KYTC contract 26-1503 bid tabulation
ASPHALT SURFACE WITH GRADE & DRAIN NASHVILLE RD (US 31W). Let by Kentucky Transportation Cabinet on February 19, 2026. 2 bids received; low bid $10,547,844 by Scotty'S Contracting & Stone LLC, -7.8% against the engineer's estimate of $11,437,503.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 19 FEB 2026
- Pay items
- 208
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Scotty'S Contracting & Stone LLC | $10,547,844 | Low | -8.0% |
| 2 | Cleary Construction Inc | $11,715,000 | +11% | +2.0% |
Engineer's estimate: $11,437,503.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Scotty'S Contracting & Stone LLC | 2. Cleary Construction Inc |
|---|---|---|---|---|---|
| 0010 | Crushed stone base | TON A A | 7,680 | $37.80 | $38.00 |
| 0020 | Traffic bound base | TON A A | 16 | $48.45 | $70.00 |
| 0030 | Crushed aggregate size no 2 | TON A A | 10,250 | $36.60 | $33.00 |
| 0040 | Leveling & wedging PG64-22 | TON A A | 1,502 | $107.32 | $122.00 |
| 0050 | CL3 asph base 1.00D PG64-22 | TON A A | 8,556 | $88.91 | $106.00 |
| 0060 | Fabric-geotextile class 1 | SQYD A A | 14,855 | $4.36 | $2.75 |
| 0070 | Fabric-geotextile class 4A | SQYD A A | 14,855 | $3.74 | $4.00 |
| 0080 | CL3 asph surf 0.38A PG64-22 | TON A A | 2,992 | $126.29 | $138.00 |
| 0090 | Asphalt material for tack non-tracking | TON A A | 21 | $568.32 | $0.01 |
| 0100 | Electronic delivery MGMT system - agg | LS A A | 1 | $0.01 | $0.01 |
| 0110 | Crushed aggregate size no 2 | TON A A | 3,867 | $35.59 | $34.00 |
| 0120 | Perforated pipe-4 in | LF A A | 768 | $7.26 | $28.00 |
| 0130 | Non-perforated pipe-4 in | LF A A | 36 | $28.91 | $30.00 |
| 0140 | Perf pipe headwall TY 3-4 in | EACH A A | 3 | $416.28 | $1,000.00 |
| 0150 | Cored hole drainage box con-4 in | EACH A A | 57 | $200.00 | $1,000.00 |
| 0160 | Standard curb and gutter | LF A A | 7,276 | $27.05 | $27.05 |
| 0170 | Standard header curb | LF A A | 408 | $48.27 | $48.27 |
| 0180 | Lip header curb | LF A A | 153 | $53.30 | $53.30 |
| 0190 | Standard barrier median type 5 | SQYD A A | 924 | $153.38 | $153.38 |
| 0200 | Barricade-type III | EACH A A | 8 | $313.36 | $85.00 |
| 0210 | Remove pavement | SQYD A A | 470 | $12.26 | $25.00 |
| 0220 | Cem conc ent pavement-8 in | SQYD A A | 2,904 | $94.34 | $94.34 |
| 0230 | Temp ditch | LF A A | 2,640 | $0.01 | $1.00 |
| 0240 | Clean temp ditch | LF A A | 1,320 | $0.01 | $0.01 |
| 0250 | Roadway excavation | CUYD A A | 14,504 | $39.92 | $50.00 |
| 0260 | Granular embankment | CUYD A A | 81 | $78.07 | $60.00 |
| 0270 | Water | MGAL A A | 200 | $0.01 | $0.01 |
| 0280 | Right-of-way monument type 1 | EACH A A | 60 | $204.54 | $150.00 |
| 0290 | Right-of-way monument type 1A | EACH A A | 4 | $199.42 | $150.00 |
| 0300 | Witness post | EACH A A | 10 | $170.94 | $150.00 |
| 0310 | Clean sinkhole | EACH A A | 3 | $5,379.01 | $4,500.00 |
| 0320 | Channel lining class II | TON A A | 91 | $66.94 | $48.00 |
| 0330 | Channel lining class III | TON A A | 49 | $98.84 | $58.00 |
| 0340 | Clearing and grubbing | LS A A | 1 | $136,043 | $120,000 |
