KYTC contract 26-1116 bid tabulation
GRADE & DRAIN WITH ASPHALT SURFACE KY 181. Let by Kentucky Transportation Cabinet on March 26, 2026. 2 bids received; low bid $8,084,455 by Scotty'S Contracting & Stone LLC, -19% against the engineer's estimate of $10,013,737.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 26 MAR 2026
- Pay items
- 133
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Scotty'S Contracting & Stone LLC | $8,084,455 | Low | -19% |
| 2 | Cleary Construction Inc | $9,862,000 | +22% | -2.0% |
Engineer's estimate: $10,013,737.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Scotty'S Contracting & Stone LLC | 2. Cleary Construction Inc |
|---|---|---|---|---|---|
| 0010 | Crushed stone base | TON A A | 14,226 | $32.46 | $44.00 |
| 0020 | Cement stabilized roadbed | SQYD A A | 5,609 | $15.44 | $15.00 |
| 0030 | Traffic bound base | TON A A | 100 | $40.13 | $52.00 |
| 0040 | Asphalt seal aggregate | TON A A | 30 | $139.72 | $195.00 |
| 0050 | Asphalt seal coat | TON A A | 4 | $852.55 | $2,300.00 |
| 0060 | Leveling & wedging PG64-22 | TON A A | 708 | $116.01 | $140.00 |
| 0070 | CL2 asph base 1.00D PG64-22 | TON A A | 8,259 | $95.32 | $122.00 |
| 0080 | CL2 asph surf 0.38D PG64-22 | TON A A | 3,783 | $111.28 | $150.00 |
| 0090 | Asphalt curing seal | TON A A | 8 | $652.84 | $900.00 |
| 0100 | Cem conc ent pavement-8 in | SQYD A A | 1,537 | $103.43 | $103.43 |
| 0110 | Cement | TON A A | 161 | $237.00 | $237.00 |
| 0120 | Sand for blotter | TON A A | 20 | $22.79 | $74.51 |
| 0130 | Joint adhesive | LF A A | 14,744 | $0.55 | $0.55 |
| 0140 | Asphalt material for tack non-tracking | TON A A | 18 | $550.38 | $883.38 |
| 0150 | Electronic delivery MGMT system - agg | LS A A | 1 | $0.01 | $0.01 |
| 0160 | Crushed aggregate size no 2 | TON A A | 1,862 | $61.19 | $45.00 |
| 0170 | Perforated pipe-4 in | LF A A | 266 | $3.16 | $29.00 |
| 0180 | Non-perforated pipe-4 in | LF A A | 178 | $6.35 | $30.00 |
| 0190 | Inspect & certify edge drain system | LS A A | 1 | $2,500.00 | $2,500.00 |
| 0200 | Perf pipe headwall TY 1-4 in | EACH A A | 3 | $771.00 | $1,250.00 |
| 0210 | Perf pipe headwall TY 3-4 in | EACH A A | 3 | $985.93 | $1,250.00 |
| 0220 | Remove pipe | LF A A | 2,426 | $3.36 | $25.00 |
| 0230 | Barricade-type III | EACH A A | 4 | $295.63 | $190.00 |
| 0240 | Temp ditch | LF A A | 6,499 | $0.01 | $1.00 |
| 0250 | Clean temp ditch | LF A A | 3,251 | $0.01 | $0.01 |
| 0260 | Roadway excavation | CUYD A A | 56,829 | $22.81 | $32.00 |
| 0270 | Water | MGAL A A | 1,118 | $0.01 | $0.01 |
| 0280 | Right-of-way monument type 1 | EACH A A | 98 | $241.88 | $169.81 |
| 0290 | Witness post | EACH A A | 49 | $164.48 | $153.26 |
| 0300 | Channel lining class II | TON A A | 150 | $46.06 | $62.00 |
| 0310 | Channel lining class III | TON A A | 218 | $47.63 | $68.00 |
| 0320 | Clearing and grubbing | LS A A | 1 | $73,871 | $82,000 |
| 0330 | Temporary signs | SQFT A A | 600 | $8.08 | $8.48 |
| 0340 | Edge key | LF A A | 377 | $42.17 | $21.65 |
| 0350 | Fabric-geotextile class 1 | SQYD A A | 13,693 | $2.02 | $2.50 |
| 0360 | Fabric-geotextile class 2 for pipe | SQYD A A | 1,229 | $2.00 | $2.00 |
| 0370 | Fabric-geotextile class 4A | SQYD A A | 19,560 | $2.88 | $4.00 |
| 0380 | Maintain & control traffic | LS A A | 1 | $316,052 | $335,000 |
| 0390 | Portable changeable message sign | EACH A A | 4 | $10,825 | $8,162.00 |
