KYTC contract 26-1103 bid tabulation
ASPHALT SURFACE WITH GRADE & DRAIN WENDELL H. FORD AIRPORT ACCESS ROAD (NEW ROUTE). Let by Kentucky Transportation Cabinet on January 29, 2026. 2 bids received; low bid $15,260,490 by Bizzack Construction LLC, -31% against the engineer's estimate of $21,984,237.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 29 JAN 2026
- Pay items
- 126
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Bizzack Construction LLC | $15,260,490 | Low | -31% |
| 2 | Frederick & May Construction Co | $17,360,146 | +14% | -21% |
Engineer's estimate: $21,984,237.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Bizzack Construction LLC | 2. Frederick & May Construction Co |
|---|---|---|---|---|---|
| 0010 | Crushed stone base | TON A A | 18,001 | $47.35 | $47.35 |
| 0020 | Traffic bound base | TON A A | 440 | $43.55 | $50.00 |
| 0030 | Asphalt seal aggregate | TON A A | 178 | $138.20 | $138.20 |
| 0040 | Asphalt seal coat | TON A A | 21 | $975.10 | $975.10 |
| 0050 | CL2 asph base 1.00D PG64-22 | TON A A | 10,171 | $141.85 | $141.85 |
| 0060 | CL3 asph base 1.00D PG76-22 | TON A A | 1,949 | $152.40 | $152.40 |
| 0070 | CL2 asph surf 0.38D PG64-22 | TON A A | 2,883 | $166.85 | $166.85 |
| 0080 | Asphalt material for tack | TON A A | 55 | $750.00 | $750.00 |
| 0090 | CL3 asph surf 0.38B PG76-22 | TON A A | 921 | $178.50 | $178.50 |
| 0100 | Asphalt pave milling & texturing | TON A A | 814 | $38.75 | $38.75 |
| 0110 | Crushed aggregate size no 2 | TON A A | 14 | $57.60 | $60.00 |
| 0120 | Perforated pipe-4 in | LF A A | 543 | $20.87 | $15.00 |
| 0130 | Non-perforated pipe-4 in | LF A A | 181 | $22.12 | $15.00 |
| 0140 | Perf pipe headwall TY 1-4 in | EACH A A | 5 | $750.00 | $800.00 |
| 0150 | Perf pipe headwall TY 3-4 in | EACH A A | 7 | $750.00 | $800.00 |
| 0160 | Perf pipe headwall TY 4-4 in | EACH A A | 2 | $750.00 | $800.00 |
| 0170 | Standard curb and gutter mod | LF A A | 1,272 | $42.14 | $42.14 |
| 0180 | Standard header curb mod | LF A A | 210 | $36.95 | $36.95 |
| 0190 | Delineator for guardrail BI directional white | EACH A A | 3 | $13.04 | $13.04 |
| 0200 | Barricade-type III | EACH A A | 10 | $240.00 | $100.00 |
| 0210 | Temp ditch | LF A A | 5,148 | $1.00 | $1.00 |
| 0220 | Clean temp ditch | LF A A | 2,574 | $0.01 | $0.10 |
| 0230 | Roadway excavation | CUYD A A | 1,603,406 | $4.75 | $5.40 |
| 0240 | Special excavation | CUYD A A | 75,000 | $4.93 | $7.40 |
| 0250 | Water | MGAL A A | 195 | $10.00 | $1.00 |
| 0260 | Guardrail-steel W beam-S face | LF A A | 219 | $29.62 | $29.62 |
| 0270 | Guardrail end treatment type 4A | EACH A A | 1 | $3,748.19 | $3,748.19 |
| 0280 | Right-of-way monument type 1 | EACH A A | 80 | $128.11 | $225.00 |
| 0290 | Witness post | EACH A A | 8 | $111.02 | $225.00 |
| 0300 | Channel lining class II | TON A A | 2,921 | $53.13 | $60.00 |
| 0310 | Channel lining class III | TON A A | 4,775 | $53.13 | $63.00 |
| 0320 | Clearing and grubbing | LS A A | 1 | $207,400 | $350,000 |
| 0330 | Concrete-class B | CUYD A A | 13.44 | $691.63 | $691.63 |
| 0340 | Temporary signs | SQFT A A | 324 | $16.96 | $18.00 |
| 0350 | Edge key | LF A A | 259 | $30.15 | $30.15 |
