KYTC contract 25-1118 bid tabulation

BRIDGE WITH GRADE, DRAIN & SURFACE NEW CONNECTION FROM THOMPSON ROAD TO US 23 @ STONECOAL. Let by Kentucky Transportation Cabinet on September 25, 2025. 3 bids received; low bid $10,213,906 by Bush & Burchett Inc, -2.8% against the engineer's estimate of $10,509,923.

Owner
Kentucky Transportation Cabinet
Letting
25 SEP 2025
Pay items
130
Data through
22 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Bush & Burchett Inc$10,213,906Low-3.0%
2Haydon Bridge Company Inc$10,987,754+8.0%+5.0%
3Triton Construction Inc$12,995,000+27%+24%
KYTC contract 25-1118: bids by rank

Engineer's estimate: $10,509,923.

Bid tabulation

LinePay itemUnitQuantity1. Bush & Burchett Inc2. Haydon Bridge Company Inc3. Triton Construction Inc
0010Crushed stone baseTON A A7,771$43.75$43.75$46.00
0020Geogrid reinforcement for subgradeSQYD A A10,309$2.60$2.60$3.00
0030Asphalt seal aggregateTON A A21$275.00$275.00$300.00
0040Asphalt seal coatTON A A2.50$1,700.00$1,700.00$1,800.00
0050CL3 asph base 1.00D PG64-22TON A A3,110$189.60$189.60$199.00
0060CL2 asph base 0.75D PG64-22TON A A85$264.85$230.58$280.00
0070CL2 asph surf 0.38D PG64-22TON A A42$241.50$212.75$260.00
0080Asphalt material for tackTON A A7.50$10.00$9.87$11.00
0090CL3 asph surf 0.38B PG64-22TON A A714$241.50$241.50$250.00
0100Cem conc ent pavement-8 inSQYD A A57$200.00$195.00$250.00
0110Fabric-geotextile class 1SQYD A A10,309$2.00$2.00$2.00
0120Remove pipeLF A A640$20.00$20.00$40.00
0130Remove drop box inletEACH A A1$400.00$400.00$900.00
0140Flume inlet type 2EACH A A4$6,000.00$7,950.00$9,000.00
0150Remove curb & gutter box inletEACH A A4$450.00$450.00$900.00
0160Standard curb and gutterLF A A1,791$50.00$58.00$70.00
0170Standard header curbLF A A260$65.00$45.00$95.00
0180Delineator for guardrail BI directional whiteEACH A A16$14.87$14.87$16.00
0190Remove pavementSQYD A A3,800$12.00$12.00$20.00
0200Temp ditchLF A A860$2.00$2.00$2.00
0210Clean temp ditchLF A A430$1.50$1.50$2.00
0220Remove structureLS A A1$200,000$150,000$260,000
0230Embankment in placeCUYD A A22,234$13.00$13.00$45.00
0235Single vehicular chain link gateEACH A A1$7,685.21$7,685.21$7,700.00
0240Guardrail-steel W beam-S faceLF A A1,463$31.85$31.02$32.00
0250Guardrail terminal section no 1EACH A A3$87.06$29.02$88.00
0260Guardrail end treatment type 1EACH A A1$3,609.51$3,609.51$3,700.00
0270Remove guardrailLF A A900$3.00$3.00$3.00
0280Channel lining class IITON A A55$60.00$60.00$70.00
0290Channel lining class IIITON A A54$62.00$62.00$75.00
0300Clearing and grubbingLS A A1$10,000$215,000$200,000
0305Edge keyLF A A241$44.15$44.15$45.00
0310Remove headwallEACH A A1$1,200.00$1,200.00$900.00
0320Maintain & control trafficLS A A1$20,000$40,000$350,000
0330Settlement platformEACH A A1$4,500.00$4,500.00$2,500.00
0340Temp silt fenceLF A A860$4.00$4.00$6.00
