphalt pave milling & texturing | TON A A | 1,408 | $27.35 | $18.16 | $31.17 |
| 0100 | Joint adhesive | LF A A | 11,701 | $1.00 | $1.00 | $5.00 |
| 0110 | Crushed aggregate size no 2 | TON A A | 9,805 | $32.00 | $34.00 | $39.54 |
| 0120 | Perforated pipe-4 in | LF A A | 5,332 | $15.00 | $16.00 | $22.54 |
| 0130 | Non-perforated pipe-4 in | LF A A | 138 | $15.00 | $35.00 | $73.37 |
| 0140 | Inspect & certify edge drain system | LS A A | 1 | $2,500.00 | $7,500.00 | $2,500.00 |
| 0150 | Perf pipe headwall TY 1-4 in | EACH A A | 2 | $1,200.00 | $850.00 | $864.51 |
| 0160 | Perf pipe headwall TY 2-4 in | EACH A A | 4 | $1,200.00 | $850.00 | $864.51 |
| 0170 | Cored hole drainage box con-4 in | EACH A A | 20 | $300.00 | $350.00 | $300.00 |
| 0180 | Standard curb and gutter | LF A A | 4,660 | $33.04 | $33.04 | $33.04 |
| 0190 | Island curb and gutter | LF A A | 517 | $33.79 | $33.79 | $33.79 |
| 0200 | Barricade-type III | EACH A A | 4 | $100.00 | $100.00 | $100.00 |
| 0210 | Paved ditch type 1 | SQYD A A | 25 | $400.00 | $363.59 | $363.59 |
| 0220 | Temp ditch | LF A A | 3,330 | $0.25 | $1.00 | $1.76 |
| 0230 | Clean temp ditch | LF A A | 1,665 | $0.01 | $0.01 | $1.76 |
| 0240 | Roadway excavation | CUYD A A | 18,508 | $14.50 | $38.00 | $38.00 |
| 0250 | Embankment in place | CUYD A A | 16,436 | $12.00 | $19.00 | $13.00 |
| 0260 | Ditching | LF A A | 435 | $7.00 | $15.00 | $28.07 |
| 0270 | Water | MGAL A A | 5 | $2,000.00 | $0.01 | $0.01 |
| 0280 | Guardrail-steel W beam-S face | LF A A | 200 | $36.78 | $35.00 | $36.78 |
| 0290 | Guardrail terminal section no 1 | EACH A A | 2 | $93.61 | $75.00 | $93.61 |
| 0300 | Guardrail end treatment type 1 | EACH A A | 4 | $3,576.20 | $4,200.00 | $3,576.20 |
| 0310 | Remove & reset guardrail | LF A A | 475 | $26.07 | $25.00 | $26.07 |
| 0320 | Right-of-way monument type 1 | EACH A A | 28 | $305.00 | $150.00 | $180.24 |
| 0330 | Witness post | EACH A A | 17 | $163.95 | $150.00 | $163.95 |
| 0340 | Channel lining class II | TON A A | 643 | $36.50 | $68.00 | $50.13 |
| 0350 | Channel lining class III | TON A A | 31 | $43.50 | $70.00 | $108.03 |
| 0360 | Clearing and grubbing | LS A A | 1 | $75,000 | $65,000 | $107,999 |
| 0370 | Temporary signs | SQFT A A | 600 | $5.00 | $5.00 | $5.00 |
| 0380 | Fabric-geotextile class 1 | SQYD A A | 17,675 | $2.50 | $2.33 | $1.41 |
| 0390 | Fabric-geotextile class 1A | SQYD A A | 17,000 | $3.00 | $2.34 | $1.39 |
| 0400 | Maintain & control traffic | LS A A | 1 | $270,000 | $368,000 | $688,124 |
| 0410 | Portable changeable message sign | EACH A A | 4 | $7,000.00 | $6,360.00 | $7,632.00 |