| 0360 | Fabric-geotextile class 2 for pipe | SQYD A A | 10,576 | $2.00 | $2.00 |
| 0370 | Maintain & control traffic | LS A A | 1 | $60,000 | $50,000 |
| 0380 | Diversions (by-pass detours) | LS A A | 1 | $12,000 | $15,000 |
| 0390 | Portable changeable message sign | EACH A A | 4 | $6,000.00 | $9,500.00 |
| 0400 | Mobilization for mill & text | LS A A | 1 | $5,500.00 | $5,500.00 |
| 0410 | Shoulder rumble strips | LF A A | 20,176 | $0.20 | $0.20 |
| 0420 | Temp silt fence | LF A A | 5,148 | $2.99 | $2.00 |
| 0430 | Silt trap type A | EACH A A | 88 | $90.00 | $25.00 |
| 0440 | Silt trap type B | EACH A A | 88 | $200.00 | $25.00 |
| 0450 | Silt trap type C | EACH A A | 88 | $140.00 | $25.00 |
| 0460 | Clean silt trap type A | EACH A A | 88 | $0.01 | $10.00 |
| 0470 | Clean silt trap type B | EACH A A | 88 | $0.01 | $10.00 |
| 0480 | Clean silt trap type C | EACH A A | 88 | $0.01 | $10.00 |
| 0490 | Staking | LS A A | 1 | $80,000 | $45,000 |
| 0500 | Conc barrier wall type 9T | LF A A | 80 | $21.81 | $120.00 |
| 0510 | Erosion control blanket | SQYD A A | 2,011 | $2.20 | $2.20 |
| 0520 | Temp mulch | SQYD A A | 282,096 | $0.34 | $0.34 |
| 0530 | Temp seeding and protection | SQYD A A | 213,709 | $0.36 | $0.36 |
| 0540 | Initial fertilizer | TON A A | 19 | $1,703.70 | $1,703.70 |
| 0550 | Maintenance fertilizer | TON A A | 13 | $1,703.70 | $1,703.70 |
| 0560 | Seeding and protection | SQYD A A | 213,709 | $0.55 | $0.55 |
| 0570 | Agricultural limestone | TON A A | 264 | $68.43 | $68.43 |
| 0580 | SBM alum sheet signs .080 in | SQFT A A | 208 | $32.42 | $32.42 |
| 0590 | Steel post type 1 | LF A A | 410 | $21.39 | $21.39 |
| 0600 | Pave striping-temp paint-4 in | LF A A | 2,316 | $0.57 | $0.55 |
| 0610 | Pave striping-perm paint-4 in | LF A A | 38,263 | $0.25 | $0.24 |
| 0620 | Pave striping-thermo-6 in W | LF A A | 6,640 | $1.30 | $1.25 |
| 0630 | Pave striping-thermo-6 in Y | LF A A | 6,084 | $1.30 | $1.25 |
| 0640 | Pave marking-thermo stop bar-24IN | LF A A | 72 | $12.47 | $12.00 |
| 0650 | Pave marking-thermo curv arrow | EACH A A | 9 | $129.89 | $125.00 |
| 0660 | Pave marking-thermo comb arrow | EACH A A | 4 | $519.55 | $500.00 |
| 0670 | Pave marking-thermo merge arrow | EACH A A | 4 | $337.71 | $325.00 |
| 0680 | Inlaid pavement marker-MW | EACH A A | 67 | $41.56 | $40.00 |
| 0690 | Inlaid pavement marker-MY | EACH A A | 30 | $41.56 | $40.00 |
| 0700 | Inlaid pavement marker-by | EACH A A | 19 | $41.56 | $40.00 |
| 0710 | Fuel adjustment | DOLL A A | 308,730 | $1.00 | $1.00 |
| 0720 | Asphalt adjustment | DOLL A A | 62,256 | $1.00 | $1.00 |
| 0730 | Object marker TY 3 | EACH A A | 1 | $28.37 | $28.37 |
| 0740 | Law enforcement officer | HOUR A A | 1,000 | $0.01 | $105.00 |
| 0750 | Centerline rumble strips | LF A A | 9,157 | $0.25 | $0.25 |
| 0760 | Sawcut pavement | LF A A | 2,496 | $2.30 | $5.00 |
| 0770 | Pneumatic backstowing | TON A A | 500 | $200.00 | $300.00 |
| 0780 | Longitudinal edge key | LF A A | 2,496 | $15.10 | $15.10 |
| 0790 | Stamped concrete | SQYD A A | 382 | $147.01 | $147.01 |
| 0800 | Pave striping-chevron markings | SQFT A A | 167 | $7.27 | $7.00 |
| 0810 | Grout | CUYD A A | 247 | $395.00 | $600.00 |
| 0820 | Pave mark-thermo-yield | EACH A A | 20 | $46.76 | $45.00 |
| 0830 | Island curb and gutter(modified) | LF A A | 298 | $47.90 | $47.90 |
| 0840 | Vibrating wire piezometer | EACH A A | 4 | $2,600.00 | $7,000.00 |
| 0850 | Electronic delivery MGMT system - agg | LS A A | 1 | $2,500.00 | $3,500.00 |
| 0860 | Entrance pipe-15 in | LF A A | 212 | $67.09 | $55.00 |
| 0870 | Entrance pipe-18 in | LF A A | 40 | $73.77 | $65.00 |
| 0880 | Culvert pipe-18 in | LF A A | 352 | $118.91 | $80.00 |
| 0890 | Culvert pipe-24 in | LF A A | 379 | $152.61 | $150.00 |
| 0900 | Culvert pipe-30 in | LF A A | 272 | $199.76 | $225.00 |
| 0910 | Culvert pipe-36 in | LF A A | 862 | $242.78 | $280.00 |
| 0920 | Culvert pipe-42 in | LF A A | 86 | $208.04 | $200.00 |
| 0930 | Culvert pipe-48 in | LF A A | 360 | $517.02 | $525.00 |
| 0940 | Storm sewer pipe-18 in | LF A A | 54 | $228.02 | $55.00 |
| 0950 | Pipe culvert headwall-18 in | EACH A A | 6 | $1,375.00 | $1,500.00 |
| 0960 | Pipe culvert headwall-24 in | EACH A A | 3 | $1,500.00 | $2,000.00 |
| 0970 | Pipe culvert headwall-30 in | EACH A A | 2 | $2,400.00 | $2,500.00 |
| 0980 | Pipe culvert headwall-36 in | EACH A A | 6 | $2,600.00 | $3,000.00 |
| 0990 | Pipe culvert headwall-42 in | EACH A A | 2 | $3,100.00 | $3,500.00 |
| 1000 | Sloped box outlet type 1-18 in | EACH A A | 2 | $2,100.00 | $2,500.00 |
| 1010 | Sloped box outlet type 1-24 in | EACH A A | 2 | $2,850.00 | $3,000.00 |
| 1020 | Sloped and parallel headwall-18 in | EACH A A | 4 | $1,550.00 | $2,500.00 |
| 1030 | Curb box inlet type A | EACH A A | 2 | $7,600.00 | $6,000.00 |
| 1040 | Drop box inlet type 1 | EACH A A | 2 | $5,600.00 | $4,500.00 |
| 1050 | Pipeline inspection | LF A A | 2,557 | $2.35 | $2.35 |
| 1060 | Pole 100 FT MTG HT high mast | EACH A A | 2 | $75,950 | $75,950 |
| 1070 | Lighting control equipment | EACH A A | 1 | $25,007 | $25,007 |
| 1080 | Fused connector kit | EACH A A | 4 | $250.00 | $250.00 |
| 1090 | Trenching and backfilling | LF A A | 240 | $21.60 | $21.60 |
| 1100 | Wire-no. 12 | LF A A | 600 | $0.64 | $0.64 |
| 1110 | Electrical junction box type A | EACH A A | 4 | $3,500.00 | $3,500.00 |
| 1120 | Bore and jack conduit | LF A A | 280 | $30.86 | $30.86 |
| 1130 | Pole base-high mast | CUYD A A | 19 | $300.00 | $300.00 |
| 1140 | High mast LED luminaire | EACH A A | 8 | $2,500.00 | $2,500.00 |
| 1150 | Cable-no. 10/3C ducted | LF A A | 410 | $4.07 | $4.07 |
| 1160 | PVC conduit-3 in-schedule 80 | LF A A | 280 | $2.94 | $2.94 |
| 1170 | W encasement steel open cut range 3 | LF A A | 140 | $275.00 | $350.00 |
| 1180 | W flush hydrant assembly | EACH A A | 3 | $9,000.00 | $7,600.00 |
| 1190 | W pipe PVC 06 inch | LF A A | 1,325 | $30.00 | $140.00 |
| 1200 | W serv PE/PLST long side 2 in | EACH A A | 1 | $15,000 | $11,000 |
| 1210 | W service relocate | EACH A A | 3 | $1,000.00 | $1,800.00 |
| 1220 | W tie-in 06 inch | EACH A A | 4 | $4,000.00 | $4,500.00 |
| 1230 | W valve 06 inch | EACH A A | 2 | $2,500.00 | $2,100.00 |
| 1240 | W line marker | EACH A A | 9 | $100.00 | $100.00 |
| 1250 | Mobilization | LS A A | 1 | $483,000 | $750,000 |
| 1260 | Demobilization | LS A A | 1 | $212,905 | $256,554 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of January 29, 2026. Compiled by Mirage Metrics.