KYTC contract 25-2326 bid tabulation
SLIDE REPAIR CARTER & LEWIS COUNTIES (US 60, KY 8, & KY 57). Let by Kentucky Transportation Cabinet on August 21, 2025. 2 bids received; low bid $1,164,959 by Hinkle Environmental Services LLC, -19% against the engineer's estimate of $1,446,289.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 21 AUG 2025
- Pay items
- 29
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Hinkle Environmental Services LLC | $1,164,959 | Low | -19% |
| 2 | Nattco Inc | $1,324,244 | +14% | -8.0% |
Engineer's estimate: $1,446,289.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Hinkle Environmental Services LLC | 2. Nattco Inc |
|---|---|---|---|---|---|
| 0010 | Dga base | TON A A | 400 | $48.00 | $60.00 |
| 0020 | Crushed aggregate size no 2 | TON A A | 4,514 | $42.00 | $75.00 |
| 0030 | Leveling & wedging PG64-22 | TON A A | 205 | $145.50 | $146.00 |
| 0040 | CL2 asph base 1.00D PG64-22 | TON A A | 415 | $137.00 | $140.00 |
| 0050 | CL2 asph surf 0.38D PG64-22 | TON A A | 400 | $150.25 | $150.00 |
| 0070 | Delineator for guardrail BI directional white | EACH A A | 65 | $13.00 | $13.00 |
| 0080 | Roadway excavation | CUYD A A | 3,009 | $12.50 | $20.00 |
| 0090 | Guardrail-steel W beam-S face | LF A A | 2,975 | $28.50 | $28.50 |
| 0100 | Guardrail end treatment type 1 | EACH A A | 2 | $3,500.00 | $3,500.00 |
| 0110 | Guardrail end treatment type 7 | EACH A A | 10 | $1,600.00 | $1,600.00 |
| 0120 | Temporary signs | SQFT A A | 400 | $8.00 | $10.00 |
| 0130 | Fabric-geotextile class 1 | SQYD A A | 1,633 | $3.00 | $5.00 |
| 0140 | Maintain & control traffic | LS A A | 1 | $35,000 | $7,925.00 |
| 0150 | Maintain & control traffic | LS A A | 1 | $35,000 | $18,425 |
| 0160 | Maintain & control traffic | LS A A | 1 | $35,000 | $11,251 |
| 0170 | Maintain & control traffic | LS A A | 1 | $35,000 | $36,630 |
| 0180 | Mobilization for mill & text | LS A A | 1 | $2,000.00 | $2,000.00 |
| 0190 | Mobilization for mill & text | LS A A | 1 | $2,000.00 | $2,000.00 |
| 0200 | Mobilization for mill & text | LS A A | 1 | $2,000.00 | $2,000.00 |
| 0210 | Mobilization for mill & text | LS A A | 1 | $3,500.00 | $3,500.00 |
| 0220 | Asphalt pave milling & texturing | TON A A | 450 | $66.00 | $66.00 |
| 0230 | Railroad rails-drilled | LF A A | 12,560 | $25.00 | $30.00 |
| 0240 | Cribbing | SQFT A A | 14,090 | $9.75 | $8.00 |
| 0250 | Pave striping-perm paint-4 in | LF A A | 6,900 | $0.50 | $1.00 |
| 0260 | Electronic delivery MGMT system - agg | LS A A | 1 | $700.00 | $500.00 |
| 0270 | Electronic delivery MGMT system - agg | LS A A | 1 | $700.00 | $500.00 |
| 0280 | Electronic delivery MGMT system - agg | LS A A | 1 | $700.00 | $500.00 |
| 0290 | Electronic delivery MGMT system - agg | LS A A | 1 | $1,700.00 | $1,500.00 |
| 0300 | Demobilization | LS A A | 1 | $17,217 | $19,836 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of August 21, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.