KYTC contract 25-1021 bid tabulation
GRADE & DRAIN WITH ASPHALT SURFACE LITTLE FORK ROAD(KY-613). Let by Kentucky Transportation Cabinet on August 21, 2025. 4 bids received; low bid $928,210 by Delmae LLC, -29% against the engineer's estimate of $1,306,025.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 21 AUG 2025
- Pay items
- 78
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Delmae LLC | $928,210 | Low | -29% |
| 2 | Frederick & May Construction Co | $1,114,375 | +20% | -15% |
| 3 | Walker Construction & Materials LLC | $1,169,686 | +26% | -10% |
| 4 | Louisville Paving Company Inc | $1,199,362 | +29% | -8.0% |
Engineer's estimate: $1,306,025.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Delmae LLC | 2. Frederick & May Construction Co | 3. Walker Construction & Materials LLC | 4. Louisville Paving Company Inc |
|---|---|---|---|---|---|---|---|
| 0010 | Crushed stone base | TON A A | 1,009 | $35.00 | $41.25 | $41.25 | $41.25 |
| 0020 | Traffic bound base | TON A A | 78 | $42.00 | $40.00 | $50.00 | $64.00 |
| 0030 | Crushed aggregate size no 2 | TON A A | 2,469 | $35.00 | $37.00 | $30.00 | $43.00 |
| 0040 | CL2 asph base 1.00D PG64-22 | TON A A | 1,377 | $123.90 | $123.90 | $123.90 | $123.90 |
| 0050 | Asphalt prime coat | TON A A | 3.04 | $1,475.00 | $1,475.00 | $1,475.00 | $1,475.00 |
| 0060 | CL2 asph surf 0.38D PG64-22 | TON A A | 438 | $141.60 | $141.60 | $141.60 | $141.60 |
| 0070 | Fabric-geotextile class 1 | SQYD A A | 3,862 | $3.00 | $2.50 | $2.50 | $1.75 |
| 0080 | Fabric-geotextile class 1A | SQYD A A | 3,579 | $4.75 | $3.50 | $4.50 | $3.50 |
| 0090 | Asphalt pave milling & texturing | TON A A | 95 | $92.50 | $92.50 | $92.50 | $92.50 |
| 0100 | Asphalt material for tack non-tracking | TON A A | 3.19 | $500.00 | $500.00 | $500.00 | $500.00 |
| 0110 | Perforated pipe-6 in | LF A A | 2,550 | $7.75 | $23.00 | $16.00 | $16.50 |
| 0120 | Non-perforated pipe-6 in | LF A A | 64 | $12.00 | $30.00 | $76.00 | $45.00 |
| 0130 | Inspect & certify edge drain system | LS A A | 1 | $2,500.00 | $4,000.00 | $2,500.00 | $5,000.00 |
| 0140 | Cored hole drainage box con-6 in | EACH A A | 2 | $500.00 | $500.00 | $250.00 | $500.00 |
| 0150 | Island header curb type 2 | LF A A | 50 | $65.00 | $100.00 | $123.00 | $138.08 |
| 0160 | Delineator for guardrail BI directional white | EACH A A | 20 | $13.00 | $13.00 | $13.00 | $16.19 |
| 0170 | Barricade-type III | EACH A A | 6 | $175.00 | $125.00 | $175.00 | $100.00 |
| 0180 | Temp ditch | LF A A | 914 | $2.00 | $1.00 | $1.00 | $2.93 |
| 0190 | Clean temp ditch | LF A A | 457 | $1.00 | $0.10 | $0.10 | $2.93 |
| 0200 | Roadway excavation | CUYD A A | 3,585 | $20.00 | $30.00 | $28.00 | $32.00 |
