KYTC contract 25-1032 bid tabulation
GRADE, DRAIN & SURFACE WITH BRIDGE I-71 WIDENING. Let by Kentucky Transportation Cabinet on October 23, 2025. 2 bids received; low bid $50,294,708 by Haydon Bridge Company Inc, +5.1% against the engineer's estimate of $47,849,842.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 23 OCT 2025
- Pay items
- 352
- Data through
- 22 OCT 2026
1 of the 2 bids matched their published totals to within a dollar and are shown; the others are left out.
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Haydon Bridge Company Inc | $50,294,708 | Low | +5.0% |
Engineer's estimate: $47,849,842.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Haydon Bridge Company Inc |
|---|---|---|---|---|
| 0010 | Trenching and backfilling | LF A A | 70 | $7.99 |
| 0020 | Cable-no. 14/7C | LF A A | 2,850 | $1.86 |
| 0030 | Anchor | EACH A A | 1 | $631.20 |
| 0040 | Messenger-15400 LB | LF A A | 600 | $8.93 |
| 0050 | Install steel strain pole | EACH A A | 4 | $2,158.02 |
| 0060 | Temp relocation of signal head | EACH A A | 6 | $736.40 |
| 0070 | Install pedestrian head-LED | EACH A A | 4 | $367.81 |
| 0080 | Install LED signal-3 section | EACH A A | 8 | $449.95 |
| 0090 | Install LED signal- 4 section | EACH A A | 1 | $486.70 |
| 0100 | Install pedestrian detector | EACH A A | 4 | $367.81 |
| 0110 | Remove & reinstall coordinating unit | EACH A A | 1 | $1,031.00 |
| 0120 | Traffic signal pole base | CUYD A A | 18 | $456.90 |
| 0130 | Install signal pedestal | EACH A A | 2 | $1,662.55 |
| 0140 | Install pedestal post | EACH A A | 2 | $1,479.84 |
| 0150 | Tether wire | LF A A | 600 | $8.93 |
| 0160 | PVC conduit-1 1/4 in-schedule 80 | LF A A | 70 | $5.99 |
| 0170 | Install signal controller-TY atc | EACH A A | 1 | $25,233 |
| 0180 | Remove signal equipment | EACH A A | 1 | $4,264.73 |
| 0190 | Install radar presence detector type A | EACH A A | 3 | $1,178.46 |
| 0200 | Dga base | TON A A | 18,476 | $27.14 |
| 0210 | Cement stabilized roadbed | SQYD A A | 46,659 | $4.72 |
| 0220 | Drainage blanket-type II-asph | TON A A | 14,145 | $78.00 |
| 0230 | Asphalt seal aggregate | TON A A | 201 | $99.97 |
| 0240 | Asphalt seal coat | TON A A | 24 | $981.00 |
| 0250 | Leveling & wedging PG64-22 | TON A A | 416 | $92.00 |
| 0260 | Leveling & wedging PG76-22 | TON A A | 2,727 | $110.00 |
| 0270 | CL3 asph base 1.00D PG64-22 | TON A A | 8,709 | $79.00 |
| 0280 | CL4 asph base 1.00D PG64-22 | TON A A | 15,068 | $77.00 |
| 0290 | CL4 asph base 1.00D PG76-22 | TON A A | 9,480 | $85.00 |
| 0300 | CL3 asph surf 0.38D PG64-22 | TON A A | 2,537 | $89.00 |
| 0310 | CL4 asph surf 0.38A PG76-22 | TON A A | 11,512 | $96.00 |
| 0320 | Asphalt curing seal | TON A A | 48 | $600.00 |
| 0330 | Cement | TON A A | 938 | $205.45 |
| 0340 | Mobilization for mill & text | LS A A | 1 | $12,500 |
