KYTC contract 25-2117 bid tabulation

ASPHALT RESURFACING EKRON TO VINE GROVE ROAD (KY 144). Let by Kentucky Transportation Cabinet on March 20, 2025, Meade, District 4. 8 bids received; low bid $526,000 by E & B Paving LLC, -21% against the engineer's estimate of $663,583.

Owner
Kentucky Transportation Cabinet
Letting
20 MAR 2025
Pay items
19
Data through
22 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1E & B Paving LLC$526,000Low-21%
2C & R Construction and Consulting LLC$535,114+2.0%-19%
3Louisville Paving Company Inc$556,842+6.0%-16%
4Scotty'S Contracting & Stone LLC$557,096+6.0%-16%
5Hall Contracting of Kentucky Inc$586,000+11%-12%
6Flynn Brothers Contracting Inc$593,117+13%-11%
7Mago Construction Company LLC$599,100+14%-10%
8Mac Construction & Excavating Inc$603,074+15%-9.0%
KYTC contract 25-2117: bids by rank

Engineer's estimate: $663,583.

Bid tabulation

LinePay itemUnitQuantity1. E & B Paving LLC2. C & R Construction and Consulting LLC3. Louisville Paving Company Inc4. Scotty'S Contracting & Stone LLC5. Hall Contracting of Kentucky Inc6. Flynn Brothers Contracting Inc
0010Temporary signsSQFT A570$6.36$6.00$4.00$5.20$4.00$6.00
0020Leveling & wedging PG64-22TON A573$74.00$75.00$80.00$86.85$79.00$79.00
0030CL2 asph surf 0.38D PG64-22TON A3,860$74.00$74.10$80.00$81.35$81.00$79.00
0040Asphalt material for tackTON A35$1.00$1.00$0.01$0.01$0.01$318.55
0050Maintain & control trafficLS A1$20,118$3,970.00$14,541$16,925$42,277$51,000
0060Mobilization for mill & textLS A1$8,000.00$5,000.00$3,000.00$6,985.00$5,500.00$850.15
0070Asphalt pave milling & texturingTON A175$8.00$5.80$65.00$55.30$65.00$54.00
0080Edgeline rumble stripsLF A35,884$0.35$0.20$0.38$0.14$0.25$0.25
0090Pave striping-temp paint-4 inLF A20,000$0.01$0.10$0.26$0.01$0.26$0.26
0100Pave striping-thermo-6 in WLF A48,000$1.27$1.63$1.27$1.27$1.27$1.27
0110Pave striping-thermo-6 in YLF A40,000$1.27$1.63$1.27$1.27$1.27$1.27
0120Pave marking-thermo X-walk-12 inLF A190$7.00$7.25$7.00$7.00$7.00$7.00
0130Pave marking-thermo stop bar-24INLF A172$14.00$14.00$14.00$14.00$14.00$14.00
0140Pave marking-thermo curv arrowEACH A2$150.00$150.00$150.00$150.00$150.00$150.00
0150Fuel adjustmentDOLL A6,900$1.00$1.00$1.00$1.00$1.00$1.00
0160Asphalt adjustmentDOLL A17,331$1.00$1.00$1.00$1.00$1.00$1.00
0170Pave mark-thermo-24 in YLF A260$14.00$14.00$14.00$14.00$14.00$14.00
0180Electronic delivery MGMT systemLS A1$1.00$100.00$1.00$0.01$1.00$1.00
0190DemobilizationLS A1$8,350.00$8,000.00$8,500.00$7,874.85$8,800.00$9,199.21
KYTC contract 25-2117: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.

Every contract let that day: KYTC letting of March 20, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy