Coldmill, resurface and crack fill bridges. Let by Missouri DOT on June 20, 2025, Franklin, St. Louis. 4 bids received; low bid $13,898,000 by N.B. West Contracting Company.
- Owner
- Missouri DOT
- Letting
- 20 JUN 2025
- Pay items
- 42
- Data through
- 16 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | N.B. West Contracting Company | $13,898,000 | Low |
| 2 | Magruder Paving, LLC | $14,345,568 | +3.0% |
| 3 | Pace Construction Company, LLC | $14,480,000 | +4.0% |
| 4 | Emery Sapp & Sons, Inc. | $16,371,750 | +18% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. N.B. West Contracting Company | 2. Magruder Paving, LLC | 3. Pace Construction Company, LLC | 4. Emery Sapp & Sons, Inc. |
|---|---|---|---|---|---|---|---|
| 0010 | Signet dbe reporting (1081000) | LS | 1 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 |
| 0020 | Removal of improvements (2022010) | LS | 1 | $20,000 | $20,000 | $39,733 | $21,750 |
| 0030 | Misc.modified shaping slopes, class III (2159903) | LF | 3,648 | $14.00 | $14.00 | $14.00 | $15.20 |
| 0040 | Bituminous pavement mixture PG64-22, (BP-1) (4011209) | TON | 27,400 | $64.00 | $72.17 | $68.00 | $83.50 |
| 0050 | Asphaltic concrete mixture PG 70-22 (SP095C mix) (4030003) | TON | 23,860 | $78.25 | $85.56 | $81.75 | $94.50 |
| 0060 | Asphaltic concrete mixture PG 70-22 (SP095CLP mix) (4030011) | TON | 28,670 | $79.25 | $82.16 | $83.00 | $96.50 |
| 0070 | Asphaltic concrete mixture PG 76-22 (SP095CLP mix) (4030012) | TON | 50,180 | $79.50 | $84.55 | $83.00 | $101.50 |
| 0080 | Tack coat - non-tracking (4071007) | GAL | 119,080 | $3.25 | $3.35 | $3.65 | $3.50 |
| 0090 | Misc.high friction surface treatment (4139905) | SY | 4,562 | $18.45 | $18.45 | $18.45 | $23.50 |
| 0100 | Furnishing and placing concrete material for full depth pavement repair (6131010) | SY | 2,828.60 | $345.00 | $268.00 | $268.00 | $300.00 |
| 0110 | Type 1 or 5 aggregate for base (4 in. thick) (pavement repair) (6131013) | SY | 2,829 | $0.50 | $1.00 | $1.00 | $1.00 |
| 0120 | Full depth pavement repair saw cut (for perimeter and internal saw cuts) (6131014) | LF | 11,930 | $16.00 | $6.00 | $6.00 | $6.50 |
| 0130 | Dowel bar (drilling, furnishing and installation) for full depth pavement repair (6131015) | EACH | 5,430 | $12.00 | $6.75 | $6.75 | $7.35 |
| 0140 | Dowel bar (furnishing and installation with baskets) for full depth pavement repair (6131017) | EACH | 2,900 | $0.50 | $15.20 | $15.20 | $16.50 |
| 0150 | Changeable message sign without communication interface, contractor furnished retained (6161098A) | EACH | 6 | $3,000.00 | $3,000.00 | $3,000.00 | $3,250.00 |
| 0160 | Misc.temporary traffic control (6169901) | LS | 1 | $20,000 | $22,393 | $20,000 | $20,500 |
| 0170 | Mobilization (6181000) | LS | 1 | $514,253 | $330,400 | $700,000 | $602,000 |
| 0180 | Preformed thermoplastic pavement marking, 24 in. white (6200015) | LF | 1,090 | $17.00 | $17.00 | $17.00 | $18.50 |