| 0350 | Asphalt pave milling & texturing | TON A A | 10,390 | $21.00 |
| 0360 | Sand for blotter | TON A A | 117 | $1.00 |
| 0370 | Sidewalk-4 in concrete | SQYD A A | 1,110 | $59.13 |
| 0380 | Joint adhesive | LF A A | 106,876 | $0.01 |
| 0390 | Longitudinal edge key | LF A A | 24,912 | $1.20 |
| 0400 | Asphalt material for tack non-tracking | TON A A | 188 | $0.01 |
| 0410 | Crushed aggregate size no 2 | TON A A | 16,033 | $49.28 |
| 0420 | Perforated pipe-6 in | LF A A | 11,290 | $15.65 |
| 0430 | Non-perforated pipe-6 in | LF A A | 424 | $30.00 |
| 0440 | Perf pipe headwall TY 4-6 in | EACH A A | 1 | $1,500.00 |
| 0450 | Flume inlet type 1 | EACH A A | 3 | $5,864.62 |
| 0460 | Flume inlet type 2 | EACH A A | 17 | $5,096.05 |
| 0470 | Special header curb | LF A A | 3,276 | $13.95 |
| 0480 | Lip header curb | LF A A | 165 | $52.53 |
| 0490 | Island header curb type 1 | LF A A | 547 | $45.44 |
| 0500 | Remove concrete roll curb | LF A A | 66 | $32.44 |
| 0510 | Conc median barrier type A TL5 56 in | LF A A | 10,231 | $163.76 |
| 0520 | Conc median barrier type A TL5 56 in | LF A A | 185 | $526.03 |
| 0530 | Delineator for guardrail mono directional white | EACH A A | 405 | $14.19 |
| 0540 | Delineator for guardrail mono directional yello | EACH A A | 10 | $14.19 |
| 0550 | Delineator for barrier - yellow | EACH A A | 200 | $12.57 |
| 0560 | Delineator for guardrail BI directional white | EACH A A | 4 | $13.38 |
| 0570 | Relocate temp conc barrier | LF A A | 18,200 | $9.32 |
| 0580 | Barricade-type III | EACH A A | 8 | $150.00 |
| 0590 | PCC pavement diamond grinding | SQYD A A | 5,618 | $4.00 |
| 0600 | JPC pavement-12 in | SQYD A A | 166 | $184.36 |
| 0610 | JPC pavement-7 in | SQYD A A | 121 | $174.98 |
| 0620 | Remove pavement | SQYD A A | 8,556 | $17.36 |
| 0630 | Temp ditch | LF A A | 6,944 | $1.76 |
| 0640 | Clean temp ditch | LF A A | 3,472 | $1.76 |
| 0650 | Roadway excavation | CUYD A A | 40,364 | $26.91 |
| 0660 | Granular embankment | CUYD A A | 978 | $77.30 |
| 0670 | Water | MGAL A A | 2,400 | $1.00 |
| 0680 | Fence-woven wire type 1 | LF A A | 25,112 | $7.08 |
| 0690 | Double vehicular woven wire gate | EACH A A | 1 | $6,504.57 |
| 0700 | Guardrail-steel W beam-S face | LF A A | 28,412.50 | $27.57 |
| 0710 | Guardrail end treatment type 1 | EACH A A | 7 | $3,447.94 |
| 0720 | Guardrail end treatment type 2M | EACH A A | 10 | $1,854.27 |
| 0730 | Guardrail end treatment type 7 | EACH A A | 1 | $1,975.46 |
| 0740 | Remove guardrail | LF A A | 31,898 | $3.15 |
| 0750 | Remove guardrail terminal sect | EACH A A | 2 | $4.50 |
| 0760 | Remove guardrail end treatment | EACH A A | 9 | $106.06 |
| 0770 | Channel lining class II | TON A A | 644 | $71.16 |
| 0780 | Clearing and grubbing | LS A A | 1 | $74,330 |
