KYTC contract 25-2365 bid tabulation
FLOOD REPAIR FOR FEMA KY 343, KY 588, KY 1148, KY 1410, KY 1811, KY 2034 & KY 2035. Let by Kentucky Transportation Cabinet on October 23, 2025. 3 bids received; low bid $972,815 by Blue Rock LLC, -12% against the engineer's estimate of $1,110,786.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 23 OCT 2025
- Pay items
- 37
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Blue Rock LLC | $972,815 | Low | -12% |
| 2 | Nattco Inc | $1,009,417 | +4.0% | -9.0% |
| 3 | Hinkle Environmental Services LLC | $1,065,459 | +10% | -4.0% |
Engineer's estimate: $1,110,786.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Blue Rock LLC | 2. Nattco Inc | 3. Hinkle Environmental Services LLC |
|---|---|---|---|---|---|---|
| 0010 | Dga base | TON A A | 307 | $90.00 | $100.00 | $90.00 |
| 0020 | Delineator for guardrail BI directional white | EACH A A | 66 | $22.00 | $20.00 | $14.00 |
| 0030 | Site preparation | EACH A A | 1 | $2,500.00 | $9,950.00 | $6,000.00 |
| 0040 | Site preparation | EACH A A | 1 | $2,500.00 | $9,950.00 | $6,000.00 |
| 0050 | Site preparation | EACH A A | 1 | $2,500.00 | $9,950.00 | $6,000.00 |
| 0060 | Site preparation | EACH A A | 1 | $2,500.00 | $9,950.00 | $6,000.00 |
| 0070 | Site preparation | EACH A A | 1 | $2,000.00 | $9,950.00 | $6,000.00 |
| 0080 | Site preparation | EACH A A | 1 | $2,000.00 | $9,950.00 | $6,000.00 |
| 0090 | Site preparation | EACH A A | 1 | $2,000.00 | $9,950.00 | $6,000.00 |
| 0100 | Guardrail-steel W beam-S face | LF A A | 737.50 | $41.00 | $37.00 | $36.00 |
| 0110 | Guardrail end treatment type 1 | EACH A A | 1 | $5,500.00 | $5,000.00 | $4,075.00 |
| 0120 | Guardrail end treatment type 7 | EACH A A | 15 | $2,097.00 | $1,500.00 | $1,525.00 |
| 0130 | Remove & reset guardrail | LF A A | 1,300 | $21.37 | $15.00 | $15.50 |
| 0140 | Remove guardrail end treatment | EACH A A | 2 | $200.00 | $100.00 | $150.00 |
| 0160 | Channel lining class II | TON A A | 193 | $90.00 | $95.00 | $104.00 |
| 0170 | Channel lining class III | TON A A | 766 | $95.00 | $100.00 | $82.00 |
| 0180 | Temporary signs | SQFT A A | 2,450 | $6.00 | $2.50 | $8.00 |
| 0190 | Fabric-geotextile class 1 | SQYD A A | 3,716 | $4.00 | $4.00 | $3.00 |
| 0200 | Maintain & control traffic | LS A A | 1 | $11,500 | $12,775 | $20,000 |
| 0210 | Maintain & control traffic | LS A A | 1 | $11,500 | $12,775 | $20,000 |
| 0220 | Maintain & control traffic | LS A A | 1 | $11,500 | $12,775 | $20,000 |
| 0230 | Maintain & control traffic | LS A A | 1 | $11,500 | $12,775 | $20,000 |
| 0240 | Maintain & control traffic | LS A A | 1 | $13,500 | $12,775 | $20,000 |
| 0250 | Maintain & control traffic | LS A A | 1 | $8,000.00 | $12,775 | $20,000 |
| 0260 | Maintain & control traffic | LS A A | 1 | $8,000.00 | $12,775 | $20,000 |
| 0270 | Railroad rails-drilled | LF A A | 15,015 | $25.00 | $24.00 | $27.25 |
| 0280 | Excavation and backfill | CUYD A A | 1,475 | $80.00 | $95.00 | $80.00 |
| 0290 | Cribbing | SQFT A A | 9,872 | $10.00 | $10.00 | $10.75 |
| 0300 | Erosion control | LS A A | 1 | $2,000.00 | $100.00 | $100.00 |
| 0310 | Erosion control | LS A A | 1 | $2,000.00 | $100.00 | $100.00 |
| 0320 | Erosion control | LS A A | 1 | $2,000.00 | $100.00 | $100.00 |
| 0330 | Erosion control | LS A A | 1 | $2,000.00 | $100.00 | $100.00 |
| 0340 | Erosion control | LS A A | 1 | $3,500.00 | $100.00 | $100.00 |
| 0345 | Erosion control | LS A A | 1 | $2,500.00 | $100.00 | $100.00 |
| 0350 | Erosion control | LS A A | 1 | $1,500.00 | $100.00 | $100.00 |
| 0360 | Excavation | CUYD A A | 289 | $40.00 | $45.00 | $60.00 |
| 0370 | Demobilization | LS A A | 1 | $18,000 | $15,000 | $16,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of October 23, 2025. Compiled by Mirage Metrics.