| 0350 | Temporary signs | SQFT A A | 814 | $9.22 | $8.50 |
| 0360 | Fabric-geotextile class 2 | SQYD A A | 2,964 | $2.24 | $2.50 |
| 0370 | Fabric-geotextile class 2 for pipe | SQYD A A | 11,637 | $2.00 | $2.00 |
| 0380 | Maintain & control traffic | LS A A | 1 | $262,253 | $220,000 |
| 0390 | Portable changeable message sign | EACH A A | 3 | $7,976.50 | $6,000.00 |
| 0400 | Mobilization for mill & text | LS A A | 1 | $3,845.00 | $3,500.00 |
| 0410 | Asphalt pave milling & texturing | TON A A | 645 | $67.39 | $27.00 |
| 0420 | Safeloading | CUYD A A | 26 | $500.00 | $550.00 |
| 0430 | Temp silt fence | LF A A | 2,640 | $3.33 | $2.50 |
| 0440 | Silt trap type A | EACH A A | 12 | $77.39 | $350.00 |
| 0450 | Silt trap type B | EACH A A | 12 | $77.39 | $165.00 |
| 0460 | Silt trap type C | EACH A A | 12 | $50.01 | $300.00 |
| 0470 | Clean silt trap type A | EACH A A | 12 | $0.01 | $0.01 |
| 0480 | Clean silt trap type B | EACH A A | 12 | $0.01 | $0.01 |
| 0490 | Clean silt trap type C | EACH A A | 12 | $0.01 | $0.01 |
| 0500 | Sidewalk-4 in concrete | SQYD A A | 5,454 | $54.85 | $54.85 |
| 0510 | Staking | LS A A | 1 | $152,806 | $135,000 |
| 0520 | Temp mulch | SQYD A A | 36,586 | $0.20 | $0.25 |
| 0530 | Temp seeding and protection | SQYD A A | 27,439 | $0.30 | $0.20 |
| 0540 | Initial fertilizer | TON A A | 1.40 | $1,500.00 | $800.00 |
| 0550 | Maintenance fertilizer | TON A A | 2.30 | $1,500.00 | $800.00 |
| 0560 | Seeding and protection | SQYD A A | 3,702 | $0.42 | $0.50 |
| 0570 | Sodding | SQYD A A | 38,940 | $8.00 | $6.00 |
| 0580 | Agricultural limestone | TON A A | 2 | $85.00 | $600.00 |
| 0590 | SBM alum sheet signs .080 in | SQFT A A | 71 | $44.00 | $40.00 |
| 0600 | SBM alum sheet signs .125 in | SQFT A A | 225 | $47.00 | $40.00 |
| 0610 | Steel post type 1 | LF A A | 488 | $28.00 | $35.00 |
| 0620 | Pave striping-temp paint-4 in | LF A A | 52,159 | $0.32 | $0.32 |
| 0630 | Pave striping-thermo-6 in W | LF A A | 13,502 | $1.35 | $1.35 |
| 0640 | Pave striping-thermo-6 in Y | LF A A | 11,384 | $1.35 | $1.35 |
| 0650 | Pave striping-thermo-12 in Y | LF A A | 50 | $7.00 | $7.00 |
| 0660 | Pave marking-thermo X-walk-6 in | LF A A | 1,228 | $4.00 | $4.00 |
| 0670 | Pave marking-thermo X-walk-12 in | LF A A | 1,145 | $7.00 | $7.00 |
| 0680 | Pave marking-thermo stop bar-24IN | LF A A | 323 | $15.00 | $15.00 |
| 0690 | Pave marking-thermo cross-hatch | SQFT A A | 2,965 | $6.00 | $6.00 |
| 0700 | Pave marking-thermo curv arrow | EACH A A | 35 | $150.00 | $150.00 |
| 0710 | Pave marking-thermo only | EACH A A | 1 | $500.00 | $500.00 |
| 0720 | Inlaid pavement marker-MW | EACH A A | 159 | $23.00 | $23.00 |
| 0730 | Inlaid pavement marker-MY | EACH A A | 22 | $23.00 | $23.00 |
| 0740 | Inlaid pavement marker-by | EACH A A | 166 | $23.00 | $23.00 |
| 0750 | Fuel adjustment | DOLL A A | 31,166 | $1.00 | $1.00 |
| 0760 | Asphalt adjustment | DOLL A A | 51,102 | $1.00 | $1.00 |
| 0770 | Tree | EACH A A | 12 | $375.00 | $500.00 |
| 0780 | Pave mark temp paint stop bar | LF A A | 323 | $1.50 | $1.50 |
| 0790 | Remove & reset traffic sign | EACH A A | 3 | $400.00 | $1,000.00 |
| 0800 | Pave mark-paint arrows | EACH A A | 33 | $65.00 | $65.00 |
| 0810 | Saw cut | LF A A | 271 | $4.25 | $2.00 |
| 0820 | Longitudinal edge key | LF A A | 9,930 | $3.16 | $3.00 |
| 0830 | Remove sign | EACH A A | 3 | $200.00 | $500.00 |
| 0840 | Striping removal | LF A A | 12,290 | $0.85 | $0.85 |
| 0850 | Detectable warnings | SQFT A A | 523 | $42.00 | $42.00 |
| 0860 | Barcode sign inventory | EACH A A | 42 | $30.00 | $25.00 |
| 0870 | Remove pavement marker | EACH A A | 308 | $11.06 | $4.00 |
| 0880 | Entrance pipe-15 in | LF A A | 206 | $82.15 | $95.00 |
| 0890 | Entrance pipe-18 in | LF A A | 247 | $90.37 | $110.00 |
| 0900 | Entrance pipe-24 in | LF A A | 131 | $102.37 | $115.00 |
| 0910 | Culvert pipe-18 in | LF A A | 59 | $252.31 | $150.00 |
| 0920 | Culvert pipe-24 in | LF A A | 50 | $280.72 | $175.00 |
| 0930 | Storm sewer pipe-15 in | LF A A | 5,404 | $138.91 | $100.00 |
| 0940 | Storm sewer pipe-18 in | LF A A | 436 | $136.55 | $125.00 |
| 0950 | Storm sewer pipe-24 in | LF A A | 797 | $195.58 | $155.00 |
| 0960 | Storm sewer pipe-36 in | LF A A | 46 | $216.76 | $195.00 |
| 0970 | Pipe culvert headwall-15 in | EACH A A | 1 | $1,400.00 | $3,500.00 |
| 0980 | Pipe culvert headwall-18 in | EACH A A | 5 | $1,800.00 | $3,750.00 |
| 0990 | Pipe culvert headwall-24 in | EACH A A | 6 | $2,000.00 | $4,000.00 |
| 1000 | Pipe culvert headwall-36 in | EACH A A | 1 | $2,900.00 | $4,250.00 |
| 1010 | Sloped box outlet type 1-15 in | EACH A A | 1 | $2,500.00 | $3,500.00 |
| 1020 | Curb box inlet type A | EACH A A | 48 | $7,500.00 | $9,000.00 |
| 1030 | Drop box inlet type 3 | EACH A A | 3 | $5,400.00 | $10,000 |
| 1040 | Drop box inlet type 13G | EACH A A | 5 | $4,800.00 | $5,250.00 |
| 1050 | Drop box inlet type 13S | EACH A A | 1 | $8,000.00 | $8,000.00 |
| 1060 | Drop box inlet type 14 | EACH A A | 2 | $4,200.00 | $9,500.00 |
| 1070 | Drop box inlet type 16G | EACH A A | 2 | $4,800.00 | $5,500.00 |
| 1080 | Manhole type A | EACH A A | 1 | $3,200.00 | $5,000.00 |
| 1090 | Manhole type C | EACH A A | 1 | $10,500 | $12,000 |
| 1100 | Frame and lid TY 1 | EACH A A | 1 | $2,000.00 | $1,750.00 |
| 1110 | Concrete-class A | CUYD A A | 4.31 | $2,000.00 | $2,000.00 |
| 1120 | Bore and jack pipe-24 in | LF A A | 102 | $783.58 | $900.00 |
| 1130 | Bore and jack pipe-18 in | LF A A | 47 | $649.21 | $780.00 |
| 1140 | Pipeline inspection | LF A A | 3,692 | $2.35 | $2.35 |
| 1150 | Safeloading | CUYD A A | 34.60 | $242.00 | $305.00 |
| 1160 | S cap existing main | EACH A A | 2 | $2,904.00 | $3,105.00 |
| 1170 | S cap existing main | EACH A A | 2 | $3,200.00 | $3,500.00 |
| 1180 | S cap existing main | EACH A A | 1 | $4,500.00 | $3,700.00 |
| 1190 | S cap existing main | EACH A A | 1 | $2,766.00 | $970.00 |
| 1200 | S cap existing main | EACH A A | 2 | $2,800.00 | $1,010.00 |
| 1210 | S cap existing main | EACH A A | 2 | $2,820.00 | $1,800.00 |
| 1220 | W cap existing main | EACH A A | 3 | $3,600.00 | $3,135.00 |
| 1230 | S encasement steel open cut range 3 | LF A A | 25 | $395.00 | $360.00 |
| 1240 | W tapping sleeve and valve size 1 | EACH A A | 4 | $2,200.00 | $855.00 |
| 1250 | S encasement steel bored range 3 | LF A A | 67 | $500.00 | $685.00 |
| 1260 | S encasement steel bored range 4 | LF A A | 55 | $665.00 | $933.00 |
| 1270 | S encasement steel bored range 5 | LF A A | 260 | $822.00 | $972.00 |
| 1280 | S force main PVC 06 inch | LF A A | 132 | $100.00 | $151.00 |
| 1290 | S force main PVC 12 inch | LF A A | 426 | $118.00 | $203.00 |
| 1300 | S force main tie-in 06 inch | EACH A A | 1 | $4,510.00 | $4,950.00 |
| 1310 | S force main tie-in 12 inch | EACH A A | 1 | $7,040.00 | $7,500.00 |
| 1330 | S lateral short side 04 inch | EACH A A | 6 | $2,570.00 | $1,275.00 |
| 1340 | S manhole | EACH A A | 21 | $6,200.00 | $9,200.00 |
| 1350 | S manhole abandon/remove | EACH A A | 14 | $3,300.00 | $3,480.00 |
| 1360 | S manhole adjust to grade | EACH A A | 2 | $1,765.00 | $1,200.00 |
| 1370 | S manhole tap existing | EACH A A | 3 | $4,000.00 | $1,680.00 |
| 1380 | S pipe PVC 08 inch | LF A A | 239 | $180.00 | $196.00 |
| 1390 | S pipe PVC 10 inch | LF A A | 62 | $187.00 | $163.00 |
| 1400 | S pipe PVC 12 inch | LF A A | 283 | $204.00 | $241.00 |
| 1410 | S pipe PVC 24 inch | LF A A | 952 | $235.00 | $292.00 |
| 1420 | S pipe special | LF A A | 542 | $212.00 | $272.00 |
| 1430 | Fused connector kit | EACH A A | 18 | $386.96 | $132.00 |
| 1440 | Trenching and backfilling | LF A A | 295 | $13.23 | $19.00 |
| 1450 | Cable-no. 14/7C | LF A A | 3,067 | $3.97 | $7.65 |
| 1460 | Messenger-10800 LB | LF A A | 200 | $15.24 | $9.57 |
| 1470 | Messenger-15400 LB | LF A A | 970 | $15.24 | $9.58 |
| 1480 | Install steel strain pole | EACH A A | 12 | $3,584.28 | $5,112.00 |
| 1490 | Temp relocation of signal head | EACH A A | 34 | $1,759.07 | $418.00 |
| 1500 | Install span mounted sign | EACH A A | 3 | $432.00 | $418.00 |
| 1510 | Install pedestrian head-LED | EACH A A | 8 | $624.05 | $431.00 |
| 1520 | Install LED signal-3 section | EACH A A | 11 | $736.71 | $466.00 |
| 1530 | Install LED signal- 4 section | EACH A A | 7 | $787.12 | $463.00 |
| 1540 | Install ped detector-audible | EACH A A | 8 | $624.05 | $380.00 |
| 1550 | Remove & reinstall coordinating unit | EACH A A | 2 | $3,481.03 | $3,727.00 |
| 1560 | Traffic signal pole base | CUYD A A | 45 | $1,232.32 | $3,319.00 |
| 1570 | Install signal pedestal | EACH A A | 6 | $4,948.96 | $3,578.00 |
| 1580 | Tether wire | LF A A | 1,170 | $15.24 | $6.78 |
| 1590 | PVC conduit-1 1/4 in-schedule 80 | LF A A | 135 | $9.62 | $7.33 |
| 1600 | PVC conduit-2 in-schedule 80 | LF A A | 160 | $13.11 | $13.38 |
| 1610 | Install signal controller-TY atc | EACH A A | 2 | $25,361 | $13,460 |
| 1620 | Remove signal equipment | EACH A A | 4 | $7,045.21 | $8,253.00 |
| 1630 | Install radar presence detector type A | EACH A A | 6 | $2,226.92 | $1,525.00 |
| 1640 | Install solar school flasher assembly | EACH A A | 2 | $22,875 | $4,100.00 |
| 1650 | W cap existing main | EACH A A | 22 | $3,200.00 | $3,250.00 |
| 1660 | Safeloading | CUYD A A | 66 | $242.00 | $364.00 |
| 1670 | Surf restoration | SQYD A A | 418 | $71.05 | $150.00 |
| 1680 | W encasement steel open cut range 3 | LF A A | 20 | $402.00 | $370.00 |
| 1690 | W encasement steel bored range 4 | LF A A | 72 | $605.00 | $907.00 |
| 1700 | W encasement steel open cut range 4 | LF A A | 28 | $450.00 | $459.00 |
| 1710 | W encasement steel bored range 6 | LF A A | 80 | $1,001.00 | $1,300.00 |
| 1720 | W encasement steel open cut range 6 | LF A A | 30 | $609.00 | $655.00 |
| 1730 | W encasement steel open cut range 5 | LF A A | 40 | $482.00 | $410.00 |
| 1740 | W encasement steel open cut range 5 | LF A A | 235 | $542.00 | $623.00 |
| 1750 | W fire hydrant assembly | EACH A A | 6 | $8,944.00 | $10,850 |
| 1760 | W fire hydrant remove | EACH A A | 9 | $2,007.00 | $1,800.00 |
| 1770 | W meter relocate | EACH A A | 27 | $1,210.00 | $812.00 |
| 1780 | W pipe polyethylene/plastic 1 inch | LF A A | 51 | $28.00 | $90.00 |
| 1790 | W pipe PVC 02 inch | LF A A | 14 | $84.00 | $221.00 |
| 1800 | W pipe ductile iron 06 inch | LF A A | 14 | $175.00 | $232.00 |
| 1810 | W pipe ductile iron 08 inch | LF A A | 290 | $130.00 | $225.00 |
| 1820 | W pipe ductile iron 12 inch | LF A A | 4,371 | $154.00 | $228.00 |
| 1830 | W pipe ductile iron 12 inch | LF A A | 416 | $155.00 | $244.00 |
| 1840 | W pipe ductile iron 16 inch | LF A A | 324 | $243.00 | $388.00 |
| 1850 | W serv PE/PLST long side 3/4 in | EACH A A | 7 | $2,434.00 | $12,150 |
| 1860 | W serv PE/PLST short side 3/4 in | EACH A A | 21 | $1,647.00 | $902.00 |
| 1870 | W valve box remove | EACH A A | 2 | $275.00 | $875.00 |
| 1880 | W tapping sleeve and valve size 1 | EACH A A | 1 | $2,200.00 | $2,300.00 |
| 1890 | W tapping sleeve and valve size 1 | EACH A A | 2 | $2,200.00 | $4,210.00 |
| 1900 | W tapping sleeve and valve size 1 | EACH A A | 2 | $2,200.00 | $2,935.00 |
| 1910 | W tapping sleeve and valve size 2 | EACH A A | 5 | $12,767 | $13,050 |
| 1920 | W tapping sleeve and valve size 2 | EACH A A | 1 | $46,000 | $33,800 |
| 1930 | W tapping sleeve and valve size 1 | EACH A A | 1 | $6,985.00 | $3,530.00 |
| 1940 | W valve 12 inch | EACH A A | 17 | $5,798.00 | $6,100.00 |
| 1950 | W valve 16 inch | EACH A A | 5 | $21,500 | $28,000 |
| 1960 | W valve 06 inch | EACH A A | 1 | $2,850.00 | $2,800.00 |
| 1970 | W valve 08 inch | EACH A A | 1 | $3,575.00 | $3,900.00 |
| 1971 | Conduit-1 1/4 in | LF A A | 40 | $25.92 | $22.00 |
| 1972 | Conduit-2 in | LF A A | 15 | $35.61 | $29.68 |
| 1973 | Trenching and backfilling | LF A A | 50 | $20.80 | $9.41 |
| 1974 | Piezoelectric sensor | EACH A A | 4 | $3,830.29 | $3,037.00 |
| 1975 | Loop wire | LF A A | 2,100 | $1.54 | $1.57 |
| 1976 | Loop saw slot and fill | LF A A | 400 | $50.35 | $12.38 |
| 1977 | Remove and replace sidewalk | SQYD A A | 2 | $500.00 | $500.00 |
| 1978 | Wood post | EACH A A | 2 | $863.10 | $619.00 |
| 1979 | Electrical junction box type A | EACH A A | 1 | $2,269.90 | $2,055.00 |
| 1980 | Mobilization | LS A A | 1 | $270,750 | $537,000 |
| 1981 | Galvanized steel cabinet | EACH A A | 1 | $1,314.64 | $1,599.00 |
| 1990 | Demobilization | LS A A | 1 | $150,930 | $165,580 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of February 19, 2026. Compiled by Mirage Metrics.