| 0790 | Concrete-class B | CUYD A A | 52.52 | $1,761.43 |
| 0800 | Temporary signs | SQFT A A | 1,450 | $7.00 |
| 0810 | Object marker type 2 | EACH A A | 12 | $380.17 |
| 0820 | Project CPM schedule | LS A A | 1 | $45,000 |
| 0830 | Fabric-geotextile class 1 | SQYD A A | 5,372 | $2.64 |
| 0840 | Handrail-type A-2 | LF A A | 80 | $225.00 |
| 0850 | Maintain & control traffic | LS A A | 1 | $45,544 |
| 0860 | Maintain & control traffic | LS A A | 1 | $995,000 |
| 0870 | Portable changeable message sign | EACH A A | 10 | $7,800.00 |
| 0880 | Edgeline rumble strips | LF A A | 42,724 | $0.15 |
| 0890 | Temp silt fence | LF A A | 6,944 | $2.00 |
| 0900 | Silt trap type A | EACH A A | 48 | $150.00 |
| 0910 | Silt trap type B | EACH A A | 48 | $150.00 |
| 0920 | Silt trap type C | EACH A A | 48 | $150.00 |
| 0930 | Clean silt trap type A | EACH A A | 48 | $150.00 |
| 0940 | Clean silt trap type B | EACH A A | 48 | $150.00 |
| 0950 | Clean silt trap type C | EACH A A | 48 | $150.00 |
| 0960 | Staking | LS A A | 1 | $150,000 |
| 0970 | Remove structure | LS A A | 1 | $160,000 |
| 0980 | Remove structure | LS A A | 1 | $160,000 |
| 0990 | Relocate crash cushion | EACH A A | 7 | $5,868.33 |
| 1000 | Masonry coating | SQYD A A | 11,547 | $9.33 |
| 1010 | Conc barrier wall type 9T | LF A A | 26,920 | $36.14 |
| 1020 | Erosion control blanket | SQYD A A | 10,642 | $1.64 |
| 1030 | Temp mulch | SQYD A A | 154,357 | $0.23 |
| 1040 | Temp seeding and protection | SQYD A A | 115,265 | $0.30 |
| 1050 | Initial fertilizer | TON A A | 4.90 | $965.00 |
| 1060 | Maintenance fertilizer | TON A A | 2.90 | $965.00 |
| 1070 | Seeding and protection | SQYD A A | 95,011 | $0.44 |
| 1080 | Agricultural limestone | TON A A | 58.90 | $97.00 |
| 1090 | Flexible delineator post-M/Y | EACH A A | 55 | $78.26 |
| 1100 | Pave striping-temp paint-4 in | LF A A | 1,178 | $0.24 |
| 1110 | Pave striping-temp paint-6 in | LF A A | 196,757 | $0.26 |
| 1120 | Pave striping removal-4 in | LF A A | 1,178 | $0.78 |
| 1130 | Pave striping removal-6 in | LF A A | 27,974 | $0.82 |
| 1140 | Pave striping-thermo-6 in W | LF A A | 44,722 | $1.30 |
| 1150 | Pave striping-thermo-6 in Y | LF A A | 31,927 | $1.30 |
| 1160 | Pave striping-thermo-12 in W | LF A A | 4,018 | $2.60 |
| 1170 | Pave striping-thermo-12 in Y | LF A A | 399 | $2.65 |
| 1180 | Pave striping-temp rem tape-W | LF A A | 5,670 | $2.07 |
| 1190 | Pave striping-temp rem tape-Y | LF A A | 27,613 | $1.97 |
| 1200 | Pave marking-thermo stop bar-24IN | LF A A | 162 | $12.95 |
| 1210 | Pave marking-thermo cross-hatch | SQFT A A | 2,619 | $5.95 |
| 1220 | Pave marking-thermo STR arrow | EACH A A | 4 | $125.00 |
| 1230 | Pave marking-thermo curv arrow | EACH A A | 30 | $135.00 |
| 1240 | Pavement marker TY iva-MW temp | EACH A A | 300 | $7.00 |
| 1250 | Pavement marker TY iva-MY temp | EACH A A | 300 | $7.00 |
| 1260 | Remove pavement marker type V | EACH A A | 1,135 | $6.00 |
| 1270 | Inlaid pavement marker-MW | EACH A A | 636 | $28.00 |
| 1280 | Inlaid pavement marker-MY | EACH A A | 292 | $28.00 |
| 1290 | Inlaid pavement marker-B W/R | EACH A A | 78 | $28.00 |
| 1300 | Inlaid pavement marker-B Y/R | EACH A A | 48 | $28.00 |
| 1310 | Foundation preparation | LS A A | 1 | $1,100,000 |
| 1320 | Retaining wall | SQFT A A | 3,600 | $30.21 |
| 1340 | Crash cushion TY 6 class T TL3 | EACH A A | 4 | $6,196.07 |
| 1350 | Fuel adjustment | DOLL A A | 102,385 | $1.00 |
| 1360 | Asphalt adjustment | DOLL A A | 240,409 | $1.00 |
| 1370 | S manhole adjust to grade | EACH A A | 1 | $3,640.99 |
| 1390 | Object marker TY 3 | EACH A A | 4 | $404.41 |
| 1400 | Site preparation | LS A A | 1 | $225,000 |
| 1410 | Temporary median crossover | EACH A A | 2 | $12,602 |
| 1420 | Law enforcement officer | HOUR A A | 400 | $80.00 |
| 1430 | Remove crash cushion | EACH A A | 11 | $195.96 |
| 1440 | Remove bridge end connector | EACH A A | 35 | $195.96 |
| 1450 | Sawcut pavement | LF A A | 26,057 | $1.50 |
| 1460 | Sound barrier wall | SQFT A A | 72,846 | $38.00 |
| 1470 | Flume inlet TY 2-mod | EACH A A | 1 | $8,998.51 |
| 1480 | Pave marking-thermo yield bar-36 in | LF A A | 144 | $31.00 |
| 1490 | Barrier wall transition | LF A A | 73 | $704.09 |
| 1500 | End anchors | EACH A A | 2 | $13,690 |
| 1510 | Detectable warnings | SQFT A A | 122 | $49.42 |
| 1520 | High friction surface treatment | SQYD A A | 11,236 | $36.25 |
| 1530 | Pave mark TY 1 tape cross-hatch | SQFT A A | 172 | $20.00 |
| 1540 | Median crossover removal | EACH A A | 2 | $0.50 |
| 1550 | Pave mark thermo-lane reduction arrow | EACH A A | 3 | $425.00 |
| 1560 | Remove thermoplastic arrows | EACH A A | 2 | $150.00 |
| 1570 | Crash cushion TY 6 class C TL3 | EACH A A | 1 | $48,799 |
| 1580 | Remove cable guardrail barrier system | LF A A | 10,217 | $3.15 |
| 1590 | Pave mark thermo chevron | SQFT A A | 392 | $5.95 |
| 1600 | Pave mark thermo-wrong way arrow | EACH A A | 10 | $395.00 |
| 1610 | Vibrating wire piezometer | EACH A A | 2 | $2,500.00 |
| 1620 | Remove pavement marker | EACH A A | 544 | $6.00 |
| 1630 | Pave marking-thermo elong route shield | EACH A A | 10 | $3,850.00 |
| 1640 | Thrie beam guardrail transition TL-3 | EACH A A | 18 | $5,882.01 |
| 1650 | Pave mark TY 1 tape lane reduction arrow | EACH A A | 1 | $1,950.00 |
| 1660 | Pave mark TY 1 tape chevron | SQFT A A | 132 | $20.00 |
| 1670 | Thrie beam bullnose terminal | EACH A A | 1 | $25,592 |
| 1680 | Connected arrow panel | MONT A A | 8 | $375.00 |
| 1690 | Pave stripe-wet ref cont tape-6 in W | LF A A | 2,279 | $14.00 |
| 1700 | Pave stripe-wet ref cont tape-6 in Y | LF A A | 1,650 | $14.00 |
