KYTC contract 25-2316 bid tabulation
JPC PAVEMENT REPAIRS FRANKLIN AND SHELBY COUNTIES (US 127 & KY 55). Let by Kentucky Transportation Cabinet on August 21, 2025. 4 bids received; low bid $2,056,071 by Bluegrass Contracting Corporation, -39% against the engineer's estimate of $3,355,329.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 21 AUG 2025
- Pay items
- 21
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Bluegrass Contracting Corporation | $2,056,071 | Low | -39% |
| 2 | Hall Contracting of Kentucky Inc | $2,377,000 | +16% | -29% |
| 3 | The Harper Company DBA the W L Harper Co | $2,401,916 | +17% | -28% |
| 4 | E & B Paving LLC | $3,132,000 | +52% | -7.0% |
Engineer's estimate: $3,355,329.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Bluegrass Contracting Corporation | 2. Hall Contracting of Kentucky Inc | 3. The Harper Company DBA the W L Harper Co | 4. E & B Paving LLC |
|---|---|---|---|---|---|---|---|
| 0010 | Dga base | TON A A | 1,350 | $39.25 | $35.00 | $48.86 | $120.00 |
| 0020 | Barricade-type III | EACH A A | 5 | $180.00 | $250.00 | $150.00 | $159.00 |
| 0030 | Remove PCC pavement | SQYD A A | 8,897 | $38.25 | $45.00 | $56.81 | $45.00 |
| 0040 | JPC pavement-10 in | SQYD A A | 8,897 | $111.00 | $125.00 | $134.96 | $143.00 |
| 0050 | Saw-clean-reseal tverse joint | LF A A | 24,800 | $1.90 | $1.69 | $3.90 | $5.00 |
| 0060 | Saw-clean-reseal longit joint | LF A A | 154,600 | $1.90 | $1.69 | $1.20 | $3.00 |
| 0070 | Flowable fill | CUYD A A | 280 | $222.00 | $180.00 | $196.75 | $285.00 |
| 0080 | Temporary signs | SQFT A A | 770 | $9.50 | $5.00 | $8.00 | $8.48 |
| 0090 | Maintain & control traffic | LS A A | 1 | $45,000 | $150,000 | $74,057 | $224,000 |
| 0100 | Maintain & control traffic | LS A A | 1 | $41,000 | $150,000 | $65,147 | $214,434 |
| 0110 | Portable changeable message sign | EACH A A | 5 | $5,925.00 | $4,452.00 | $2,477.60 | $6,678.00 |
| 0120 | Arrow panel | EACH A A | 3 | $4,000.00 | $2,968.00 | $1,681.23 | $3,021.00 |
| 0130 | Pave striping-temp paint-6 in | LF A A | 10,000 | $0.23 | $0.24 | $0.21 | $0.24 |
| 0140 | Pave striping-perm paint-6 in | LF A A | 105,000 | $0.29 | $0.30 | $0.26 | $0.30 |
| 0150 | Pave mark TY 1 tape stop bar-24 in | LF A A | 20 | $57.00 | $30.00 | $50.00 | $30.00 |
| 0160 | Pave mark TY 1 tape-curv arrow | EACH A A | 5 | $680.00 | $200.00 | $600.00 | $200.00 |
| 0170 | Pave stripe-wet ref tape-6 in Y | LF A A | 3,700 | $11.30 | $9.50 | $10.00 | $9.50 |
| 0180 | Pave stripe-wet ref tape-6 in W | LF A A | 2,200 | $11.30 | $9.50 | $10.00 | $9.50 |
| 0190 | Electronic delivery MGMT system - agg | LS A A | 1 | $1,000.00 | $1.00 | $1.00 | $1.00 |
| 0200 | Electronic delivery MGMT system - agg | LS A A | 1 | $1,000.00 | $1.00 | $1.00 | $1.00 |
| 0210 | Demobilization | LS A A | 1 | $30,386 | $35,858 | $36,500 | $50,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of August 21, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.