KYTC contract 25-2161 bid tabulation
ASPHALT RESURFACING POPLAR LEVEL ROAD (KY 864). Let by Kentucky Transportation Cabinet on October 23, 2025. 4 bids received; low bid $1,288,585 by Louisville Paving Company Inc, -17% against the engineer's estimate of $1,554,004.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 23 OCT 2025
- Pay items
- 57
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Louisville Paving Company Inc | $1,288,585 | Low | -17% |
| 2 | Hall Contracting of Kentucky Inc | $1,402,000 | +9.0% | -10% |
| 3 | E & B Paving LLC | $1,442,536 | +12% | -7.0% |
| 4 | Mac Construction & Excavating Inc | $1,448,760 | +12% | -7.0% |
Engineer's estimate: $1,554,004.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Louisville Paving Company Inc | 2. Hall Contracting of Kentucky Inc | 3. E & B Paving LLC | 4. Mac Construction & Excavating Inc |
|---|---|---|---|---|---|---|---|
| 0010 | Leveling & wedging PG64-22 | TON A A | 1,030 | $82.00 | $78.00 | $89.00 | $94.06 |
| 0020 | Adjust manhole frame to grade | EACH A A | 24 | $325.00 | $200.00 | $159.00 | $129.80 |
| 0030 | Temporary signs | SQFT A A | 670 | $4.00 | $4.00 | $6.36 | $6.00 |
| 0040 | Maintain & control traffic | LS A A | 1 | $53,000 | $52,029 | $55,346 | $22,670 |
| 0050 | Portable changeable message sign | EACH A A | 2 | $636.00 | $680.00 | $530.00 | $2,000.00 |
| 0060 | Mobilization for mill & text | LS A A | 1 | $2,500.00 | $2,500.00 | $2,500.00 | $20,000 |
| 0070 | Asphalt pave milling & texturing | TON A A | 6,915 | $12.81 | $20.34 | $13.13 | $19.94 |
| 0080 | Sidewalk-4 in concrete | SQYD A A | 35 | $110.00 | $565.00 | $682.23 | $278.09 |
| 0090 | Arrow panel | EACH A A | 2 | $477.00 | $510.00 | $318.00 | $1,200.00 |
| 0100 | Base failure repair | SQYD A A | 450 | $57.00 | $172.00 | $65.26 | $89.52 |
| 0110 | Adjust water valve | EACH A A | 40 | $150.00 | $100.00 | $68.01 | $129.80 |
| 0120 | Conduit-1 1/4 in | LF A A | 80 | $8.00 | $8.00 | $21.00 | $8.00 |
| 0130 | Conduit-2 in | LF A A | 45 | $10.00 | $10.00 | $28.00 | $10.00 |
| 0140 | Trenching and backfilling | LF A A | 110 | $18.00 | $18.00 | $9.00 | $18.00 |
| 0150 | Piezoelectric sensor | EACH A A | 4 | $2,103.75 | $2,105.00 | $3,725.00 | $2,103.75 |
| 0160 | Loop wire | LF A A | 2,800 | $0.25 | $0.25 | $1.51 | $0.25 |
| 0170 | Loop saw slot and fill | LF A A | 565 | $15.00 | $15.00 | $12.28 | $15.00 |
| 0180 | Remove and replace sidewalk | SQYD A A | 5 | $600.00 | $200.00 | $682.23 | $1,175.69 |
| 0190 | Pave striping-temp paint-4 in | LF A A | 66,000 | $0.19 | $0.19 | $0.19 | $0.19 |
| 0200 | Pave striping-perm paint-4 in | LF A A | 2,000 | $0.23 | $0.23 | $0.23 | $0.23 |
| 0210 | Pave striping-thermo-6 in W | LF A A | 40,000 | $1.15 | $1.15 | $1.15 | $1.15 |
| 0220 | Pave striping-thermo-6 in Y | LF A A | 26,000 | $1.15 | $1.15 | $1.15 | $1.15 |
| 0230 | Pave striping-thermo-12 in W | LF A A | 730 | $2.30 | $2.30 | $2.30 | $2.30 |
| 0240 | Pave striping-thermo-12 in Y | LF A A | 695 | $5.00 | $5.00 | $5.00 | $5.00 |
| 0250 | Pave marking-thermo X-walk-6 in | LF A A | 5,675 | $3.25 | $3.25 | $3.25 | $3.25 |
