MoDOT contract 250620-C03 bid tabulation
JKU0017 - ROUTE I-29 - CLAY, PLATTE COUNTIES. Let by Missouri DOT on June 20, 2025, Platte, Kansas City. 3 bids received; low bid $14,141,227 by Superior Bowen Asphalt Company, LLC.
- Owner
- Missouri DOT
- Letting
- 20 JUN 2025
- Pay items
- 46
- Data through
- 16 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Superior Bowen Asphalt Company, LLC | $14,141,227 | Low |
| 2 | Ideker, Inc. | $14,180,165 | 0.0% |
| 3 | Emery Sapp & Sons, Inc. | $14,281,545 | +1.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Superior Bowen Asphalt Company, LLC | 2. Ideker, Inc. | 3. Emery Sapp & Sons, Inc. |
|---|---|---|---|---|---|---|
| 0010 | Signet dbe reporting (1081000) | LS | 1 | $1,000.00 | $1,000.00 | $1,000.00 |
| 0020 | Removal of improvements (2022010) | LS | 1 | $162,650 | $217,671 | $178,100 |
| 0030 | Linear grading class 1 (2071000) | STA | 8.20 | $1.00 | $2,594.26 | $1,150.00 |
| 0040 | Bituminous pavement mixture PG64-22, (BP-1) (4011209) | TON | 2,730 | $94.50 | $92.34 | $91.00 |
| 0050 | Bituminous pavement mixture PG64-22, (BP-2) (4011211) | TON | 14,822.80 | $103.00 | $89.43 | $90.80 |
| 0060 | Bituminous pavement mixture PG64-22 (base) (4013000) | TON | 184.20 | $182.00 | $269.96 | $234.50 |
| 0070 | Misc.remote truck sampling device installation (4019901) | LS | 1 | $5,000.00 | $25,000 | $22,324 |
| 0080 | Asphaltic concrete mixture PG 76-22 (SP095BSM mix) (4030009) | TON | 61,445.20 | $126.30 | $116.97 | $124.05 |
| 0090 | Tack coat - non-tracking (4071007) | GAL | 95,646 | $4.25 | $4.32 | $3.75 |
| 0100 | Truck mounted attenuator (TMA) (6123001) | LS | 1 | $1,000.00 | $121,500 | $9,743.50 |
| 0110 | Furnishing and placing concrete material for full depth pavement repair (6131010) | SY | 321.70 | $517.75 | $517.75 | $560.40 |
| 0120 | Subgrade compaction (6 in. depth) (pavement repair) (6131012) | SY | 33 | $1.00 | $1.00 | $1.08 |
| 0130 | Type 1 or 5 aggregate for base (4 in. thick) (pavement repair) (6131013) | SY | 33 | $1.00 | $1.00 | $1.08 |
| 0140 | Full depth pavement repair saw cut (for perimeter and internal saw cuts) (6131014) | LF | 1,356 | $1.45 | $1.45 | $1.57 |
| 0150 | Dowel bar (drilling, furnishing and installation) for full depth pavement repair (6131015) | EACH | 736 | $4.35 | $4.35 | $4.71 |
| 0160 | Dowel bar (furnishing and installation with baskets) for full depth pavement repair (6131017) | EACH | 10 | $9.20 | $9.20 | $9.96 |
| 0170 | Tie bar (drilling, furnishing and installation) for full depth pavement repair (type L joints) (6131018) | EACH | 7 | $2.90 | $2.90 | $3.14 |
| 0180 | Furnishing and placing bituminous material for class B partial depth pavement repair (6133018) | TON | 14.40 | $150.00 | $703.67 | $236.80 |
| 0190 | Removal for class B partial depth pavement repair (6133019) | SY | 86.40 | $100.00 | $108.41 | $237.60 |
| 0200 | Construction signs (6161005) | SF | 1,214 | $6.00 | $6.00 | $6.50 |
| 0210 | Channelizer (trim-line) (6161025) | EACH | 750 | $18.00 | $18.00 | $19.50 |
| 0220 | Type 3 moveable barricade (6161030) | EACH | 6 | $145.00 | $145.00 | $157.00 |
| 0230 | Direction indicator barricade (6161033) | EACH | 130 | $80.00 | $80.00 | $86.60 |
| 0240 | Flashing arrow panel (6161040) | EACH | 2 | $2,995.00 | $2,995.00 | $3,242.40 |
| 0250 | Changeable message sign without communication interface, contractor furnished retained (6161098A) | EACH | 6 | $4,750.00 | $4,750.00 | $5,142.40 |
| 0260 | Mobilization (6181000) | LS | 1 | $750,000 | $592,573 | $892,000 |
| 0270 | Preformed thermoplastic pavement marking, 12 in white (6200012) | LF | 339 | $11.00 | $11.00 | $11.90 |
| 0280 | Preformed thermoplastic pavement marking, left/right arrow (6200021) | EACH | 56 | $215.00 | $215.00 | $232.75 |
| 0290 | 6 in. white high build waterborne pavement marking paint, type L beads (6205902A) | LF | 271,370 | $0.25 | $0.25 | $0.27 |
| 0300 | 6 in. yellow high build waterborne pavement marking paint, type L beads (6205903A) | LF | 190,338 | $0.25 | $0.25 | $0.27 |
| 0310 | 12 in. white high build waterborne pavement marking paint, type L beads (6205906A) | LF | 26,359 | $0.48 | $0.48 | $0.50 |
| 0320 | 4 in. white standard waterborne pavement marking paint, type P beads (6206000C) | LF | 18,892 | $0.14 | $0.14 | $0.15 |
| 0330 | 4 in. yellow standard waterborne pavement marking paint, type P beads (6206001C) | LF | 8,035 | $0.14 | $0.14 | $0.15 |
| 0340 | Misc.temporary pavement marking paint (6209901) | LS | 1 | $1.00 | $1,000.01 | $40,000 |
| 0350 | Misc.preformed thermoplastic pavement marking, lane reduction arrow (6209902) | EACH | 2 | $575.00 | $575.00 | $622.50 |
| 0360 | Coldmilling bituminous pavement for removal of surfacing (3 in. thick or less) (6221001) | SY | 932,771 | $1.25 | $1.97 | $1.30 |
| 0370 | Modified coldmilling (depth transitions) (6224010) | SY | 1,805 | $8.00 | $18.18 | $7.95 |
| 0380 | Bituminous shoulder rumble strip (6261000A) | STA | 2,489.30 | $5.27 | $20.27 | $23.95 |
| 0390 | MGS guardrail (6061060) | LF | 42,347 | $21.50 | $21.50 | $23.30 |
| 0400 | MGS guardrail, 8 FT. posts, 6 FT. - 3 in. spacing (6061061) | LF | 2,673 | $26.00 | $26.00 | $28.15 |
| 0410 | MGS bridge approach transition section (regular/no curb) (6061069) | EACH | 54 | $3,343.00 | $3,343.00 | $3,619.20 |
| 0420 | MGS vertical concrete barrier transition (6061070) | EACH | 42 | $3,069.00 | $3,069.00 | $3,322.50 |
| 0430 | MGS end anchor (6061080) | EACH | 57 | $1,030.00 | $1,030.00 | $1,115.10 |
| 0440 | Asymmetrical transition section, 6.5 FT. posts (6062303) | EACH | 22 | $472.00 | $472.00 | $511.00 |
| 0450 | Type A crashworthy end terminal (MASH) (6063014) | EACH | 94 | $2,545.00 | $2,545.00 | $2,755.25 |
| 0460 | Type C crashworthy end terminal (MASH) (6063020) | EACH | 2 | $23,521 | $23,521 | $25,464 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
Every contract let that day: MoDOT letting of June 20, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.