| 0420 | Mobilization for mill & text | LS A A | 1 | $3,500.00 | $4,000.00 | $14,000 |
| 0430 | Safeloading | CUYD A A | 14 | $550.00 | $407.83 | $468.66 |
| 0440 | Temp silt fence | LF A A | 3,330 | $3.00 | $3.00 | $2.00 |
| 0450 | Silt trap type A | EACH A A | 16 | $250.00 | $350.00 | $0.01 |
| 0460 | Silt trap type B | EACH A A | 16 | $250.00 | $190.00 | $474.98 |
| 0470 | Silt trap type C | EACH A A | 16 | $250.00 | $360.00 | $278.98 |
| 0480 | Clean silt trap type A | EACH A A | 16 | $50.00 | $1.00 | $0.01 |
| 0490 | Clean silt trap type B | EACH A A | 16 | $50.00 | $1.00 | $0.01 |
| 0500 | Clean silt trap type C | EACH A A | 16 | $50.00 | $1.00 | $0.01 |
| 0510 | Sidewalk-4 in concrete | SQYD A A | 1,673 | $59.00 | $59.74 | $59.74 |
| 0520 | Staking | LS A A | 1 | $100,000 | $250,000 | $70,000 |
| 0530 | Temp relocation of signal head | EACH A A | 7 | $700.00 | $2,500.00 | $652.19 |
| 0540 | Erosion control blanket | SQYD A A | 9,601 | $3.15 | $1.73 | $3.15 |
| 0550 | Temp mulch | SQYD A A | 49,800 | $0.39 | $0.28 | $0.39 |
| 0560 | Temp seeding and protection | SQYD A A | 37,350 | $0.43 | $0.32 | $0.43 |
| 0570 | Initial fertilizer | TON A A | 2.40 | $1,361.33 | $1,032.00 | $1,361.33 |
| 0580 | Maintenance fertilizer | TON A A | 3.90 | $1,361.33 | $1,032.00 | $1,361.33 |
| 0590 | Seeding and protection | SQYD A A | 74,700 | $0.73 | $0.45 | $0.73 |
| 0600 | Special seeding crown vetch | SQYD A A | 8,975 | $0.15 | $0.39 | $0.15 |
| 0610 | Sodding | SQYD A A | 1,988 | $9.92 | $6.60 | $9.92 |
| 0620 | Agricultural limestone | TON A A | 46.40 | $101.95 | $98.00 | $101.95 |
| 0630 | Topsoil furnished and placed | CUYD A A | 175 | $196.62 | $42.26 | $196.62 |
| 0640 | Pave striping-temp paint-6 in | LF A A | 17,050 | $0.30 | $0.30 | $0.30 |
| 0650 | Pave striping-thermo-6 in W | LF A A | 14,043 | $1.35 | $1.35 | $1.35 |
| 0660 | Pave striping-thermo-6 in Y | LF A A | 16,796 | $1.35 | $1.35 | $1.35 |
| 0670 | Pave striping-thermo-12 in W | LF A A | 156 | $2.70 | $2.70 | $2.70 |
| 0680 | Pave striping-thermo-12 in Y | LF A A | 1,342 | $2.70 | $2.70 | $2.70 |
| 0690 | Pave marking-thermo stop bar-24IN | LF A A | 93 | $10.00 | $10.00 | $10.00 |
| 0700 | Pave marking-thermo cross-hatch | SQFT A A | 1,031 | $7.00 | $7.00 | $7.00 |
| 0710 | Pave marking-thermo curv arrow | EACH A A | 36 | $120.00 | $120.00 | $120.00 |
| 0720 | Pave marking-thermo comb arrow | EACH A A | 4 | $150.00 | $150.00 | $150.00 |
| 0730 | Inlaid pavement marker-MW | EACH A A | 3 | $35.00 | $35.00 | $35.00 |
| 0740 | Inlaid pavement marker-by | EACH A A | 314 | $35.00 | $35.00 | $35.00 |
| 0760 | Fuel adjustment | DOLL A A | 18,588 | $1.00 | $1.00 | $1.00 |
| 0770 | Asphalt adjustment | DOLL A A | 46,688 | $1.00 | $1.00 | $1.00 |
| 0780 | Tree | EACH A A | 3 | $654.75 | $988.00 | $654.75 |
| 0790 | Shrub | EACH A A | 24 | $160.69 | $105.00 | $160.69 |
| 0800 | Shrub | EACH A A | 3 | $196.53 | $868.00 | $196.53 |
| 0810 | Shrub | EACH A A | 70 | $196.53 | $91.00 | $196.53 |
| 0820 | Object marker TY 3 | EACH A A | 4 | $28.97 | $50.00 | $28.97 |
| 0830 | Pave marking-thermo yield bar-36 in | LF A A | 74 | $45.00 | $45.00 | $45.00 |
| 0840 | Detectable warnings | SQFT A A | 178 | $43.00 | $43.00 | $43.00 |
| 0850 | Pave mark-thermo-X-walk-24 in | LF A A | 32 | $10.00 | $10.00 | $10.00 |
| 0860 | Stamped concrete | SQYD A A | 749 | $205.02 | $205.02 | $205.02 |
| 0865 | Stamped concrete | SQYD A A | 548 | $119.55 | $119.55 | $119.55 |
| 0880 | Container plants | EACH A A | 37 | $180.24 | $88.00 | $180.24 |
| 0890 | Pipeline inspection | LF A A | 3,987 | $2.35 | $2.35 | $2.35 |
| 0910 | Electronic delivery MGMT system - agg | LS A A | 1 | $421.03 | $1.00 | $0.01 |
| 0920 | Decorative rock | SQFT A A | 1,450 | $8.20 | $9.84 | $8.20 |
| 0930 | Entrance pipe-15 in | LF A A | 241 | $62.50 | $90.00 | $60.05 |
| 0940 | Entrance pipe-18 in | LF A A | 244 | $70.00 | $95.00 | $63.86 |
| 0950 | Entrance pipe-24 in | LF A A | 68 | $80.00 | $100.00 | $75.06 |
| 0960 | Culvert pipe-18 in | LF A A | 100 | $100.00 | $105.00 | $77.82 |
| 0970 | Culvert pipe-30 in | LF A A | 298 | $200.00 | $265.00 | $127.38 |
| 0980 | Culvert pipe-36 in | LF A A | 42 | $195.00 | $215.00 | $179.35 |
| 0990 | Culvert pipe-48 in | LF A A | 4 | $500.00 | $750.00 | $956.99 |
| 1000 | Storm sewer pipe-15 in | LF A A | 102 | $75.00 | $95.00 | $61.11 |
| 1010 | Storm sewer pipe-18 in | LF A A | 2,396 | $82.50 | $100.00 | $67.12 |
| 1020 | Storm sewer pipe-24 in | LF A A | 290 | $100.00 | $115.00 | $98.29 |
| 1030 | Storm sewer pipe-30 in | LF A A | 192 | $215.00 | $200.00 | $118.48 |
| 1040 | Storm sewer pipe-36 in | LF A A | 10 | $200.00 | $300.00 | $377.55 |
| 1050 | Pipe culvert headwall-18 in | EACH A A | 1 | $1,850.00 | $2,500.00 | $2,715.50 |
| 1060 | Pipe culvert headwall-24 in | EACH A A | 1 | $1,850.00 | $2,600.00 | $2,805.60 |
| 1070 | Pipe culvert headwall-30 in | EACH A A | 2 | $2,500.00 | $3,000.00 | $2,956.14 |
| 1080 | Pipe culvert headwall-36 in | EACH A A | 2 | $2,500.00 | $3,250.00 | $2,982.64 |
| 1090 | Sloped box outlet type 1-15 in | EACH A A | 5 | $2,500.00 | $3,000.00 | $2,448.70 |
| 1100 | Sloped box outlet type 1-18 in | EACH A A | 8 | $2,500.00 | $3,500.00 | $2,420.24 |
| 1110 | S & F box inlet-outlet-18 in | EACH A A | 3 | $3,000.00 | $5,500.00 | $3,052.03 |
| 1120 | S & F box inlet-outlet-24 in | EACH A A | 4 | $4,000.00 | $5,750.00 | $3,930.12 |
| 1130 | S & F box inlet-outlet-30 in | EACH A A | 3 | $6,000.00 | $7,000.00 | $5,782.59 |
| 1140 | Curb box inlet type A | EACH A A | 16 | $5,000.00 | $8,500.00 | $4,612.74 |
| 1150 | Drop box inlet type 11 | EACH A A | 3 | $2,750.00 | $4,000.00 | $2,904.96 |
| 1160 | Drop box inlet type 13S | EACH A A | 1 | $6,000.00 | $7,500.00 | $5,831.65 |
| 1170 | Manhole type C | EACH A A | 2 | $6,500.00 | $7,750.00 | $4,572.58 |
| 1180 | Fabric-geotextile class 2 for pipe | SQYD A A | 5,588 | $2.00 | $2.00 | $2.00 |
| 1190 | Concrete-class A | CUYD A A | 13.26 | $600.00 | $500.00 | $400.00 |
| 1200 | Drop box inlet TY 13S(mod) | EACH A A | 1 | $6,700.00 | $6,500.00 | $5,831.65 |
| 1210 | Modify existing drainage box | EACH A A | 1 | $2,500.00 | $2,500.00 | $2,197.56 |
| 1220 | Pole 40 FT MTG HT | EACH A A | 12 | $3,029.52 | $3,029.52 | $3,029.52 |
| 1230 | Bracket 8 FT | EACH A A | 9 | $645.52 | $645.52 | $645.52 |
| 1240 | Bracket 10 FT | EACH A A | 3 | $826.08 | $826.08 | $826.08 |
| 1250 | Pole base | EACH A A | 12 | $3,343.17 | $3,343.17 | $3,343.17 |
| 1260 | Transformer base | EACH A A | 12 | $1,562.25 | $1,562.25 | $1,562.25 |
| 1270 | Lighting control equipment | EACH A A | 1 | $25,552 | $25,552 | $26,316 |
| 1280 | Fused connector kit | EACH A A | 24 | $231.75 | $231.75 | $231.75 |
| 1290 | Trenching and backfilling | LF A A | 1,475 | $12.32 | $12.32 | $12.32 |
| 1300 | Wire-no. 12 | LF A A | 1,985 | $2.11 | $2.11 | $2.11 |
| 1310 | Pole 45 FT wooden | EACH A A | 1 | $1,879.41 | $1,879.41 | $1,879.41 |
| 1320 | Electrical junction box type A | EACH A A | 4 | $1,466.68 | $1,466.68 | $1,466.68 |
| 1330 | Bore and jack conduit | LF A A | 255 | $30.26 | $30.26 | $30.26 |
| 1340 | Wire-no. 10 | LF A A | 6,200 | $1.76 | $1.76 | $1.76 |
| 1350 | LED luminaire | EACH A A | 12 | $905.26 | $905.26 | $905.26 |
| 1360 | PVC conduit-1 1/4 in-schedule 80 | LF A A | 1,125 | $5.90 | $5.90 | $5.90 |
| 1370 | PVC conduit-2 in-schedule 80 | LF A A | 600 | $8.08 | $8.08 | $8.08 |
| 1380 | Remove signal equipment | EACH A A | 1 | $8,287.29 | $8,287.29 | $8,287.29 |
| 1390 | Mobilization | LS A A | 1 | $250,000 | $297,000 | $300,000 |
| 1400 | Demobilization | LS A A | 1 | $76,552 | $90,897 | $92,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of October 23, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.