| 0400 | Edgeline rumble strips | LF A A | 34,864 | $0.23 | $0.13 |
| 0410 | Temp silt fence | LF A A | 6,499 | $1.41 | $2.50 |
| 0420 | Silt trap type A | EACH A A | 30 | $0.01 | $360.00 |
| 0430 | Silt trap type B | EACH A A | 30 | $278.43 | $200.00 |
| 0440 | Silt trap type C | EACH A A | 30 | $0.01 | $320.00 |
| 0450 | Clean silt trap type A | EACH A A | 30 | $0.01 | $0.01 |
| 0460 | Clean silt trap type B | EACH A A | 30 | $0.01 | $0.01 |
| 0470 | Clean silt trap type C | EACH A A | 30 | $0.01 | $0.01 |
| 0480 | Staking | LS A A | 1 | $71,971 | $165,000 |
| 0485 | Temp signal | LS A A | 1 | $21,167 | $45,000 |
| 0490 | Erosion control blanket | SQYD A A | 131,806 | $1.73 | $2.19 |
| 0500 | Temp mulch | SQYD A A | 86,685 | $0.28 | $0.41 |
| 0510 | Temp seeding and protection | SQYD A A | 65,015 | $0.35 | $0.42 |
| 0520 | Initial fertilizer | TON A A | 13.70 | $994.00 | $1,440.58 |
| 0530 | Maintenance fertilizer | TON A A | 7 | $994.00 | $1,440.58 |
| 0540 | Seeding and protection | SQYD A A | 68,122 | $0.56 | $0.75 |
| 0550 | Agricultural limestone | TON A A | 80.90 | $98.00 | $89.05 |
| 0560 | Pave striping-temp paint-4 in | LF A A | 46,822 | $0.30 | $0.30 |
| 0570 | Pave striping-perm paint-4 in | LF A A | 46,822 | $0.32 | $0.32 |
| 0580 | Pave marking-thermo stop bar-24IN | LF A A | 94 | $18.00 | $18.00 |
| 0590 | Pave marking-thermo curv arrow | EACH A A | 6 | $115.00 | $115.00 |
| 0600 | Fuel adjustment | DOLL A A | 34,655 | $1.00 | $1.00 |
| 0610 | Asphalt adjustment | DOLL A A | 46,974 | $1.00 | $1.00 |
| 0620 | Centerline rumble strips | LF A A | 11,736 | $0.24 | $0.24 |
| 0630 | Longitudinal edge key | LF A A | 18,205 | $2.51 | $3.54 |
| 0640 | Remove and relocate sign assembly | EACH A A | 41 | $152.82 | $585.19 |
| 0650 | Turf reinforcement mat 1 | SQYD A A | 12,297 | $5.68 | $11.00 |
| 0655 | Relocate temporary signals | LS A A | 1 | $7,418.58 | $10,000 |
| 0660 | Entrance pipe-18 in | LF A A | 642 | $79.63 | $85.00 |
| 0670 | Entrance pipe-24 in | LF A A | 176 | $101.54 | $135.00 |
| 0680 | Entrance pipe-30 in | LF A A | 392 | $127.94 | $150.00 |
| 0690 | Entrance pipe-18 in equiv | LF A A | 1,096 | $84.67 | $95.00 |
| 0700 | Culvert pipe-18 in | LF A A | 356 | $166.03 | $130.00 |
| 0710 | Culvert pipe-24 in | LF A A | 381 | $159.26 | $175.00 |
| 0720 | Culvert pipe-30 in | LF A A | 74 | $139.59 | $200.00 |
| 0730 | Culvert pipe-36 in | LF A A | 146 | $221.21 | $275.00 |
| 0740 | Culvert pipe-42 in | LF A A | 125 | $347.50 | $450.00 |
| 0750 | Culvert pipe-18 in equiv | LF A A | 69 | $200.92 | $100.00 |
| 0760 | Pipe culvert headwall-24 in | EACH A A | 1 | $2,500.00 | $3,000.00 |
| 0770 | Pipe culvert headwall-36 in | EACH A A | 2 | $4,200.00 | $3,250.00 |
| 0780 | Pipe culvert headwall-42 in | EACH A A | 4 | $4,500.00 | $3,500.00 |
| 0790 | Sloped box outlet type 1-18 in | EACH A A | 54 | $3,200.00 | $3,000.00 |
| 0800 | Drop box inlet type 1 | EACH A A | 1 | $6,200.00 | $7,500.00 |
| 0810 | Drop box inlet type 2 | EACH A A | 1 | $6,500.00 | $8,500.00 |
| 0820 | Drop box inlet type 11 | EACH A A | 1 | $4,500.00 | $3,500.00 |
| 0830 | Drop box inlet type 12 | LF A A | 10 | $850.00 | $700.00 |
| 0840 | Concrete-class A | CUYD A A | 44.08 | $1,000.00 | $1,528.67 |
| 0850 | Steel reinforcement | LB A A | 379 | $3.00 | $10.34 |
| 0860 | Pipe liner acceptance testing | LS A A | 1 | $3,500.00 | $3,500.00 |
| 0870 | Pipeline inspection | LF A A | 698 | $3.60 | $3.60 |
| 0880 | PVC fold and form pipe liner-18 in | LF A A | 89 | $140.15 | $140.15 |
| 0890 | PVC fold and form pipe liner-24 in | LF A A | 531 | $171.55 | $171.55 |
| 0900 | PVC fold and form pipe liner-30 in | LF A A | 129 | $210.25 | $210.25 |
| 0910 | PVC fold and form pipe liner-36 in | LF A A | 151 | $263.30 | $263.30 |
| 0920 | Sloped and mitered headwall-18 in | EACH A A | 46 | $2,800.00 | $2,600.00 |
| 0930 | Sloped and mitered headwall-24 in | EACH A A | 21 | $3,800.00 | $3,200.00 |
| 0940 | Sloped and mitered headwall-30 in | EACH A A | 14 | $4,000.00 | $3,500.00 |
| 0950 | Sloped and mitered headwall-36 in | EACH A A | 2 | $5,500.00 | $3,600.00 |
| 0960 | Structure excav-solid rock | CUYD A A | 13 | $350.00 | $875.00 |
| 0970 | Foundation preparation | LS A A | 1 | $17,000 | $19,000 |
| 0980 | Concrete-class A | CUYD A A | 88.80 | $1,400.00 | $1,500.00 |
| 0990 | Steel reinforcement | LB A A | 8,124 | $2.00 | $1.90 |
| 1000 | Structure excav-solid rock | CUYD A A | 13 | $350.00 | $875.00 |
| 1010 | Foundation preparation | LS A A | 1 | $17,000 | $18,000 |
| 1020 | Concrete-class A | CUYD A A | 91.20 | $1,300.00 | $1,500.00 |
| 1030 | Steel reinforcement | LB A A | 9,514 | $2.00 | $1.90 |
| 1040 | Trim & remove trees & brush | LF A A | 300 | $12.00 | $50.00 |
| 1050 | S force main directional bore | LF A A | 3,036 | $85.00 | $93.00 |
| 1060 | S line marker | EACH A A | 30 | $100.00 | $50.00 |
| 1070 | S cap existing main | EACH A A | 2 | $1,200.00 | $2,100.00 |
| 1080 | S force main air RLS/vac VLV 02 in inst | EACH A A | 4 | $15,000 | $10,000 |
| 1090 | S force main tie-in 06 inch inst | EACH A A | 2 | $2,000.00 | $3,000.00 |
| 1100 | Seeding and mulching | ACRE A A | 1 | $1,700.00 | $22,000 |
| 1110 | W air release valve 3/4 inch | EACH A A | 2 | $2,500.00 | $3,000.00 |
| 1120 | W cap existing main | EACH A A | 8 | $1,200.00 | $800.00 |
| 1130 | W directional bore | LF A A | 303 | $95.00 | $20.00 |
| 1140 | W encasement steel bored range 3 | LF A A | 212 | $500.00 | $300.00 |
| 1150 | W encasement steel open cut range 3 | LF A A | 40 | $200.00 | $100.00 |
| 1160 | W flush hydrant assembly | EACH A A | 3 | $8,500.00 | $9,500.00 |
| 1170 | W meter relocate | EACH A A | 69 | $1,200.00 | $800.00 |
| 1180 | W pipe PVC 03 inch | LF A A | 24 | $85.00 | $50.00 |
| 1190 | W pipe PVC 04 inch | LF A A | 11,086 | $53.00 | $65.40 |
| 1200 | W pipe PVC 06 inch | LF A A | 189 | $68.00 | $60.00 |
| 1210 | W serv PE/PLST long side 3/4 in | EACH A A | 32 | $3,900.00 | $2,000.00 |
| 1220 | W serv PE/PLST short side 3/4 in | EACH A A | 37 | $2,100.00 | $800.00 |
| 1230 | W tapping sleeve and valve size 1 | EACH A A | 8 | $5,500.00 | $4,500.00 |
| 1240 | W tie-in 03 inch | EACH A A | 2 | $1,900.00 | $1,000.00 |
| 1250 | W tie-in 04 inch | EACH A A | 3 | $2,000.00 | $1,200.00 |
| 1260 | W tie-in 06 inch | EACH A A | 3 | $2,200.00 | $1,500.00 |
| 1270 | W valve 04 inch | EACH A A | 3 | $2,000.00 | $1,800.00 |
| 1280 | W valve 06 inch | EACH A A | 1 | $2,300.00 | $2,200.00 |
| 1290 | W line marker | EACH A A | 10 | $85.00 | $50.00 |
| 1300 | Mobilization | LS A A | 1 | $223,396 | $459,000 |
| 1310 | Demobilization | LS A A | 1 | $115,025 | $138,382 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of March 26, 2026. Compiled by Mirage Metrics.