KYTC contract 26-1515 bid tabulation
GRADE & DRAIN WITH ASPHALT SURFACE STARFIRE HAUL ROAD (CR 1390). Let by Kentucky Transportation Cabinet on August 20, 2026. 4 bids received; low bid $15,232,039 by Bizzack Construction LLC, -30% against the engineer's estimate of $21,713,424.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 20 AUG 2026
- Pay items
- 117
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Bizzack Construction LLC | $15,232,039 | Low | -30% |
| 2 | Frederick & May Construction Co | $15,590,980 | +2.0% | -28% |
| 3 | Standafer Builders Inc | $17,061,815 | +12% | -21% |
| 4 | Triton Construction Inc | $23,325,000 | +53% | +7.0% |
Engineer's estimate: $21,713,424.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Bizzack Construction LLC | 2. Frederick & May Construction Co | 3. Standafer Builders Inc | 4. Triton Construction Inc |
|---|---|---|---|---|---|---|---|
| 0010 | Crushed stone base | TON A A | 19,286 | $53.14 | $53.10 | $53.10 | $54.00 |
| 0020 | Geogrid reinforcement for subgrade | SQYD A A | 1,277 | $3.97 | $6.70 | $3.00 | $9.00 |
| 0030 | Traffic bound base | TON A A | 800 | $47.04 | $47.00 | $47.00 | $90.00 |
| 0040 | Asphalt seal aggregate | TON A A | 147 | $146.50 | $146.50 | $146.50 | $146.50 |
| 0050 | Asphalt seal coat | TON A A | 19 | $1,150.00 | $1,150.00 | $1,150.00 | $1,150.00 |
| 0060 | Leveling & wedging PG64-22 | TON A A | 36 | $174.85 | $174.85 | $174.85 | $174.85 |
| 0070 | CL2 asph base 1.00D PG64-22 | TON A A | 24,026 | $139.80 | $139.80 | $139.80 | $139.80 |
| 0080 | CL2 asph surf 0.38D PG64-22 | TON A A | 3,886 | $174.85 | $174.85 | $174.85 | $174.85 |
| 0090 | Asphalt material for tack | TON A A | 59 | $825.00 | $825.00 | $825.00 | $825.00 |
| 0100 | JPC pavement-11 in | SQYD A A | 737 | $162.74 | $162.74 | $162.74 | $182.00 |
| 0110 | JPC pavement-8 in | SQYD A A | 540 | $137.18 | $137.18 | $137.18 | $147.00 |
| 0120 | Crushed aggregate size no 2 | TON A A | 2,303 | $49.14 | $47.50 | $50.00 | $85.00 |
| 0130 | Perforated pipe-4 in | LF A A | 14,859 | $9.15 | $14.86 | $12.00 | $8.00 |
| 0140 | Non-perforated pipe-4 in | LF A A | 28 | $35.00 | $30.00 | $25.00 | $8.00 |
| 0150 | Perf pipe headwall TY 1-4 in | EACH A A | 2 | $1,000.00 | $1,200.00 | $1,500.00 | $1,100.00 |
| 0160 | Perf pipe headwall TY 3-4 in | EACH A A | 1 | $1,100.00 | $1,200.00 | $1,500.00 | $1,375.00 |
| 0170 | Cored hole drainage box con-4 in | EACH A A | 138 | $0.01 | $20.00 | $75.00 | $600.00 |
| 0180 | Delineator for G/R BI directional white | EACH A A | 53 | $11.66 | $13.00 | $13.00 | $13.00 |
| 0190 | Barricade-type III | EACH A A | 3 | $220.00 | $100.00 | $200.00 | $500.00 |
| 0200 | Temp ditch | LF A A | 7,600 | $0.01 | $0.10 | $5.00 | $3.00 |
| 0210 | Clean temp ditch | LF A A | 3,800 | $0.01 | $0.01 | $1.00 | $2.00 |
| 0220 | Roadway excavation | CUYD A A | 574,132 | $5.25 | $5.50 | $6.82 | $12.00 |