| 1710 | Pave stripe-wet ref cont tape-12 in W | LF A A | 607 | $28.00 |
| 1720 | Electronic delivery MGMT system - agg | LS A A | 1 | $0.01 |
| 1730 | Storm sewer pipe-15 in | LF A A | 1,475 | $130.93 |
| 1740 | Storm sewer pipe-18 in | LF A A | 2,146 | $98.74 |
| 1750 | Storm sewer pipe-24 in | LF A A | 53 | $186.57 |
| 1760 | Pipe culvert headwall-18 in | EACH A A | 1 | $2,213.15 |
| 1770 | Pipe culvert headwall-24 in | EACH A A | 1 | $2,332.53 |
| 1780 | Remove pipe | LF A A | 219 | $33.50 |
| 1790 | Sloped and parallel headwall-15 in | EACH A A | 1 | $3,273.57 |
| 1800 | Curb box inlet type B | EACH A A | 1 | $10,651 |
| 1810 | Conc med barr box inlet TY B1 TL5 56 | EACH A A | 3 | $14,194 |
| 1820 | Conc med barr box inlet TY B1 TL5 56 | EACH A A | 9 | $14,674 |
| 1830 | Conc med barr box inlet TY B2 TL5 56 | EACH A A | 32 | $14,175 |
| 1840 | Conc med barr box inlet TY A2 TL5 56 | EACH A A | 4 | $20,122 |
| 1850 | Conc med barr box inlet TY A2 TL5 56 | EACH A A | 1 | $16,347 |
| 1860 | Remove inlet | EACH A A | 31 | $844.53 |
| 1870 | Fabric-geotextile class 2 for pipe | SQYD A A | 5,096 | $2.00 |
| 1880 | Remove headwall | EACH A A | 6 | $803.58 |
| 1890 | Safeloading | CUYD A A | 35 | $962.00 |
| 1900 | Concrete-class A | CUYD A A | 25 | $1,244.44 |
| 1910 | Bore and jack pipe-24 in | LF A A | 56 | $995.26 |
| 1920 | Bore and jack pipe-18 in | LF A A | 71 | $831.82 |
| 1930 | Pipeline inspection | LF A A | 1,957 | $2.35 |
| 1940 | Granular embankment | CUYD A A | 469 | $125.00 |
| 1950 | Foundation preparation | LS A A | 1 | $295,000 |
| 1960 | Concrete-class A | CUYD A A | 1,181.30 | $885.00 |
| 1970 | Steel reinforcement | LB A A | 210,141 | $1.46 |
| 1980 | Junction box-24 in | EACH A A | 4 | $1,200.00 |
| 1990 | Structure granular backfill | CUYD A A | 158.20 | $90.00 |
| 2000 | Armored edge for concrete | LF A A | 58.50 | $150.00 |
| 2010 | Conduit-3 in | LF A A | 287 | $40.00 |
| 2020 | Foundation preparation | LS A A | 1 | $175,000 |
| 2030 | Reinf conc slope wall-4 in | SQYD A A | 210 | $240.00 |
| 2040 | Test piles | LF A A | 290 | $150.00 |
| 2050 | Piles-steel HP14X117 | LF A A | 1,764 | $150.00 |
| 2060 | Pile points-14 in | EACH A A | 32 | $165.00 |
| 2070 | Concrete-class A | CUYD A A | 142.40 | $1,550.00 |
| 2080 | Concrete-class AA | CUYD A A | 221.90 | $1,550.00 |
| 2090 | Steel reinforcement | LB A A | 18,938 | $1.50 |
| 2100 | Steel reinforcement-epoxy coated | LB A A | 64,335 | $1.75 |
| 2110 | Remove superstructure | LS A A | 1 | $190,000 |
| 2120 | Precast PC box beam SB21 | LF A A | 550.30 | $340.00 |
| 2130 | Electrical junction box type A | EACH A A | 4 | $1,750.00 |
| 2140 | Concrete sealing | SQFT A A | 7,580 | $2.00 |
| 2150 | Epoxy injection crack repair | LF A A | 4 | $500.00 |
| 2160 | Mobilization for concrete surf treatment | LS A A | 1 | $1,000.00 |
| 2170 | Junction box-24 in | EACH A A | 6 | $1,200.00 |
| 2180 | Structure granular backfill | CUYD A A | 848 | $80.00 |
| 2190 | Remove concrete masonry | CUYD A A | 278 | $1,150.00 |
| 2200 | Armored edge for concrete | LF A A | 221.50 | $125.00 |
| 2210 | Foundation preparation | LS A A | 1 | $2,750,000 |
| 2220 | Cyclopean stone rip rap | TON A A | 504 | $115.00 |
| 2230 | Test piles | LF A A | 659 | $135.00 |
| 2240 | Piles-steel HP14X89 | LF A A | 3,822 | $135.00 |
| 2250 | Pile points-14 in | EACH A A | 44 | $200.00 |
| 2260 | Concrete-class A | CUYD A A | 735.90 | $1,750.00 |
| 2270 | Concrete-class AA | CUYD A A | 1,215.10 | $1,500.00 |
| 2280 | Mechanical reinf coupler #5 | EACH A A | 80 | $50.00 |
| 2290 | Mechanical reinf coupler #10 | EACH A A | 64 | $200.00 |
| 2300 | Steel reinforcement | LB A A | 91,599 | $2.65 |
| 2310 | Steel reinforcement-epoxy coated | LB A A | 327,278 | $2.05 |
| 2320 | Remove superstructure | LS A A | 1 | $1,075,000 |
| 2330 | Precast PC I beam type 4 | LF A A | 2,878 | $795.00 |
| 2340 | Electrical junction box type A | EACH A A | 4 | $1,750.00 |
| 2350 | Micropile proof test | EACH A A | 2 | $11,000 |
| 2360 | Concrete sealing | SQFT A A | 73,769 | $2.89 |
| 2370 | Deck drain | EACH A A | 40 | $950.00 |
| 2380 | Micropile verification test | EACH A A | 1 | $165,000 |
| 2390 | Mechanical reinf coupler #4-epoxy coated | EACH A A | 1,964 | $61.00 |
| 2400 | PVC conduit-3 in-schedule 80 | LF A A | 492 | $23.00 |
| 2410 | Rail system single slope - 40 in | LF A A | 492 | $150.00 |
| 2420 | Micropile bond zone | EACH A A | 12 | $12,000 |
| 2430 | Galvanic anode | EACH A A | 552 | $130.00 |
| 2440 | Micropiles-9 5/8 in-common | LF A A | 1,544 | $225.00 |
| 2450 | Micropiles-9 5/8 in-solid rock | LF A A | 60 | $725.00 |
| 2460 | Junction box-24 in | EACH A A | 6 | $1,200.00 |
| 2470 | Structure granular backfill | CUYD A A | 229.60 | $80.00 |
| 2480 | Armored edge for concrete | LF A A | 69.10 | $125.00 |
| 2490 | Conduit-3 in | LF A A | 549 | $60.00 |
| 2500 | Foundation preparation | LS A A | 1 | $175,000 |
| 2510 | Crushed aggregate slope prot | TON A A | 271 | $70.00 |
| 2520 | Test piles | LF A A | 439 | $150.00 |
| 2530 | Piles-steel HP14X117 | LF A A | 2,684 | $150.00 |
| 2540 | Pile points-14 in | EACH A A | 32 | $200.00 |
| 2550 | Concrete-class A | CUYD A A | 187.30 | $1,750.00 |
| 2560 | Concrete-class AA | CUYD A A | 449.20 | $1,850.00 |
| 2570 | Mechanical reinf coupler #6 epoxy coated | EACH A A | 1,662 | $81.00 |
| 2580 | Steel reinforcement | LB A A | 27,812 | $2.16 |
| 2590 | Steel reinforcement-epoxy coated | LB A A | 160,270 | $1.94 |
| 2600 | Remove superstructure | LS A A | 1 | $295,000 |
| 2610 | Electrical junction box type A | EACH A A | 4 | $1,600.00 |
| 2620 | Micropile proof test | EACH A A | 2 | $11,000 |
| 2630 | Concrete sealing | SQFT A A | 14,477 | $1.52 |
| 2640 | Epoxy injection crack repair | LF A A | 30 | $225.00 |
| 2650 | PPC I-beam type HN 42-49 | LF A A | 1,085.30 | $1,250.00 |
| 2660 | Micropile verification test | EACH A A | 1 | $165,000 |
| 2670 | Micropile bond zone | EACH A A | 4 | $12,000 |
| 2680 | Micropiles-9 5/8 in-common | LF A A | 496 | $225.00 |
| 2690 | Micropiles-9 5/8 in-solid rock | LF A A | 16 | $725.00 |
| 2700 | Mobilization for concrete surf treatment | LS A A | 1 | $1,250.00 |
| 2710 | Junction box-24 in | EACH A A | 4 | $1,200.00 |
| 2720 | Structure granular backfill | CUYD A A | 196 | $90.00 |
| 2730 | Armored edge for concrete | LF A A | 58.90 | $150.00 |
| 2740 | Foundation preparation | LS A A | 1 | $175,000 |
| 2750 | Crushed aggregate slope prot | TON A A | 199 | $60.00 |
| 2760 | Test piles | LF A A | 424 | $150.00 |
| 2770 | Piles-steel HP14X117 | LF A A | 2,656 | $150.00 |
| 2780 | Pile points-14 in | EACH A A | 32 | $165.00 |
| 2790 | Concrete-class A | CUYD A A | 158.80 | $1,550.00 |
| 2800 | Concrete-class AA | CUYD A A | 224.90 | $1,550.00 |
| 2810 | Steel reinforcement | LB A A | 22,168 | $1.50 |
| 2820 | Steel reinforcement-epoxy coated | LB A A | 47,686 | $1.75 |
| 2830 | Remove superstructure | LS A A | 1 | $190,000 |
| 2840 | Precast PC box beam SB21 | LF A A | 632.70 | $360.00 |
| 2850 | Electrical junction box type A | EACH A A | 4 | $1,600.00 |
| 2860 | Concrete patching repair | SQFT A A | 203 | $150.00 |
| 2870 | Concrete sealing | SQFT A A | 8,731 | $2.00 |
| 2880 | Epoxy injection crack repair | LF A A | 16 | $300.00 |
| 2890 | PVC conduit-3 in-schedule 80 | LF A A | 318 | $15.00 |
| 2900 | Mobilization for concrete surf treatment | LS A A | 1 | $1,000.00 |
| 2910 | Reference marker | EACH A A | 24 | $308.04 |
| 2920 | Barrier mounting bracket | EACH A A | 12 | $372.68 |
| 2930 | GMSS galv steel type A | LB A A | 3,191 | $4.58 |
| 2940 | SBM aluminum panel signs | SQFT A A | 3,038 | $39.38 |
| 2950 | SBM alum sheet signs .080 in | SQFT A A | 301.80 | $41.87 |
| 2960 | SBM alum sheet signs .125 in | SQFT A A | 1,005.90 | $46.71 |
| 2970 | Steel post type 1 | LF A A | 1,654 | $33.68 |
| 2980 | Steel post mile markers | EACH A A | 4 | $397.94 |
| 2990 | Oss galv steel cantilever | EACH A A | 4 | $90,165 |
| 3000 | GMSS galv steel type C | LB A A | 598 | $13.31 |
| 3010 | Rem overhead sign support STR | EACH A A | 5 | $5,394.05 |
| 3020 | Rem overhead struc conc base | EACH A A | 5 | $5,394.05 |
| 3030 | Remove sign support beam | EACH A A | 10 | $359.60 |
| 3040 | Oss galv steel 60 FT truss | EACH A A | 2 | $148,163 |
| 3050 | Class A concrete for signs | CUYD A A | 186.30 | $1,019.63 |
| 3060 | Steel reinforcement for signs | LB A A | 14,708 | $2.51 |
