KYTC contract 26-2944 bid tabulation
BRIDGE REPAIRS I-64 RIVERSIDE EXPRESSWAY. Let by Kentucky Transportation Cabinet on March 26, 2026. 5 bids received.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 26 MAR 2026
- Pay items
- 127
- Data through
- 22 OCT 2026
4 of the 5 bids matched their published totals to within a dollar and are shown; the others are left out.
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 2 | American Contracting & Services Inc | $9,049,140 | +3.0% | 0.0% |
| 3 | Southern Road & Bridge LLC | $9,865,088 | +12% | +9.0% |
| 4 | Intech Contracting LLC | $12,880,679 | +46% | +43% |
| 5 | M & M Services Co Inc | $15,531,217 | +76% | +72% |
Engineer's estimate: $9,013,119.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. American Contracting & Services Inc | 2. Southern Road & Bridge LLC | 3. Intech Contracting LLC | 4. M & M Services Co Inc |
|---|---|---|---|---|---|---|---|
| 0010 | Barricade-type III | EACH A A | 8 | $500.00 | $125.00 | $1,000.00 | $550.00 |
| 0020 | Temporary signs | SQFT A A | 1,970 | $15.00 | $15.00 | $10.00 | $35.00 |
| 0030 | Truck mounted attenuator | EACH A A | 2 | $50,000 | $125,000 | $20,000 | $80,000 |
| 0040 | Portable changeable message sign | EACH A A | 8 | $15,000 | $11,000 | $7,500.00 | $16,800 |
| 0050 | Arrow panel | EACH A A | 5 | $4,000.00 | $11,000 | $2,500.00 | $1,600.00 |
| 0060 | Law enforcement officer | HOUR A A | 1,370 | $150.00 | $160.00 | $110.00 | $180.00 |
| 0070 | Portable queue warning alert system | MONT A A | 15 | $2,600.00 | $5,000.00 | $4,000.00 | $3,900.00 |
| 0080 | Queue warning PCMS | MONT A A | 15 | $800.00 | $500.00 | $2,750.00 | $1,650.00 |
| 0090 | Queue warning portable radar sensors | MONT A A | 15 | $50.00 | $500.00 | $100.00 | $1,050.00 |
| 0100 | Channel lining class II | TON A A | 5 | $500.00 | $405.00 | $750.00 | $225.00 |
| 0110 | Fabric-geotextile class 2 | SQYD A A | 181 | $5.00 | $7.00 | $30.00 | $8.00 |
| 0120 | Fabric-geotextile class 2 for pipe | SQYD A A | 291 | $2.00 | $2.00 | $2.00 | $2.00 |
| 0130 | Maintain & control traffic | LS A A | 1 | $115,000 | $150,000 | $200,000 | $75,000 |
| 0140 | Temp silt fence | LF A A | 900 | $5.00 | $4.00 | $10.00 | $3.00 |
| 0150 | Silt trap type A | EACH A A | 2 | $2,500.00 | $225.00 | $1,500.00 | $30.00 |
| 0160 | Clean silt trap type A | EACH A A | 2 | $500.00 | $65.00 | $500.00 | $38.00 |
| 0170 | Reinf conc slope wall-4 in | SQYD A A | 63 | $740.00 | $285.00 | $1,000.00 | $600.00 |
| 0180 | Railroad coordination | LS A A | 1 | $40,000 | $25,000 | $75,000 | $150,000 |
| 0190 | Channel lining class II | TON A A | 1 | $550.00 | $2,500.00 | $750.00 | $950.00 |
| 0200 | Fabric-geotextile class 2 | SQYD A A | 46 | $5.00 | $9.00 | $30.00 | $5.00 |
| 0210 | Fabric-geotextile class 2 for pipe | SQYD A A | 122 | $2.00 | $2.00 | $2.00 | $2.00 |
| 0220 | Maintain & control traffic | LS A A | 1 | $65,000 | $150,000 | $200,000 | $90,000 |
| 0230 | Temp silt fence | LF A A | 700 | $5.00 | $5.00 | $10.00 | $3.00 |
| 0240 | Silt trap type A | EACH A A | 2 | $2,500.00 | $250.00 | $1,500.00 | $30.00 |
| 0250 | Clean silt trap type A | EACH A A | 2 | $500.00 | $75.00 | $500.00 | $30.00 |
| 0260 | Reinf conc slope wall-4 in | SQYD A A | 27 | $740.00 | $350.00 | $1,000.00 | $450.00 |
| 0270 | Railroad coordination | LS A A | 1 | $50,000 | $20,000 | $75,000 | $80,000 |
| 0280 | Maintain & control traffic | LS A A | 1 | $125,000 | $150,000 | $200,000 | $65,000 |
| 0290 | Temp silt fence | LF A A | 500 | $5.00 | $5.00 | $10.00 | $3.00 |
| 0300 | Silt trap type C | EACH A A | 2 | $500.00 | $250.00 | $1,500.00 | $250.00 |
| 0310 | Clean silt trap type C | EACH A A | 2 | $500.00 | $100.00 | $500.00 | $500.00 |
| 0320 | Channel lining class II | TON A A | 6 | $500.00 | $450.00 | $750.00 | $185.00 |
| 0330 | Fabric-geotextile class 2 | SQYD A A | 294 | $5.00 | $8.00 | $30.00 | $5.00 |
| 0340 | Maintain & control traffic | LS A A | 1 | $90,000 | $150,000 | $200,000 | $18,000 |
| 0350 | Railroad coordination | LS A A | 1 | $50,000 | $15,000 | $75,000 | $55,000 |
| 0360 | Channel lining class II | TON A A | 8 | $500.00 | $650.00 | $750.00 | $250.00 |
| 0370 | Fabric-geotextile class 2 | SQYD A A | 375 | $5.00 | $6.00 | $30.00 | $5.00 |
| 0380 | Maintain & control traffic | LS A A | 1 | $210,000 | $150,000 | $200,000 | $18,000 |
| 0390 | Maintain & control traffic | LS A A | 1 | $120,000 | $150,000 | $200,000 | $18,000 |
| 0400 | Delineator for barrier - white | EACH A A | 14 | $100.00 | $150.00 | $25.00 | $20.00 |
| 0410 | Maintain & control traffic | LS A A | 1 | $210,000 | $150,000 | $200,000 | $22,000 |
| 0420 | Conc barrier wall type 9T | LF A A | 280 | $65.00 | $450.00 | $150.00 | $35.00 |
| 0430 | Crash cushion TY 6 class B TL2 | EACH A A | 1 | $10,000 | $11,500 | $15,000 | $26,000 |
| 0440 | Fiberglass drain pipe | LF A A | 2,106 | $370.00 | $225.00 | $390.00 | $480.00 |
| 0450 | Remove | LS A A | 1 | $100,000 | $125,000 | $180,000 | $80,000 |
| 0460 | Joint seal replacement | LF A A | 799 | $150.00 | $95.00 | $420.00 | $265.00 |
| 0470 | Fiberglass drain pipe | LF A A | 715 | $370.00 | $225.00 | $390.00 | $480.00 |
| 0480 | Remove | LS A A | 1 | $30,000 | $50,000 | $60,000 | $42,000 |
| 0490 | Joint seal replacement | LF A A | 182 | $160.00 | $95.00 | $170.00 | $210.00 |
| 0500 | Joint seal replacement | LF A A | 444 | $150.00 | $95.00 | $420.00 | $390.00 |
| 0510 | Jack & support bridge span | LS A A | 1 | $60,000 | $150,000 | $100,000 | $85,000 |
| 0520 | Fiberglass drain pipe | LF A A | 288 | $375.00 | $225.00 | $390.00 | $480.00 |
| 0530 | Concrete patching repair | SQFT A A | 37 | $300.00 | $850.00 | $401.00 | $350.00 |
| 0540 | Remove | LS A A | 1 | $25,000 | $25,000 | $25,000 | $28,000 |
| 0550 | Concrete repair | LS A A | 1 | $16,000 | $18,500 | $27,000 | $8,500.00 |
| 0560 | Joint seal replacement | LF A A | 1,017 | $150.00 | $95.00 | $420.00 | $360.00 |
| 0570 | Concrete coating | SQFT A A | 152 | $30.00 | $25.00 | $70.00 | $21.00 |
| 0580 | Fiberglass drain pipe | LF A A | 1,815 | $375.00 | $225.00 | $390.00 | $480.00 |
| 0590 | Bearing replacement | EACH A A | 1 | $20,000 | $125,000 | $28,500 | $24,000 |
| 0600 | Concrete patching repair | SQFT A A | 230 | $300.00 | $800.00 | $401.00 | $285.00 |
| 0610 | Remove | LS A A | 1 | $60,000 | $200,000 | $160,000 | $38,000 |
| 0620 | Joint seal replacement | LF A A | 2,110 | $160.00 | $95.00 | $170.00 | $240.00 |
| 0630 | Joint seal replacement | LF A A | 642 | $150.00 | $95.00 | $420.00 | $365.00 |
| 0640 | Steel repair | EACH A A | 2 | $2,100.00 | $6,500.00 | $2,500.00 | $25,000 |
| 0650 | Steel repair | EACH A A | 2 | $3,100.00 | $6,500.00 | $2,500.00 | $25,000 |
| 0660 | Steel repair | EACH A A | 2 | $3,100.00 | $6,500.00 | $2,500.00 | $25,000 |
| 0670 | Steel repair | EACH A A | 3 | $2,100.00 | $6,500.00 | $2,500.00 | $25,000 |
| 0680 | Steel repair | EACH A A | 3 | $4,500.00 | $6,500.00 | $2,500.00 | $25,000 |
| 0690 | Steel repair | EACH A A | 2 | $2,100.00 | $6,500.00 | $2,500.00 | $25,000 |
| 0700 | Steel repair | EACH A A | 7 | $2,000.00 | $6,500.00 | $2,500.00 | $25,000 |
| 0710 | Fiberglass drain pipe | LF A A | 74 | $550.00 | $250.00 | $450.00 | $580.00 |
| 0720 | Fiberglass drain pipe | LF A A | 2,561 | $370.00 | $225.00 | $390.00 | $440.00 |
| 0730 | Concrete patching repair | SQFT A A | 366 | $300.00 | $825.00 | $401.00 | $285.00 |
| 0740 | Remove | LS A A | 1 | $90,000 | $100,000 | $225,000 | $85,000 |
| 0750 | Concrete repair | LS A A | 1 | $25,000 | $25,000 | $80,000 | $6,500.00 |
| 0760 | Joint seal replacement | LF A A | 1,572 | $160.00 | $100.00 | $170.00 | $240.00 |
| 0770 | Joint seal replacement | LF A A | 908 | $150.00 | $100.00 | $420.00 | $360.00 |
| 0780 | Steel repair | EACH A A | 1 | $2,500.00 | $6,500.00 | $2,500.00 | $25,000 |
| 0790 | Steel repair | EACH A A | 3 | $1,900.00 | $6,500.00 | $2,500.00 | $25,000 |
| 0800 | Steel repair | EACH A A | 16 | $3,000.00 | $6,500.00 | $2,500.00 | $25,000 |
| 0810 | Steel repair | EACH A A | 1 | $2,900.00 | $6,500.00 | $2,500.00 | $25,000 |
| 0820 | Steel repair | EACH A A | 8 | $2,100.00 | $6,500.00 | $2,500.00 | $25,000 |
| 0830 | Steel repair | EACH A A | 4 | $3,500.00 | $6,500.00 | $2,500.00 | $25,000 |
| 0840 | Steel repair | EACH A A | 1 | $2,100.00 | $6,500.00 | $2,500.00 | $25,000 |
| 0850 | Steel repair | EACH A A | 8 | $4,500.00 | $6,500.00 | $2,500.00 | $25,000 |
| 0860 | Steel repair | EACH A A | 7 | $2,000.00 | $6,500.00 | $2,500.00 | $25,000 |
| 0870 | Steel repair | EACH A A | 1 | $1,800.00 | $4,400.00 | $3,300.00 | $25,000 |
| 0880 | Concrete patching repair | SQFT A A | 40 | $300.00 | $750.00 | $401.00 | $350.00 |
| 0890 | Joint seal replacement | LF A A | 2,653 | $160.00 | $100.00 | $170.00 | $190.00 |
| 0900 | Joint seal replacement | LF A A | 801 | $150.00 | $100.00 | $420.00 | $360.00 |
| 0910 | Steel repair | EACH A A | 3 | $4,400.00 | $7,000.00 | $2,500.00 | $25,000 |
| 0920 | Steel repair | EACH A A | 1 | $6,700.00 | $15,000 | $8,000.00 | $25,000 |
| 0930 | Steel repair | EACH A A | 17 | $3,000.00 | $6,500.00 | $2,500.00 | $25,000 |