| 0240 | Water | MGAL A A | 165 | $0.01 | $1.00 | $10.00 | $70.00 |
| 0250 | Fence-4 FT chain link | LF A A | 1,014 | $26.76 | $66.46 | $66.46 | $66.46 |
| 0260 | Single vehicular chain link gate | EACH A A | 1 | $4,820.30 | $5,348.00 | $5,348.00 | $5,348.00 |
| 0270 | G/R-W beam-S face TL-3 | LF A A | 3,000 | $30.39 | $29.00 | $29.00 | $29.00 |
| 0280 | G/R terminal section no 1 | EACH A A | 4 | $76.13 | $85.00 | $85.00 | $85.00 |
| 0290 | G/R end treatment type 1 | EACH A A | 8 | $3,357.40 | $3,500.00 | $3,500.00 | $3,500.00 |
| 0300 | Channel lining class II | TON A A | 1,820 | $50.31 | $50.50 | $53.00 | $45.00 |
| 0310 | Channel lining class III | TON A A | 10,133 | $50.31 | $50.50 | $53.00 | $45.00 |
| 0320 | Clearing and grubbing | LS A A | 1 | $168,000 | $100,000 | $354,960 | $721,794 |
| 0330 | Concrete-class B | CUYD A A | 10.73 | $932.56 | $385.00 | $385.00 | $385.00 |
| 0340 | Temporary signs | SQFT A A | 500 | $12.72 | $13.00 | $12.00 | $12.00 |
| 0350 | Edge key | LF A A | 44 | $75.80 | $75.80 | $75.80 | $75.80 |
| 0360 | Hook bolt with expan anchor | EACH A A | 95 | $12.95 | $12.95 | $12.95 | $10.00 |
| 0370 | Fabric-geotextile class 1 | SQYD A A | 15,875 | $2.83 | $2.25 | $2.00 | $4.00 |
| 0380 | Fabric-geotextile class 1A | SQYD A A | 2,700 | $3.82 | $4.00 | $3.20 | $6.00 |
| 0390 | Maintain & control traffic | LS A A | 1 | $13,000 | $25,000 | $125,000 | $252,000 |
| 0400 | Temp silt fence | LF A A | 7,600 | $2.84 | $2.25 | $2.65 | $5.00 |
| 0410 | Silt trap type A | EACH A A | 116 | $50.00 | $25.00 | $100.00 | $350.00 |
| 0420 | Silt trap type B | EACH A A | 116 | $102.00 | $25.00 | $100.00 | $140.00 |
| 0430 | Silt trap type C | EACH A A | 116 | $150.00 | $25.00 | $100.00 | $200.00 |
| 0440 | Clean silt trap type A | EACH A A | 116 | $0.01 | $10.00 | $10.00 | $296.00 |
| 0450 | Clean silt trap type B | EACH A A | 116 | $0.01 | $10.00 | $10.00 | $105.00 |
| 0455 | Remove structure | LS A A | 1 | $20,000 | $25,000 | $63,000 | $100,000 |
| 0460 | Clean silt trap type C | EACH A A | 116 | $0.01 | $10.00 | $10.00 | $150.00 |
| 0470 | Sidewalk-4 in concrete | SQYD A A | 7,412 | $64.48 | $64.48 | $64.48 | $100.00 |
| 0480 | Staking | LS A A | 1 | $65,500 | $75,000 | $150,000 | $150,000 |
| 0490 | Arrow panel | EACH A A | 1 | $1,700.00 | $1,010.00 | $600.00 | $3,000.00 |
| 0500 | PVC pipe-6 in | LF A A | 1,020 | $26.29 | $30.00 | $26.00 | $62.00 |
| 0510 | Erosion control blanket | SQYD A A | 150,949 | $2.15 | $2.15 | $2.15 | $2.15 |
| 0520 | Temp mulch | SQYD A A | 371,300 | $0.29 | $0.29 | $0.29 | $0.29 |
| 0530 | Temp seeding and protection | SQYD A A | 278,500 | $0.32 | $0.32 | $0.32 | $0.32 |
| 0540 | Initial fertilizer | TON A A | 29 | $1,600.00 | $1,600.00 | $1,600.00 | $1,600.00 |
| 0550 | Maintenance fertilizer | TON A A | 19 | $1,600.00 | $1,600.00 | $1,600.00 | $1,600.00 |
| 0560 | Seeding and protection | SQYD A A | 556,900 | $0.58 | $0.58 | $0.58 | $0.58 |
| 0570 | Agricultural limestone | TON A A | 346 | $125.00 | $125.00 | $125.00 | $125.00 |
| 0580 | SBM alum sheet signs .080 in | SQFT A A | 48 | $40.70 | $40.70 | $40.70 | $40.70 |
| 0590 | SBM alum sheet signs .125 in | SQFT A A | 11 | $40.70 | $40.70 | $40.70 | $40.70 |
| 0600 | Steel post type 1 | LF A A | 132 | $24.44 | $24.44 | $24.44 | $24.44 |
| 0610 | Pave striping-perm paint-4 in | LF A A | 14,989 | $0.20 | $0.20 | $0.20 | $0.20 |
| 0620 | Pave striping-dur TY 1-4 in Y | LF A A | 164 | $8.00 | $8.00 | $8.00 | $8.00 |
| 0630 | Pave striping-dur TY 1-6 in W | LF A A | 870 | $9.00 | $9.00 | $9.00 | $9.00 |
| 0640 | Pave marking-thermo stop bar-12IN | LF A A | 39 | $8.00 | $8.00 | $8.00 | $8.00 |
| 0650 | Pave marking-thermo curv arrow | EACH A A | 4 | $115.00 | $115.00 | $115.00 | $115.00 |
| 0660 | Fuel adjustment | DOLL A A | 113,572 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0670 | Asphalt adjustment | DOLL A A | 113,044 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0680 | Object marker TY 3 | EACH A A | 8 | $85.00 | $85.00 | $85.00 | $85.00 |
| 0690 | Saw cut | LF A A | 495 | $5.05 | $4.00 | $6.00 | $7.00 |
| 0700 | Detectable warnings | SQFT A A | 138 | $45.56 | $45.56 | $45.56 | $55.00 |
| 0710 | Roll curb modified | LF A A | 14,807 | $21.94 | $21.94 | $21.94 | $55.00 |
| 0720 | R/W monument type 3 | EACH A A | 69 | $120.00 | $220.00 | $377.00 | $300.00 |
| 0730 | Barcode sign inventory | EACH A A | 9 | $30.00 | $30.00 | $30.00 | $30.00 |
| 0740 | Impermeable detention basin lining | SQYD A A | 4,152 | $35.49 | $17.53 | $17.22 | $35.00 |
| 0750 | Utility coordination | LS A A | 1 | $0.01 | $500.00 | $25,000 | $5,000.00 |
| 0760 | PGR grout | CUYD A A | 350.10 | $470.00 | $500.00 | $500.00 | $500.00 |
| 0780 | Entrance pipe-15 in | LF A A | 101 | $80.07 | $60.00 | $50.00 | $120.00 |
| 0790 | Entrance pipe-18 in | LF A A | 43 | $86.87 | $70.00 | $58.00 | $120.00 |
| 0800 | Entrance pipe-24 in | LF A A | 78 | $107.47 | $100.00 | $60.00 | $140.00 |
| 0810 | Culvert pipe-18 in | LF A A | 319 | $123.99 | $80.00 | $75.00 | $200.00 |
| 0820 | Culvert pipe-24 in | LF A A | 144 | $115.89 | $122.00 | $100.00 | $210.00 |
| 0830 | Culvert pipe-30 in | LF A A | 93 | $149.35 | $124.00 | $150.00 | $210.00 |
| 0840 | Culvert pipe-36 in | LF A A | 90 | $200.71 | $152.00 | $200.00 | $230.00 |
| 0850 | Culvert pipe-42 in | LF A A | 106 | $279.54 | $186.00 | $235.00 | $230.00 |
| 0860 | Storm sewer pipe-18 in | LF A A | 4,366 | $94.61 | $80.00 | $90.00 | $124.00 |
| 0870 | Storm sewer pipe-24 in | LF A A | 1,775 | $129.95 | $101.00 | $105.00 | $210.00 |
| 0880 | Storm sewer pipe-30 in | LF A A | 1,094 | $143.63 | $129.00 | $150.00 | $240.00 |