| 0260 | Pave marking-thermo stop bar-24IN | LF A A | 1,308 | $12.05 | $12.05 | $12.05 | $12.05 |
| 0270 | Pave marking-thermo cross-hatch | SQFT A A | 80 | $5.00 | $5.00 | $5.00 | $5.00 |
| 0280 | Pave marking-thermo curv arrow | EACH A A | 135 | $115.00 | $115.00 | $115.00 | $115.00 |
| 0290 | Pave marking-thermo comb arrow | EACH A A | 3 | $155.00 | $155.00 | $155.00 | $155.00 |
| 0300 | Pave marking-thermo only | EACH A A | 2 | $295.00 | $295.00 | $295.00 | $295.00 |
| 0310 | Remove pavement marker type V | EACH A A | 1,115 | $5.50 | $5.50 | $5.50 | $6.08 |
| 0320 | Fuel adjustment | DOLL A A | 10,764 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0330 | Asphalt adjustment | DOLL A A | 27,035 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0340 | Galvanized steel cabinet | EACH A A | 2 | $2,500.00 | $2,500.00 | $2,117.00 | $2,500.00 |
| 0350 | Wood post | EACH A A | 5 | $500.00 | $500.00 | $590.00 | $500.00 |
| 0360 | Electrical junction box type A | EACH A A | 2 | $1,800.00 | $1,800.00 | $2,111.00 | $1,800.00 |
| 0370 | Law enforcement officer | HOUR A A | 170 | $80.00 | $95.00 | $90.00 | $85.00 |
| 0380 | Electrical junction box-10 X 8 X 4 | EACH A A | 1 | $1,100.00 | $1,100.00 | $839.00 | $1,100.00 |
| 0390 | Pave marking thermo-bike | EACH A A | 94 | $225.00 | $225.00 | $225.00 | $225.00 |
| 0400 | Pave marking-thermo yield bar-36 in | LF A A | 90 | $31.00 | $31.00 | $31.00 | $31.00 |
| 0410 | CL3 asph surf 0.38A PG64-22 | TON A A | 6,915 | $86.00 | $83.50 | $89.00 | $92.75 |
| 0420 | Detectable warnings | SQFT A A | 144 | $34.00 | $35.00 | $101.10 | $45.85 |
| 0430 | Detectable warnings | SQFT A A | 360 | $39.00 | $70.00 | $103.79 | $67.36 |
| 0440 | Pave mark-thermo-X-walk-24 in | LF A A | 810 | $12.05 | $12.05 | $12.05 | $12.05 |
| 0450 | Pave marking thermo-bike lane arrow | EACH A A | 94 | $75.00 | $75.00 | $75.00 | $75.00 |
| 0460 | Pave marking-thermo dotted lane exten | LF A A | 1,575 | $2.25 | $2.25 | $2.25 | $2.25 |
| 0470 | Asphalt material for tack non-tracking | TON A A | 42 | $0.01 | $0.01 | $689.00 | $0.01 |
| 0480 | Install radar presence detector type A | EACH A A | 36 | $1,000.00 | $1,000.00 | $1,123.00 | $1,000.00 |
| 0490 | Standard header curb mod | LF A A | 88 | $85.00 | $42.00 | $86.79 | $65.43 |
| 0500 | Standard barrier median type 4 mod | SQYD A A | 2 | $750.00 | $490.00 | $601.83 | $2,101.80 |
| 0510 | Temporary signs | SQFT A A | 300 | $4.00 | $4.00 | $6.00 | $6.00 |
| 0520 | Maintain & control traffic | LS A A | 1 | $10,000 | $1,775.00 | $3,575.00 | $13,050 |
| 0530 | Concrete-class A | CUYD A A | 3 | $550.00 | $600.00 | $363.76 | $1,710.47 |
| 0540 | Remove non-mountable median | SQYD A A | 16 | $22.90 | $300.00 | $145.80 | $212.41 |
| 0550 | Adjust drainage structure | EACH A A | 1 | $1,600.00 | $2,600.00 | $795.00 | $6,152.81 |
| 0560 | Remove mountable median | SQYD A A | 123 | $286.00 | $410.00 | $534.24 | $362.32 |
| 0570 | Demobilization | LS A A | 1 | $20,312 | $21,041 | $21,200 | $23,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of October 23, 2025. Compiled by Mirage Metrics.