| 0190 | Preformed thermoplastic pavement marking, left/right arrow (6200021) | EACH | 157 | $215.00 | $215.00 | $215.00 | $233.00 |
| 0200 | Preformed thermoplastic pavement marking, combination STR/LT/RT (6200027) | EACH | 23 | $315.00 | $315.00 | $315.00 | $340.00 |
| 0210 | Preformed thermoplastic pavement marking, word (only) (6200030) | EACH | 14 | $325.00 | $325.00 | $325.00 | $350.00 |
| 0220 | Preformed thermoplastic pavement marking, 12 in white, yield line triangles (6200042) | EACH | 164 | $17.00 | $17.00 | $17.00 | $18.50 |
| 0230 | 4 in. yellow high build waterborne pavement marking paint, type L beads (6205901A) | LF | 172,870 | $0.19 | $0.19 | $0.19 | $0.21 |
| 0240 | 6 in. white high build waterborne pavement marking paint, type L beads (6205902A) | LF | 406,029 | $0.28 | $0.28 | $0.28 | $0.30 |
| 0250 | 6 in. yellow high build waterborne pavement marking paint, type L beads (6205903A) | LF | 114,690 | $0.27 | $0.27 | $0.27 | $0.29 |
| 0260 | 24 in. white standard waterborne pavement marking paint, type P beads (6206124A) | LF | 1,203 | $5.00 | $5.00 | $5.00 | $5.45 |
| 0270 | Misc.temporary pavement marking paint (6209901) | LS | 1 | $72,500 | $72,500 | $40,000 | $1.00 |
| 0280 | Misc.lane reduction arrow, preformed themoplastic pavement marking (6209902) | EACH | 6 | $1,200.00 | $1,200.00 | $1,200.00 | $1,300.00 |
| 0290 | Coldmilling bituminous pavement for removal of surfacing (3 in. thick or less) (6221001) | SY | 380,918 | $1.65 | $2.37 | $2.27 | $1.90 |
| 0300 | Modified coldmilling (depth transitions) (6224010) | SY | 34,726 | $6.00 | $4.80 | $5.35 | $4.50 |
| 0310 | Bituminous shoulder rumble strip (6261000A) | STA | 3,886 | $12.00 | $12.00 | $17.25 | $13.00 |
| 0320 | Bituminous centerline rumble strip (6261001) | STA | 412 | $15.00 | $15.00 | $27.00 | $16.25 |
| 0330 | Contractor furnished surveying and staking (6274000) | LS | 1 | $39,018 | $10,000 | $2,500.00 | $4,000.00 |
| 0340 | MGS guardrail, 8 FT. posts, 6 FT. - 3 in. spacing (6061061) | LF | 2,287.50 | $30.00 | $30.00 | $30.00 | $32.50 |
| 0350 | MGS bridge approach transition section (regular/no curb) (6061069) | EACH | 10 | $4,000.00 | $4,000.00 | $4,000.00 | $4,300.00 |
| 0360 | MGS end anchor (6061080) | EACH | 2 | $1,800.00 | $1,800.00 | $1,800.00 | $1,950.00 |
| 0370 | Type A crashworthy end terminal (MASH) (6063014) | EACH | 18 | $3,800.00 | $3,800.00 | $3,800.00 | $4,120.00 |
| 0380 | Cable, loop detector, in duct (9028500) | LF | 5,030 | $5.40 | $5.40 | $6.25 | $5.85 |
| 0390 | Concrete footings, embedded (9031010) | CY | 1.10 | $2,500.00 | $2,500.00 | $2,500.00 | $3,000.00 |
| 0400 | Pipe posts (9031220) | LB | 530 | $8.00 | $8.00 | $8.00 | $8.70 |
| 0410 | 36 in. surface-mount delineator post (9031242) | EACH | 2 | $180.00 | $180.00 | $180.00 | $200.00 |
| 0420 | Concrete crack filler (7040163) | SY | 14,164 | $14.95 | $14.95 | $14.95 | $18.05 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
Every contract let that day: MoDOT letting of June 20, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.