| 0890 | Storm sewer pipe-36 in | LF A A | 973 | $181.03 | $162.00 | $325.00 | $300.00 |
| 0900 | Pipe culvert headwall-18 in | EACH A A | 2 | $1,600.00 | $1,570.00 | $1,150.00 | $2,500.00 |
| 0910 | Pipe culvert headwall-24 in | EACH A A | 3 | $2,000.00 | $1,700.00 | $1,300.00 | $3,000.00 |
| 0920 | Pipe culvert headwall-30 in | EACH A A | 4 | $3,400.00 | $2,650.00 | $1,800.00 | $3,500.00 |
| 0930 | Pipe culvert headwall-36 in | EACH A A | 3 | $3,500.00 | $2,650.00 | $2,100.00 | $4,500.00 |
| 0940 | Pipe culvert headwall-42 in | EACH A A | 4 | $4,700.00 | $3,330.00 | $2,400.00 | $5,500.00 |
| 0950 | Sloped box outlet type 1-18 in | EACH A A | 2 | $2,700.00 | $1,850.00 | $2,600.00 | $3,500.00 |
| 0960 | Curb box inlet type B | EACH A A | 24 | $7,000.00 | $6,000.00 | $6,650.00 | $6,480.00 |
| 0970 | Drop box inlet type 6F | EACH A A | 1 | $4,500.00 | $5,500.00 | $9,500.00 | $10,000 |
| 0980 | Junction box-48 in | EACH A A | 1 | $3,600.00 | $3,000.00 | $6,100.00 | $8,000.00 |
| 0990 | Manhole type B | EACH A A | 1 | $6,500.00 | $6,000.00 | $5,000.00 | $9,000.00 |
| 1000 | Fabric-geotextile class 2 for pipe | SQYD A A | 16,346 | $2.00 | $2.00 | $2.00 | $2.00 |
| 1010 | Pipeline inspection | LF A A | 974 | $2.57 | $2.57 | $2.57 | $4.00 |
| 1020 | Curb box inlet type F modified | EACH A A | 96 | $3,570.00 | $3,500.00 | $5,250.00 | $5,800.00 |
| 1030 | Structure granular backfill | CUYD A A | 500 | $85.00 | $82.70 | $115.00 | $150.00 |
| 1040 | Armored edge for concrete | LF A A | 64 | $85.00 | $150.00 | $50.00 | $120.00 |
| 1050 | Foundation preparation | LS A A | 1 | $25,000 | $25,000 | $32,000 | $150,000 |
| 1060 | Cyclopean stone rip rap | TON A A | 297 | $60.00 | $54.50 | $65.00 | $120.00 |
| 1070 | Test piles | LF A A | 48 | $250.00 | $265.00 | $255.00 | $230.00 |
| 1080 | Pre-drilling for piles | LF A A | 246 | $150.00 | $462.00 | $800.00 | $200.00 |
| 1090 | Piles-steel HP14X117 | LF A A | 348 | $175.00 | $255.00 | $255.00 | $320.00 |
| 1100 | Concrete-class A | CUYD A A | 118.60 | $1,000.00 | $1,400.00 | $875.00 | $1,600.00 |
| 1110 | Concrete-class AA | CUYD A A | 61.70 | $1,750.00 | $1,500.00 | $1,200.00 | $2,000.00 |
| 1120 | Steel reinforcement-epoxy coated | LB A A | 18,073 | $1.75 | $2.25 | $2.15 | $2.50 |
| 1130 | Precast PC box beam CB27-48 | LF A A | 656 | $450.00 | $435.00 | $350.00 | $560.00 |
| 1140 | Concrete sealing | SQFT A A | 4,148 | $2.00 | $2.00 | $3.50 | $3.00 |
| 1150 | Rail system side mounted MGS | LF A A | 150 | $196.64 | $225.00 | $180.00 | $225.00 |
| 1160 | Mobilization for concrete surf treatment | LS A A | 1 | $500.00 | $1,000.00 | $2,500.00 | $1,000.00 |
| 1170 | Mobilization | LS A A | 1 | $300,000 | $597,594 | $350,000 | $1,000,000 |
| 1180 | Demobilization | LS A A | 1 | $218,000 | $230,410 | $250,000 | $385,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of August 20, 2026. Compiled by Mirage Metrics.