| 3070 | Remove & relocate signs | EACH A A | 4 | $2,400.00 |
| 3080 | Roadway cross section | EACH A A | 19 | $539.41 |
| 3090 | Barrier wall post | EACH A A | 5 | $1,795.66 |
| 3100 | Remove sign | EACH A A | 14 | $719.21 |
| 3110 | GMSS type D | EACH A A | 29 | $602.13 |
| 3120 | Barcode sign inventory | EACH A A | 148 | $44.95 |
| 3130 | Pole 80 FT MTG HT high mast | EACH A A | 4 | $64,232 |
| 3140 | Fused connector kit | EACH A A | 18 | $238.51 |
| 3150 | Marker | EACH A A | 10 | $446.96 |
| 3160 | Trenching and backfilling | LF A A | 3,575 | $7.99 |
| 3170 | Remove lighting | LS A A | 1 | $41,748 |
| 3180 | Electrical junction box type A | EACH A A | 11 | $1,503.12 |
| 3190 | Electrical junction box type C | EACH A A | 2 | $2,295.59 |
| 3200 | Maintain lighting | LS A A | 1 | $41,468 |
| 3210 | Bore and jack conduit | LF A A | 1,240 | $19.77 |
| 3220 | Pole base-high mast | CUYD A A | 20 | $456.90 |
| 3230 | Wire-no. 10 | LF A A | 2,025 | $1.47 |
| 3240 | High mast LED luminaire | EACH A A | 16 | $2,935.98 |
| 3250 | Cable-no. 10/3C ducted | LF A A | 5,415 | $4.32 |
| 3260 | PVC conduit-2 in-schedule 80 | LF A A | 610 | $8.26 |
| 3270 | PVC conduit-3 in-schedule 80 | LF A A | 1,050 | $12.94 |
| 3280 | Conduit-1 1/4 in | LF A A | 80 | $18.55 |
| 3290 | Conduit-2 in | LF A A | 20 | $24.49 |
| 3300 | Electrical junction box type B | EACH A A | 2 | $1,051.95 |
| 3310 | Trenching and backfilling | LF A A | 90 | $7.99 |
| 3320 | Piezoelectric sensor | EACH A A | 6 | $3,094.29 |
| 3330 | Loop wire | LF A A | 2,650 | $0.89 |
| 3340 | Loop saw slot and fill | LF A A | 600 | $19.95 |
| 3350 | Galvanized steel cabinet | EACH A A | 2 | $1,317.72 |
| 3360 | Wood post | EACH A A | 4 | $515.48 |
| 3370 | Site preparation | EACH A A | 1 | $5,963.06 |
| 3380 | Pole base | EACH A A | 1 | $9,482.03 |
| 3390 | Conduit-2 in | LF A A | 525 | $24.49 |
| 3400 | Electrical junction box type B | EACH A A | 1 | $1,051.95 |
| 3410 | Trenching and backfilling | LF A A | 525 | $7.99 |
| 3420 | Wire-no. 4 | LF A A | 1,050 | $2.90 |
| 3430 | Concrete-class A | CUYD A A | 39.70 | $1,019.91 |
| 3440 | Steel reinforcement | LB A A | 2,779 | $2.51 |
| 3450 | CCTV assembly | EACH A A | 2 | $6,726.48 |
| 3460 | Model 336 enclosure | EACH A A | 2 | $22,834 |
| 3470 | Surge device 120 volt | EACH A A | 2 | $2,261.91 |
| 3480 | Data surge device | EACH A A | 2 | $2,263.34 |
| 3490 | Video surge device | EACH A A | 2 | $2,290.50 |
| 3500 | Pole 50 FT-install | EACH A A | 1 | $9,809.26 |
| 3510 | Inst variable message sign-exist truss | EACH A A | 1 | $86,156 |
| 3520 | Trainee payment reimbursement | HOUR A A | 1,400 | $1.00 |
| 3530 | Mobilization | LS A A | 1 | $2,335,000 |
| 3540 | Demobilization | LS A A | 1 | $708,500 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of October 23, 2025. Compiled by Mirage Metrics.