0350Silt trap type AEACH A A6$240.00$240.00$450.00
0360Silt trap type BEACH A A6$240.00$245.00$350.00
0370Silt trap type CEACH A A6$340.00$340.00$250.00
0380Clean silt trap type AEACH A A6$50.00$232.00$250.00
0390Clean silt trap type BEACH A A6$50.00$243.00$200.00
0400Clean silt trap type CEACH A A6$50.00$289.00$250.00
0410Sidewalk-4 in concreteSQYD A A461$70.00$125.00$150.00
0420StakingLS A A1$30,000$35,000$35,000
0430Steel pipe-2 1/2 inLF A A15.75$60.00$60.00$50.00
0440Steel pipe-4 inLF A A15.75$95.00$95.00$65.00
0450Erosion control blanketSQYD A A371$2.59$2.59$3.00
0460Temp mulchSQYD A A19,152$0.35$0.35$0.40
0470Temp seeding and protectionSQYD A A14,509$0.37$0.37$0.40
0480Initial fertilizerTON A A0.60$1,778.16$1,778.17$1,800.00
0490Maintenance fertilizerTON A A0.40$1,778.16$1,778.15$1,800.00
0500Seeding and protectionSQYD A A11,656$0.64$0.62$0.65
0510Pave striping-perm paint-6 inLF A A8,907$0.40$0.40$0.40
0520Pave striping-thermo-6 in WLF A A2,262$2.00$2.00$2.00
0530Pave striping-thermo-6 in YLF A A452$2.00$2.00$2.00
0540Pave striping-thermo-12 in WLF A A601$4.00$4.00$4.00
0550Pave marking-thermo stop bar-24INLF A A163$15.00$15.00$15.00
0560Pave marking-thermo cross-hatchSQFT A A236$5.50$5.50$5.50
0570Pave marking-thermo curv arrowEACH A A27$150.00$150.00$150.00
0580Pave marking-thermo comb arrowEACH A A8$300.00$300.00$300.00
0590Fuel adjustmentDOLL A A6,125$1.00$1.00$1.00
0600Asphalt adjustmentDOLL A A15,384$1.00$1.00$1.00
0610Object marker TY 3EACH A A1$45.86$45.86$50.00
0620Remove & relocate signsEACH A A14$427.31$427.31$450.00
0625Longitudinal edge keyLF A A330$34.10$34.10$35.00
0630Striping removalLF A A2,000$2.00$2.00$2.00
0640Detectable warningsSQFT A A36$50.00$45.00$16.00
0650Turf reinforcement mat 1SQYD A A177$9.44$9.44$10.00
0660Remove thermoplastic arrowsEACH A A4$150.00$150.00$150.00
0670R/W monument type 3EACH A A9$151.04$151.04$150.00
0680Pave mark thermo chevronSQFT A A257$7.25$8.00$8.00
0690Vibrating wire piezometerEACH A A1$4,500.00$1,500.00$5,000.00
0700Thrie beam guardrail transition TL-2EACH A A4$1,775.01$1,775.01$1,800.00
0710Electronic delivery MGMT system - aggLS A A1$1,000.00$0.01$1,000.00
0720Storm sewer pipe-18 inLF A A237$168.00$168.00$160.00
0730Storm sewer pipe-24 inLF A A593$174.00$174.00$185.00
0740Pipe culvert headwall-24 inEACH A A2$2,846.00$2,846.00$2,500.00
0750Curb box inlet type AEACH A A4$6,422.00$6,422.00$10,000
0760Drop box inlet type 1EACH A A2$6,870.00$6,870.00$8,500.00
0770Drop box inlet type 11EACH A A1$6,521.00$6,521.00$4,500.00
0780Frame and lid TY 1EACH A A2$1,400.00$1,400.00$700.00
0790Drainage junction box TY BEACH A A2$4,620.00$4,620.00$5,000.00
0800Structure granular backfillCUYD A A912$90.00$85.00$120.00
0810Armored edge for concreteLF A A360$85.00$95.00$108.00
0820Foundation preparationLS A A1$350,000$325,000$520,000
0830Cyclopean stone rip rapTON A A7,760$55.00$62.50$45.00
0840Test pilesLF A A338$200.00$350.00$130.00
0850Piles-steel HP14X89LF A A1,589$100.00$125.00$105.00
0860Pile points-12 inEACH A A24$150.00$0.01$250.00
0870Concrete-class ACUYD A A491.90$1,000.00$1,250.00$1,600.00
0880Concrete-class AACUYD A A847.50$1,250.00$995.00$1,200.00
0890Steel reinforcementLB A A69,828$1.75$2.07$2.50
0900Steel reinforcement-epoxy coatedLB A A275,696$1.75$1.68$2.00
0910Approach slabSQYD A A334$450.00$815.00$450.00
0920Rock soundingsLF A A334$50.00$105.00$70.00
0930Rock coringsLF A A260$85.00$195.00$100.00
0940CSL testing (6 tubes)EACH A A8$4,000.00$1,500.00$7,500.00
0950Concrete sealingSQFT A A48,424$2.00$1.50$2.00
0960Precast PC I beam-HN 72-49LF A A2,373$750.00$750.00$810.00
0970Drilled shaft-84 in-commonLF A A318$2,600.00$3,300.00$3,000.00
0980Drilled shaft-78 in-rockLF A A104$2,600.00$3,500.00$5,000.00
0990Rail system single slope - 40 inLF A A686$125.00$145.00$140.00
1000Mobilization for concrete surf treatmentLS A A1$1,000.00$500.00$1.00
1010Electrical junction box type BEACH A A10$3,063.28$3,063.28$3,064.00
1020Trenching and backfillingLF A A1,765$85.79$85.79$86.00
1030Cable-no. 14/5CLF A A2,302$3.81$3.81$4.00
1040Cable-no. 14/7CLF A A1,248$4.67$4.67$5.00
1050Messenger-10800 LBLF A A773$17.15$17.15$18.00
1060Install steel strain poleEACH A A8$7,500.00$7,500.00$7,500.00
1070Install LED signal-3 sectionEACH A A11$529.36$529.36$530.00
1080Install LED signal- 4 sectionEACH A A2$945.91$945.91$946.00
1090Traffic signal pole baseCUYD A A32.97$750.00$750.00$750.00
1100Install antennaEACH A A1$3,780.62$3,780.62$3,781.00
1110Advance warning flasherEACH A A2$17,759$17,759$17,760
1120PVC conduit-1 1/4 in-schedule 80LF A A1,765$17.10$17.10$18.00
1130PVC conduit-2 in-schedule 80LF A A20$24.24$24.24$25.00
1140Install signal controller-TY atcEACH A A1$35,000$35,000$35,000
1150Remove signal equipmentEACH A A1$12,500$12,500$12,500
1160Install radar presence detector type AEACH A A4$2,287.96$2,287.96$2,288.00
1170Pole 120 FT MTG HT high mastEACH A A1$125,000$125,000$125,000
1180Lighting control equipmentEACH A A1$47,221$47,221$47,222
1190Trenching and backfillingLF A A70$85.79$85.79$86.00
1200Wire-no. 12LF A A360$1.88$1.88$2.00
1210Pole 35 FT woodenEACH A A1$2,264.44$2,264.44$2,265.00
1220Remove lightingLS A A1$34,423$34,423$34,424
1230Pole base-high mastCUYD A A8.70$750.00$750.00$750.00
1240High mast LED luminaireEACH A A4$5,594.02$5,594.02$5,595.00
1250Cable-no. 10/3C ductedLF A A70$12.91$12.91$13.00
1260MobilizationLS A A1$450,000$514,000$609,000
1270DemobilizationLS A A1$145,000$155,804$184,300
KYTC contract 25-1118: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.

Every contract let that day: KYTC letting of September 25, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy