KYTC contract 26-2034 bid tabulation
ASPHALT RESURFACING HARDINSBURG TO FORDSVILLE ROAD (KY 261). Let by Kentucky Transportation Cabinet on March 26, 2026. 4 bids received; low bid $621,865 by C & R Construction and Consulting LLC, -27% against the engineer's estimate of $848,780.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 26 MAR 2026
- Pay items
- 14
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | C & R Construction and Consulting LLC | $621,865 | Low | -27% |
| 2 | Mago Construction Company LLC | $640,968 | +3.0% | -24% |
| 3 | E & B Paving LLC | $686,193 | +10% | -19% |
| 4 | Louisville Paving Company Inc | $706,130 | +14% | -17% |
Engineer's estimate: $848,780.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. C & R Construction and Consulting LLC | 2. Mago Construction Company LLC | 3. E & B Paving LLC | 4. Louisville Paving Company Inc |
|---|---|---|---|---|---|---|---|
| 0010 | Leveling & wedging PG64-22 | TON A A | 917 | $78.70 | $82.00 | $80.00 | $91.00 |
| 0020 | CL2 asph surf 0.38D PG64-22 | TON A A | 5,100 | $78.70 | $82.00 | $80.00 | $91.00 |
| 0030 | Asphalt material for tack | TON A A | 48 | $1.00 | $0.01 | $1.00 | $0.01 |
| 0040 | Temporary signs | SQFT A A | 490 | $7.00 | $5.00 | $7.42 | $4.00 |
| 0050 | Maintain & control traffic | LS A A | 1 | $12,730 | $9,775.00 | $47,587 | $31,340 |
| 0060 | Mobilization for mill & text | LS A A | 1 | $3,000.00 | $5,000.00 | $15,000 | $2,500.00 |
| 0070 | Asphalt pave milling & texturing | TON A A | 110 | $10.00 | $12.50 | $40.00 | $111.45 |
| 0080 | Edgeline rumble strips | LF A A | 69,780 | $0.14 | $0.24 | $0.24 | $0.14 |
| 0090 | Base failure repair | SQYD A A | 845 | $48.00 | $50.00 | $55.00 | $34.50 |
| 0100 | Pave striping-temp paint-4 in | LF A A | 35,000 | $0.23 | $0.01 | $0.01 | $0.01 |
| 0110 | Pave striping-perm paint-6 in | LF A A | 111,000 | $0.25 | $0.25 | $0.25 | $0.25 |
| 0120 | Fuel adjustment | DOLL A A | 9,366 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0130 | Asphalt adjustment | DOLL A A | 23,524 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0140 | Demobilization | LS A A | 1 | $9,000.00 | $8,986.38 | $9,950.00 | $10,611 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of March 26, 2026. Compiled by Mirage Metrics.