KYTC contract 25-1026 bid tabulation
ASPHALT REHAB WITH BRIDGE (S) I-64. Let by Kentucky Transportation Cabinet on September 25, 2025. 1 bid received; low bid $19,600,000 by Walker Construction & Materials LLC, +5.7% against the engineer's estimate of $18,541,481.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 25 SEP 2025
- Pay items
- 167
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Walker Construction & Materials LLC | $19,600,000 | Low | +6.0% |
Engineer's estimate: $18,541,481.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Walker Construction & Materials LLC |
|---|---|---|---|---|
| 0010 | Dga base | TON A A | 7,794 | $40.00 |
| 0020 | Crushed aggregate size no 2 | TON A A | 2 | $100.00 |
| 0030 | Asphalt seal aggregate | TON A A | 2,105 | $100.00 |
| 0040 | Asphalt seal coat | TON A A | 254 | $1,050.00 |
| 0050 | Leveling & wedging PG76-22 | TON A A | 4,300 | $125.50 |
| 0060 | CL3 asph base 1.00D PG64-22 | TON A A | 5,000 | $115.50 |
| 0070 | CL4 asph base 1.00D PG76-22 | TON A A | 2,953 | $125.50 |
| 0080 | CL4 asph surf 0.50A PG76-22 | TON A A | 37,099 | $125.50 |
| 0090 | CL4 asph surf 0.38A PG76-22 | TON A A | 20,717 | $125.50 |
| 0100 | Mobilization for mill & text | LS A A | 1 | $3,675.00 |
| 0110 | Mobilization for mill & text | LS A A | 1 | $3,500.00 |
| 0120 | Mobilization for mill & text | LS A A | 1 | $3,500.00 |
| 0130 | Mobilization for mill & text | LS A A | 1 | $3,500.00 |
| 0140 | Asphalt pave milling & texturing | TON A A | 55,515 | $21.00 |
| 0150 | Base failure repair | SQYD A A | 122 | $375.00 |
| 0160 | Pavement repair | SQYD A A | 996 | $175.00 |
| 0170 | Asphalt material for tack non-tracking | TON A A | 231 | $100.00 |
| 0180 | Storm sewer pipe-15 in | LF A A | 127 | $175.00 |
| 0190 | Non-perforated pipe-4 in | LF A A | 34 | $35.00 |
| 0200 | Remove pipe | LF A A | 8 | $60.00 |
| 0210 | Sloped box outlet type 1-15 in | EACH A A | 4 | $6,200.00 |
| 0220 | Drop box inlet type 1 | EACH A A | 1 | $8,250.00 |
| 0230 | Cap drop box inlet | EACH A A | 1 | $3,450.00 |
| 0240 | Remove curb | LF A A | 200 | $25.00 |
| 0250 | Delineator for guardrail mono directional white | EACH A A | 44 | $15.00 |
| 0260 | Delineator for guardrail mono directional yello | EACH A A | 109 | $15.00 |
| 0270 | Relocate temp conc barrier | LF A A | 5,680 | $5.25 |
| 0280 | Barricade-type III | EACH A A | 9 | $225.00 |
| 0290 | Embankment in place | CUYD A A | 2,741 | $50.00 |
| 0300 | Guardrail end treatment type 1 | EACH A A | 1 | $4,500.00 |
| 0310 | Remove guardrail | LF A A | 2,912.50 | $2.00 |
| 0320 | Remove & reset guardrail | LF A A | 263 | $20.00 |
| 0330 | Temporary signs | SQFT A A | 6,000 | $12.72 |
| 0340 | Remove headwall | EACH A A | 4 | $900.00 |
| 0350 | Maintain & control traffic | LS A A | 1 | $175,000 |
| 0360 | Maintain & control traffic | LS A A | 1 | $250,000 |
| 0370 | Maintain & control traffic | LS A A | 1 | $215,000 |
| 0380 | Maintain & control traffic | LS A A | 1 | $150,000 |
| 0390 | Truck mounted attenuator | EACH A A | 4 | $15,000 |
| 0400 | Portable changeable message sign | EACH A A | 8 | $7,500.00 |
| 0410 | Edgeline rumble strips | LF A A | 359,069 | $0.15 |
| 0420 | Silt trap type C | EACH A A | 20 | $200.00 |
| 0430 | Clean silt trap type C | EACH A A | 20 | $20.00 |
| 0440 | Sidewalk-4 in concrete | SQYD A A | 1,876 | $60.00 |
| 0450 | Staking | LS A A | 1 | $20,000 |
| 0460 | Staking | LS A A | 1 | $25,000 |
| 0470 | Staking | LS A A | 1 | $25,000 |
| 0480 | Staking | LS A A | 1 | $15,000 |
| 0490 | Arrow panel | EACH A A | 8 | $2,500.00 |
| 0500 | Relocate crash cushion | EACH A A | 8 | $3,000.00 |
| 0510 | Initial fertilizer | TON A A | 1 | $1,250.00 |
| 0520 | Maintenance fertilizer | TON A A | 1 | $1,250.00 |
| 0530 | Seeding and protection | SQYD A A | 20,217 | $0.65 |
| 0540 | Flexible delineator post-M/W | EACH A A | 2,428 | $65.00 |
| 0550 | Flexible delineator post-M/Y | EACH A A | 196 | $65.00 |
| 0560 | Pave striping-temp paint-6 in | LF A A | 214,122 | $0.24 |
| 0570 | Pave striping-thermo-6 in W | LF A A | 225,522 | $0.95 |
| 0580 | Pave striping-thermo-6 in Y | LF A A | 179,947 | $0.95 |
| 0590 | Pave striping-thermo-12 in W | LF A A | 4,604 | $2.00 |
| 0600 | Pave striping-temp rem tape-B | LF A A | 9,000 | $2.85 |
| 0610 | Pave striping-temp rem tape-W | LF A A | 27,000 | $2.85 |
| 0620 | Pave striping-temp rem tape-Y | LF A A | 9,000 | $2.85 |
| 0630 | Pave striping-dur TY 1-6 in W | LF A A | 1,591 | $9.00 |
| 0640 | Pave striping-dur TY 1-6 in Y | LF A A | 1,269 | $9.00 |
| 0650 | Pave marking-thermo stop bar-24IN | LF A A | 144 | $10.00 |
| 0660 | Pave marking-thermo curv arrow | EACH A A | 30 | $90.00 |
| 0670 | Pavement marker type IV-MW | EACH A A | 556 | $8.00 |
| 0680 | Pavement marker type IV-MY | EACH A A | 514 | $8.00 |
| 0690 | Inlaid pavement marker-B W/R | EACH A A | 2,313 | $26.00 |
| 0700 | Inlaid pavement marker-B Y/R | EACH A A | 135 | $26.00 |
| 0710 | Crash cushion TY 6 class T TL3 | EACH A A | 10 | $7,000.00 |
| 0720 | Fuel adjustment | DOLL A A | 108,409 | $1.00 |
| 0730 | Asphalt adjustment | DOLL A A | 266,354 | $1.00 |
| 0740 | Joint adhesive | LF A A | 340,668 | $0.45 |
| 0750 | Conc barr wall TY 9T-install | LF A A | 7,060 | $35.00 |
| 0760 | Object marker TY 3 | EACH A A | 1 | $75.00 |
| 0770 | Temporary median crossover | EACH A A | 2 | $95,000 |
| 0780 | Law enforcement officer | HOUR A A | 1,600 | $105.00 |
| 0790 | Remove crash cushion | EACH A A | 20 | $1,000.00 |
| 0800 | Remove barrier | LF A A | 320 | $250.00 |
| 0810 | Remove and reset perf pipe headwall | EACH A A | 2 | $1,250.00 |
| 0820 | Guardrail thrie beam | LF A A | 2,981.50 | $65.00 |
| 0830 | G/R steel W beam-S face (7 FT post) | LF A A | 725 | $35.00 |
| 0840 | Water blasting existing stripe | LF A A | 45,000 | $0.35 |
| 0850 | High tension cable-rope barrier | LF A A | 4,222 | $30.00 |
| 0860 | End anchors | EACH A A | 2 | $10,500 |
| 0870 | Median crossover removal | EACH A A | 2 | $90,000 |
| 0880 | Remove cable guardrail barrier system | LF A A | 4,222 | $3.00 |
| 0890 | Pave mark thermo chevron | SQFT A A | 2,915 | $6.50 |
| 0900 | Pave marking-thermo dotted lane exten | LF A A | 934 | $6.50 |
| 0910 | Remove pavement marker | EACH A A | 2,448 | $10.00 |
| 0920 | Pave mount infrared temp equipment | SF A A | 6,070,104 | $0.01 |
| 0930 | Queue protection vehicle | HOUR A A | 3,840 | $1.00 |
| 0940 | Thrie beam guardrail transition TL-3 | EACH A A | 22 | $4,700.00 |
| 0950 | Thrie beam guardrail transition TL-2 | EACH A A | 13 | $3,000.00 |
| 0960 | Furnish queue protection vehicles | MONT A A | 12 | $2,500.00 |
| 0970 | Portable queue warning alert system | MONT A A | 12 | $600.00 |
| 0980 | Queue warning PCMS | MONT A A | 72 | $250.00 |
| 0990 | Queue warning portable radar sensors | MONT A A | 72 | $125.00 |
| 1000 | Mobilization for concrete surf treatment | LS A A | 1 | $3,500.00 |
| 1010 | Mobilization for concrete surf treatment | LS A A | 1 | $3,500.00 |
| 1020 | Mobilization for concrete surf treatment | LS A A | 1 | $3,500.00 |
| 1030 | Mobilization for concrete surf treatment | LS A A | 1 | $3,500.00 |
| 1040 | Thrie beam bullnose terminal | EACH A A | 20 | $22,750 |
| 1050 | Connected arrow panel | MONT A A | 12 | $795.00 |
| 1060 | Electronic delivery MGMT system - agg | LS A A | 1 | $10,000 |
| 1070 | Expan joint replace 1 in | LF A A | 60 | $550.00 |
| 1080 | Armored edge for concrete | LF A A | 60 | $450.00 |
| 1090 | Steel reinforcement | LB A A | 540 | $3.00 |
| 1100 | Epoxy sand slurry | SQYD A A | 45 | $55.00 |
| 1110 | Rem epoxy bit foreign overlay | SQYD A A | 530 | $21.00 |
| 1120 | Conc class M full depth patch | CUYD A A | 9 | $1,100.00 |
| 1130 | Concrete overlay-latex | CUYD A A | 22.10 | $1,450.00 |
| 1140 | Blast cleaning | SQYD A A | 575 | $15.00 |
| 1150 | Partial depth patching | CUYD A A | 19 | $1,500.00 |
| 1160 | Expan joint replace 1 in | LF A A | 60 | $550.00 |
| 1170 | Armored edge for concrete | LF A A | 60 | $450.00 |
| 1180 | Steel reinforcement | LB A A | 540 | $3.00 |
| 1190 | Epoxy sand slurry | SQYD A A | 45 | $55.00 |
| 1200 | Rem epoxy bit foreign overlay | SQYD A A | 530 | $21.00 |
| 1210 | Conc class M full depth patch | CUYD A A | 9 | $1,100.00 |
| 1220 | Concrete overlay-latex | CUYD A A | 22.10 | $1,450.00 |
| 1230 | Blast cleaning | SQYD A A | 575 | $15.00 |
| 1240 | Partial depth patching | CUYD A A | 19 | $1,500.00 |
| 1250 | Concrete-class A | CUYD A A | 109.20 | $1,565.00 |
| 1260 | Steel reinforcement | LB A A | 10,270 | $2.50 |
| 1270 | Remove barrier | LF A A | 87 | $100.00 |
| 1280 | Concrete sealing | SQFT A A | 2,447 | $5.00 |
| 1290 | Concrete-class A | CUYD A A | 112.50 | $1,375.00 |
| 1300 | Steel reinforcement | LB A A | 9,135 | $3.75 |
| 1310 | Remove barrier | LF A A | 69 | $315.00 |
| 1320 | Concrete sealing | SQFT A A | 2,480 | $4.00 |
| 1330 | Bridge barrier retrofit | LF A A | 31 | $1,500.00 |
| 1340 | Concrete sealing | SQFT A A | 545 | $15.00 |
| 1350 | Concrete-class A | CUYD A A | 26.20 | $2,200.00 |
| 1360 | Steel reinforcement | LB A A | 2,395 | $2.50 |
| 1370 | Remove barrier | LF A A | 57 | $100.00 |
| 1380 | Concrete sealing | SQFT A A | 485 | $8.00 |
| 1390 | Bridge barrier retrofit | LF A A | 1,128 | $505.00 |
| 1400 | Concrete sealing | SQFT A A | 6,852 | $4.00 |
| 1410 | Concrete-class A | CUYD A A | 105.60 | $1,690.00 |
| 1420 | Steel reinforcement | LB A A | 8,630 | $2.50 |
| 1430 | Remove barrier | LF A A | 101 | $100.00 |
| 1440 | Concrete sealing | SQFT A A | 2,260 | $8.00 |
| 1450 | Concrete-class A | CUYD A A | 104.50 | $1,575.00 |
| 1460 | Steel reinforcement | LB A A | 9,440 | $4.95 |
| 1470 | Remove barrier | LF A A | 69 | $315.00 |
| 1480 | Concrete sealing | SQFT A A | 2,410 | $4.00 |
| 1490 | Concrete-class A | CUYD A A | 111.30 | $1,625.00 |
| 1500 | Steel reinforcement | LB A A | 7,415 | $2.50 |
| 1510 | Remove barrier | LF A A | 254 | $100.00 |
| 1520 | Concrete sealing | SQFT A A | 2,175 | $4.45 |
| 1530 | Concrete-class A | CUYD A A | 19.30 | $2,520.00 |
| 1540 | Steel reinforcement | LB A A | 2,005 | $2.50 |
| 1550 | Remove barrier | LF A A | 48 | $100.00 |
| 1560 | Concrete sealing | SQFT A A | 400 | $10.00 |
| 1570 | Conduit-1 1/4 in | LF A A | 220 | $14.00 |
| 1580 | Conduit-2 in | LF A A | 60 | $18.00 |
| 1590 | Trenching and backfilling | LF A A | 250 | $13.00 |
| 1600 | Piezoelectric sensor | EACH A A | 12 | $2,500.00 |
| 1610 | Loop wire | LF A A | 4,800 | $1.50 |
| 1620 | Loop saw slot and fill | LF A A | 1,060 | $28.00 |
| 1630 | Galvanized steel cabinet | EACH A A | 6 | $1,100.00 |
| 1640 | Wood post | EACH A A | 12 | $550.00 |
| 1650 | Electrical junction box type A | EACH A A | 6 | $1,415.00 |
| 1660 | Mobilization | LS A A | 1 | $885,000 |
| 1670 | Demobilization | LS A A | 1 | $329,188 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of September 25, 2025. Compiled by Mirage Metrics.