KYTC contract 25-2353 bid tabulation
SLIDE REPAIR KY 1087, KY 1088, KY 1410 & KY 2759 FEMA REPAIRS. Let by Kentucky Transportation Cabinet on September 25, 2025. 3 bids received; low bid $666,597 by Nattco Inc, -31% against the engineer's estimate of $969,693.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 25 SEP 2025
- Pay items
- 27
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Nattco Inc | $666,597 | Low | -31% |
| 2 | Hinkle Environmental Services LLC | $714,499 | +7.0% | -26% |
| 3 | Blue Rock LLC | $719,442 | +8.0% | -26% |
Engineer's estimate: $969,693.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Nattco Inc | 2. Hinkle Environmental Services LLC | 3. Blue Rock LLC |
|---|---|---|---|---|---|---|
| 0010 | Dga base | TON A A | 181 | $90.00 | $75.00 | $90.00 |
| 0020 | Delineator for guardrail BI directional white | EACH A A | 39 | $15.00 | $15.00 | $20.00 |
| 0030 | Site preparation | EACH A A | 1 | $6,000.00 | $9,500.00 | $18,000 |
| 0040 | Site preparation | EACH A A | 1 | $6,000.00 | $9,500.00 | $19,000 |
| 0050 | Site preparation | EACH A A | 1 | $6,000.00 | $9,500.00 | $6,000.00 |
| 0060 | Site preparation | EACH A A | 1 | $6,000.00 | $9,500.00 | $10,000 |
| 0070 | Guardrail-steel W beam-S face | LF A A | 312.50 | $31.00 | $45.00 | $70.00 |
| 0080 | Guardrail terminal section no 1 | EACH A A | 1 | $100.00 | $115.00 | $110.00 |
| 0090 | Guardrail end treatment type 7 | EACH A A | 12 | $1,500.00 | $1,550.00 | $2,100.00 |
| 0100 | Remove & reset guardrail | LF A A | 862.50 | $20.00 | $15.00 | $25.00 |
| 0110 | Channel lining class II | TON A A | 144 | $90.00 | $110.00 | $90.00 |
| 0120 | Channel lining class III | TON A A | 578 | $90.00 | $75.00 | $95.00 |
| 0130 | Temporary signs | SQFT A A | 1,400 | $2.50 | $8.00 | $4.50 |
| 0140 | Fabric-geotextile class 1 | SQYD A A | 3,006 | $4.00 | $3.00 | $4.00 |
| 0150 | Maintain & control traffic | LS A A | 1 | $18,000 | $20,000 | $10,000 |
| 0160 | Maintain & control traffic | LS A A | 1 | $27,000 | $20,000 | $20,500 |
| 0170 | Maintain & control traffic | LS A A | 1 | $9,000.00 | $20,000 | $3,500.00 |
| 0180 | Maintain & control traffic | LS A A | 1 | $18,000 | $20,000 | $7,000.00 |
| 0190 | Railroad rails-drilled | LF A A | 8,814 | $25.00 | $27.25 | $25.00 |
| 0200 | Excavation and backfill | CUYD A A | 1,194 | $90.00 | $100.00 | $90.00 |
| 0210 | Cribbing | SQFT A A | 7,992 | $10.00 | $9.50 | $10.00 |
| 0220 | Erosion control | LS A A | 1 | $50.00 | $200.00 | $2,000.00 |
| 0230 | Erosion control | LS A A | 1 | $50.00 | $200.00 | $2,000.00 |
| 0240 | Erosion control | LS A A | 1 | $50.00 | $200.00 | $1,500.00 |
| 0250 | Erosion control | LS A A | 1 | $50.00 | $200.00 | $1,500.00 |
| 0260 | Excavation | CUYD A A | 230 | $45.00 | $45.00 | $90.00 |
| 0270 | Demobilization | LS A A | 1 | $9,900.00 | $10,560 | $18,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of September 25, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.