| 0210 | Guardrail-steel W beam-S face | LF A A | 950 | $33.00 | $33.00 | $33.00 | $33.34 |
| 0220 | Guardrail connector to bridge end TY A | EACH A A | 2 | $3,500.00 | $3,500.00 | $3,500.00 | $4,029.40 |
| 0230 | Remove guardrail | LF A A | 1,055 | $5.00 | $5.00 | $5.00 | $4.55 |
| 0240 | Guardrail end treatment type 4A | EACH A A | 2 | $3,800.00 | $3,800.00 | $3,800.00 | $3,863.84 |
| 0250 | Remove concrete masonry | CUYD A A | 1 | $1,000.00 | $1,000.00 | $3,500.00 | $4,500.00 |
| 0260 | Right-of-way monument type 1 | EACH A A | 18 | $200.00 | $250.00 | $225.00 | $166.61 |
| 0270 | Witness post | EACH A A | 3 | $175.00 | $250.00 | $255.00 | $150.06 |
| 0280 | Channel lining class II | TON A A | 42 | $100.00 | $45.00 | $175.00 | $86.00 |
| 0290 | Clearing and grubbing | LS A A | 1 | $25,000 | $81,500 | $111,111 | $62,712 |
| 0300 | Temporary signs | SQFT A A | 321 | $14.00 | $17.00 | $15.00 | $5.00 |
| 0310 | Maintain & control traffic | LS A A | 1 | $20,000 | $25,032 | $22,222 | $95,000 |
| 0320 | Portable changeable message sign | EACH A A | 2 | $5,000.00 | $4,500.00 | $3,500.00 | $3,180.00 |
| 0330 | Mobilization for mill & text | LS A A | 1 | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 |
| 0340 | Edgeline rumble strips | LF A A | 3,386 | $1.75 | $0.90 | $2.00 | $2.12 |
| 0350 | Temp silt fence | LF A A | 914 | $4.00 | $2.00 | $5.00 | $2.00 |
| 0360 | Silt trap type A | EACH A A | 5 | $350.00 | $50.00 | $200.00 | $150.00 |
| 0370 | Silt trap type B | EACH A A | 5 | $350.00 | $50.00 | $200.00 | $150.00 |
| 0380 | Silt trap type C | EACH A A | 5 | $350.00 | $50.00 | $200.00 | $150.00 |
| 0390 | Clean silt trap type A | EACH A A | 5 | $25.00 | $25.00 | $20.00 | $150.00 |
| 0400 | Clean silt trap type B | EACH A A | 5 | $25.00 | $25.00 | $20.00 | $150.00 |
| 0410 | Clean silt trap type C | EACH A A | 5 | $25.00 | $25.00 | $20.00 | $150.00 |
| 0420 | Staking | LS A A | 1 | $10,000 | $30,000 | $15,555 | $30,000 |
| 0430 | Erosion control blanket | SQYD A A | 1,302 | $2.50 | $2.50 | $2.50 | $3.25 |
| 0440 | Temp mulch | SQYD A A | 15,263 | $0.33 | $0.33 | $0.33 | $0.42 |
| 0450 | Temp seeding and protection | SQYD A A | 11,390 | $0.35 | $0.35 | $0.35 | $0.43 |
| 0460 | Initial fertilizer | TON A A | 0.89 | $1,500.00 | $1,500.00 | $1,500.00 | $1,582.14 |
| 0470 | Maintenance fertilizer | TON A A | 0.54 | $1,600.00 | $1,600.00 | $1,600.00 | $1,582.14 |
| 0480 | Seeding and protection | SQYD A A | 13,180 | $0.76 | $0.76 | $0.76 | $0.77 |
| 0490 | Agricultural limestone | TON A A | 10.73 | $120.00 | $120.00 | $120.00 | $84.31 |
| 0500 | Pave striping-perm paint-4 in | LF A A | 6,217 | $0.80 | $0.35 | $0.45 | $0.35 |
| 0510 | Pave marking-thermo stop bar-24IN | LF A A | 10 | $15.00 | $20.00 | $15.00 | $20.00 |
| 0520 | Joint adhesive | LF A A | 1,827 | $4.25 | $4.25 | $4.25 | $4.25 |
| 0530 | Object marker TY 3 | EACH A A | 2 | $110.00 | $110.00 | $110.00 | $46.00 |
| 0540 | Sawcut pavement | LF A A | 911 | $5.00 | $5.00 | $3.00 | $3.00 |
| 0550 | Longitudinal edge key | LF A A | 911 | $12.85 | $12.85 | $12.85 | $12.85 |
| 0560 | Turf reinforcement mat 1 | SQYD A A | 67 | $25.00 | $25.00 | $25.00 | $9.48 |
| 0570 | Turf reinforcement mat 4 | SQYD A A | 2,755 | $10.85 | $10.85 | $10.85 | $11.13 |
| 0580 | Cored hole drainage conn to headwall | EACH A A | 6 | $250.00 | $300.00 | $250.00 | $500.00 |
| 0590 | Replace handrail | LS A A | 1 | $4,500.00 | $9,000.00 | $5,000.00 | $6,250.00 |
| 0600 | Electronic delivery MGMT system - agg | LS A A | 1 | $1,500.00 | $1,800.00 | $1,500.00 | $1,500.00 |
| 0610 | Entrance pipe-15 in | LF A A | 148 | $36.00 | $70.00 | $140.00 | $78.00 |
| 0620 | Entrance pipe-24 in | LF A A | 84 | $75.00 | $80.00 | $150.00 | $113.00 |
| 0630 | Culvert pipe-24 in | LF A A | 180 | $130.00 | $140.00 | $210.00 | $133.00 |
| 0640 | Storm sewer pipe-24 in | LF A A | 108 | $80.00 | $130.00 | $250.00 | $133.00 |
| 0650 | Pipe culvert headwall-24 in | EACH A A | 3 | $2,000.00 | $2,000.00 | $2,500.00 | $2,400.00 |
| 0660 | Sloped box outlet type 1-24 in | EACH A A | 1 | $4,500.00 | $4,500.00 | $4,700.00 | $4,000.00 |
| 0670 | S & F box inlet-outlet-24 in | EACH A A | 7 | $4,500.00 | $5,500.00 | $5,900.00 | $4,750.00 |
| 0680 | Drop box inlet type 1 | EACH A A | 1 | $3,750.00 | $4,500.00 | $4,800.00 | $6,750.00 |
| 0690 | Junction box-24 in | EACH A A | 1 | $3,600.00 | $2,500.00 | $4,900.00 | $2,750.00 |
| 0700 | Fabric-geotextile class 2 for pipe | SQYD A A | 1,039 | $2.00 | $2.00 | $2.00 | $2.00 |
| 0710 | Clean roadway drains | EACH A A | 1 | $4,000.00 | $5,000.00 | $3,000.00 | $3,000.00 |
| 0720 | Clean pipe structure | EACH A A | 1 | $4,000.00 | $5,000.00 | $3,000.00 | $3,000.00 |
| 0730 | W flush hydrant assembly | EACH A A | 1 | $11,000 | $8,000.00 | $11,000 | $10,500 |
| 0740 | W pipe PVC 06 inch | LF A A | 1,120 | $34.00 | $43.50 | $65.00 | $62.00 |
| 0750 | W tie-in 06 inch | EACH A A | 2 | $2,500.00 | $3,800.00 | $3,500.00 | $3,200.00 |
| 0760 | W valve 06 inch | EACH A A | 2 | $3,700.00 | $2,600.00 | $1,500.00 | $1,400.00 |
| 0770 | W line marker | EACH A A | 2 | $250.00 | $100.00 | $110.00 | $100.00 |
| 0780 | Demobilization | LS A A | 1 | $15,000 | $16,469 | $18,000 | $17,991 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of August 21, 2025. Compiled by Mirage Metrics.