| 0940 | Steel repair | EACH A A | 1 | $1,900.00 | $6,500.00 | $2,500.00 | $25,000 |
| 0950 | Steel repair | EACH A A | 13 | $3,000.00 | $6,500.00 | $2,500.00 | $25,000 |
| 0960 | Steel repair | EACH A A | 2 | $10,000 | $21,500 | $10,000 | $25,000 |
| 0970 | Jack & support bridge span | LS A A | 1 | $30,000 | $85,000 | $73,000 | $190,000 |
| 0980 | Jack & support bridge span | LS A A | 1 | $75,000 | $205,000 | $350,000 | $190,000 |
| 0990 | Fiberglass drain pipe | LF A A | 6 | $900.00 | $850.00 | $390.00 | $600.00 |
| 1000 | Concrete patching repair | SQFT A A | 250 | $300.00 | $800.00 | $401.00 | $250.00 |
| 1010 | Remove | LS A A | 1 | $5,000.00 | $10,000 | $5,000.00 | $2,500.00 |
| 1020 | Concrete repair | LS A A | 1 | $18,000 | $25,000 | $25,000 | $105,000 |
| 1030 | Retrofit | EACH A A | 2 | $22,000 | $95,000 | $45,000 | $95,000 |
| 1040 | Joint seal replacement | LF A A | 1,266 | $160.00 | $150.00 | $170.00 | $220.00 |
| 1050 | Joint seal replacement | LF A A | 1,287 | $150.00 | $150.00 | $420.00 | $260.00 |
| 1060 | Epoxy injection crack repair | LF A A | 2 | $1,000.00 | $500.00 | $1,000.00 | $190.00 |
| 1070 | Steel repair | EACH A A | 1 | $20,000 | $42,500 | $25,000 | $25,000 |
| 1080 | Steel repair | EACH A A | 1 | $8,000.00 | $10,000 | $8,000.00 | $25,000 |
| 1090 | Steel repair | EACH A A | 11 | $10,000 | $13,500 | $5,500.00 | $25,000 |
| 1100 | Steel repair | EACH A A | 1 | $28,000 | $30,000 | $12,000 | $25,000 |
| 1110 | Steel repair | EACH A A | 4 | $2,500.00 | $6,500.00 | $2,500.00 | $25,000 |
| 1120 | Steel repair | EACH A A | 1 | $3,100.00 | $6,500.00 | $2,500.00 | $25,000 |
| 1130 | Steel repair | EACH A A | 9 | $3,000.00 | $6,500.00 | $2,500.00 | $25,000 |
| 1140 | Steel repair | EACH A A | 1 | $2,900.00 | $6,500.00 | $2,500.00 | $25,000 |
| 1150 | Steel repair | EACH A A | 1 | $5,000.00 | $6,500.00 | $2,500.00 | $25,000 |
| 1160 | Steel repair | EACH A A | 37 | $1,800.00 | $4,000.00 | $3,300.00 | $25,000 |
| 1170 | Steel repair | EACH A A | 1 | $1,800.00 | $10,000 | $3,300.00 | $25,000 |
| 1180 | Bridge cleaning | LS A A | 1 | $150,000 | $250,000 | $500,000 | $65,000 |
| 1190 | Bearing lubrication | EACH A A | 7 | $4,000.00 | $1,500.00 | $1,500.00 | $650.00 |
| 1200 | Concrete coating | SQFT A A | 677 | $20.00 | $32.00 | $70.00 | $45.00 |
| 1210 | Concrete patching repair | SQFT A A | 195 | $300.00 | $800.00 | $401.00 | $350.00 |
| 1220 | Concrete patching repair | SQFT A A | 65 | $300.00 | $1,000.00 | $401.00 | $350.00 |
| 1230 | Concrete patching repair | SQFT A A | 15 | $300.00 | $1,250.00 | $401.00 | $350.00 |
| 1240 | Concrete patching repair | SQFT A A | 15 | $300.00 | $1,250.00 | $401.00 | $350.00 |
| 1250 | Concrete patching repair | SQFT A A | 125 | $300.00 | $900.00 | $401.00 | $350.00 |
| 1260 | Mobilization | LS A A | 1 | $407,211 | $450,000 | $604,727 | $725,000 |
| 1270 | Demobilization | LS A A | 1 | $133,927 | $225,000 | $181,418 | $229,525 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of March 26, 2026. Compiled by Mirage Metrics.