KYTC contract 26-2065 bid tabulation

ASPHALT RESURFACING GARRETT ROAD (KY 1238). Let by Kentucky Transportation Cabinet on March 26, 2026. 5 bids received; low bid $102,758 by E & B Paving LLC, -44% against the engineer's estimate of $184,308.

Owner
Kentucky Transportation Cabinet
Letting
26 MAR 2026
Pay items
12
Data through
22 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1E & B Paving LLC$102,758Low-44%
2Scotty'S Contracting & Stone LLC$106,089+3.0%-42%
3Mago Construction Company LLC$106,101+3.0%-42%
4C & R Construction and Consulting LLC$107,053+4.0%-42%
5Louisville Paving Company Inc$126,100+23%-32%
KYTC contract 26-2065: bids by rank

Engineer's estimate: $184,308.

Bid tabulation

LinePay itemUnitQuantity1. E & B Paving LLC2. Scotty'S Contracting & Stone LLC3. Mago Construction Company LLC4. C & R Construction and Consulting LLC5. Louisville Paving Company Inc
0010Leveling & wedging PG64-22TON A A148$73.00$83.80$82.50$81.00$83.00
0020CL2 asph surf 0.38D PG64-22TON A A960$73.00$75.80$82.50$71.00$83.00
0030Asphalt material for tackTON A A9$1.00$0.01$0.01$1.00$0.01
0040Temporary signsSQFT A A210$7.42$6.50$0.01$7.00$4.00
0050Maintain & control trafficLS A A1$6,219.80$3,500.00$2,000.00$5,000.00$9,867.91
0060Mobilization for mill & textLS A A1$3,500.00$2,500.00$1,500.00$4,778.00$10,500
0070Asphalt pave milling & texturingTON A A40$16.00$26.45$6.00$10.00$1.00
0080Pave striping-temp paint-4 inLF A A8,000$0.01$0.01$0.01$0.30$0.01
0090Pave striping-perm paint-4 inLF A A27,000$0.23$0.32$0.27$0.32$0.32
0100Pave striping-thermo-12 in WLF A A156$7.78$8.00$7.78$8.00$8.00
0110Pave marking-thermo stop bar-24INLF A A64$12.45$15.00$12.45$15.00$15.00
0120DemobilizationLS A A1$1,647.00$1,567.82$1,567.99$2,000.00$1,960.00
KYTC contract 26-2065: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.

Every contract let that day: KYTC letting of March 26, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy