KYTC contract 25-3118 bid tabulation
ASPHALT RESURFACING VARIOUS ROADS IN SPENCER CO. Let by Kentucky Transportation Cabinet on October 23, 2025. 5 bids received; low bid $444,500 by Louisville Paving Company Inc, -20% against the engineer's estimate of $553,212.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 23 OCT 2025
- Pay items
- 20
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Louisville Paving Company Inc | $444,500 | Low | -20% |
| 2 | Mago Construction Company LLC | $457,635 | +3.0% | -17% |
| 3 | Flynn Brothers Contracting Inc | $489,659 | +10% | -11% |
| 4 | E & B Paving LLC | $496,500 | +12% | -10% |
| 5 | Mac Construction & Excavating Inc | $514,287 | +16% | -7.0% |
Engineer's estimate: $553,212.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Louisville Paving Company Inc | 2. Mago Construction Company LLC | 3. Flynn Brothers Contracting Inc | 4. E & B Paving LLC | 5. Mac Construction & Excavating Inc |
|---|---|---|---|---|---|---|---|---|
| 0010 | Leveling & wedging PG64-22 | TON A A | 331 | $78.00 | $81.60 | $77.95 | $127.07 | $88.12 |
| 0020 | CL2 asph surf 0.38D PG64-22 | TON A A | 4,155 | $78.00 | $81.60 | $79.30 | $80.00 | $87.41 |
| 0030 | Asphalt material for tack | TON A A | 21 | $0.01 | $0.01 | $425.00 | $1.00 | $0.01 |
| 0040 | Temporary signs | SQFT A A | 780 | $4.00 | $0.01 | $4.00 | $7.42 | $7.00 |
| 0050 | Maintain & control traffic | LS A A | 1 | $15,000 | $3,050.00 | $20,015 | $15,500 | $15,125 |
| 0060 | Maintain & control traffic | LS A A | 1 | $5,006.63 | $4,550.00 | $20,015 | $14,072 | $21,516 |
| 0070 | Mobilization for mill & text | LS A A | 1 | $1,500.00 | $2,700.00 | $750.00 | $5,000.00 | $2,950.00 |
| 0080 | Mobilization for mill & text | LS A A | 1 | $1,500.00 | $10,850 | $750.00 | $5,000.00 | $2,950.00 |
| 0090 | Asphalt pave milling & texturing | TON A A | 215 | $10.00 | $0.01 | $77.35 | $8.00 | $0.01 |
| 0100 | Edgeline rumble strips | LF A A | 38,227 | $0.32 | $0.22 | $0.24 | $0.32 | $0.27 |
| 0110 | Pave striping-temp paint-4 in | LF A A | 48,227 | $0.01 | $0.18 | $0.01 | $0.18 | $0.18 |
| 0120 | Pave striping-perm paint-4 in | LF A A | 100,500 | $0.20 | $0.20 | $0.20 | $0.20 | $0.20 |
| 0130 | Pave marking-thermo stop bar-24IN | LF A A | 45 | $12.00 | $12.00 | $12.00 | $12.00 | $12.00 |
| 0140 | Pave marking-thermo cross-hatch | SQFT A A | 125 | $5.25 | $5.25 | $5.25 | $5.25 | $5.25 |
| 0150 | Pave marking-thermo comb arrow | EACH A A | 2 | $155.00 | $155.00 | $155.00 | $155.00 | $155.00 |
| 0160 | Fuel adjustment | DOLL A A | 6,983 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0170 | Asphalt adjustment | DOLL A A | 17,538 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0180 | Pave marking-thermo yield bar-36 in | LF A A | 12 | $29.00 | $29.00 | $29.00 | $29.00 | $29.00 |
| 0190 | Pave marking-thermo dotted lane exten | LF A A | 200 | $2.25 | $2.25 | $2.25 | $2.25 | $2.25 |
| 0200 | Demobilization | LS A A | 1 | $6,675.00 | $6,400.69 | $7,578.45 | $7,100.00 | $8,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of October 23, 2025. Compiled by Mirage Metrics.