MoDOT contract 251017-C08 bid tabulation

JKU0400 - ROUTE 58 - CASS COUNTY. Let by Missouri DOT on October 17, 2025, Cass, Kansas City. 3 bids received; low bid $3,787,450 by Ideker, Inc..

Owner
Missouri DOT
Letting
17 OCT 2025
Pay items
39
Data through
16 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Ideker, Inc.$3,787,450Low
2Emery Sapp & Sons, Inc.$3,827,714+1.0%
3Superior Bowen Asphalt Company, LLC$4,389,075+16%
MoDOT contract 251017-C08: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Ideker, Inc.2. Emery Sapp & Sons, Inc.3. Superior Bowen Asphalt Company, LLC
0010Signet dbe reporting (1081000)LS1$1,000.00$1,000.00$1,000.00
0020Removal of improvements (2022010)LS1$192,621$82,773$190,875
0030Linear grading class 1 (2071000)STA308$405.00$206.54$405.00
0040Shaping slopes, class III (2153000)100F12$675.00$1,500.00$1,500.00
0050Misc.permanent aggregate edge treatment (3049910)TON3,070$85.95$46.21$44.30
0060Bituminous pavement mixture PG64-22, (BP-1) (4011209)TON23,926.90$71.37$94.40$98.00
0070Bituminous pavement mixture PG64-22 (base widening) (4013010)TON3,086.90$122.18$90.54$122.00
0080Tack coat (4071005)GAL34,398$2.89$2.88$3.25
0090Concrete curb ramp (6081010)SY18.60$667.20$677.21$667.20
0100Truncated domes (6081012)SF67$25.40$25.78$25.40
0110Misc.water valve and manhole height adjustment (6099902)EACH7$250.00$4,000.00$628.44
0120Furnishing and placing concrete material for full depth pavement repair (6131010)SY261.30$472.20$479.28$472.20
0130Subgrade compaction (6 in. depth) (pavement repair) (6131012)SY26$1.00$1.01$1.00
0140Type 1 or 5 aggregate for base (4 in. thick) (pavement repair) (6131013)SY26$1.00$1.01$1.00
0150Full depth pavement repair saw cut (for perimeter and internal saw cuts) (6131014)LF1,148$1.45$1.47$1.45
0160Dowel bar (drilling, furnishing and installation) for full depth pavement repair (6131015)EACH600$7.80$7.92$7.80
0170Furnishing and placing bituminous material for class B partial depth pavement repair (6133018)TON201.10$207.64$119.59$144.91
0180Removal for class B partial depth pavement repair (6133019)SY591.80$118.19$135.28$219.60
0190Construction signs (6161005)SF1,921$7.50$3.20$7.50
0200Channelizer (trim-line) (6161025)EACH442$5.00$12.00$5.00
0210Changeable message sign without communication interface, contractor furnished retained (6161098A)EACH2$2,015.00$2,000.00$2,015.00
0220Mobilization (6181000)LS1$400,571$235,100$400,000
0230Preformed thermoplastic pavement marking, 24 in. white (6200015)LF204$21.00$21.00$21.00
0240Preformed thermoplastic pavement marking, left/right arrow (6200021)EACH1$250.00$250.00$250.00
0250Preformed thermoplastic pavement marking, R/R crossing marker (6200033)EACH4$1,350.00$1,350.00$1,350.00
02604 in. white class 1 pavement marking paint (18-mil, type P beads) (6206000D)LF155,473$0.12$0.12$0.12
02704 in. yellow class 1 pavement marking paint (18-mil, type P beads) (6206001D)LF120,093$0.12$0.12$0.12
028024 in. yellow class 1 pavement marking paint (18-mil, type P beads) (6206125B)LF80$18.00$18.00$18.00
0290Modified coldmilling (depth transitions) (6224010)SY9,511$9.36$8.34$7.75
0300Bituminous shoulder rumble strip (6261000A)STA950$15.58$15.54$14.00
0310Mulching (8025006)ACRE2.80$1,960.00$800.00$800.00
0320Seeding - cool season grasses (8051000A)ACRE1.40$1,120.00$2,600.00$2,600.00
0335Alternate ditch check (8061006)LF12,894$2.26$5.20$5.20
0340Sediment removal (8061016)CY1,842$2.00$4.70$10.00
0350Temporary seeding (8061017)ACRE1.40$1,120.00$900.00$900.00
0360MGS guardrail, 8 FT. posts, 6 FT. - 3 in. spacing (6061061)LF825$25.50$29.00$29.00
0370MGS bridge approach transition section (regular/no curb) (6061069)EACH16$3,839.00$3,300.00$3,300.00
0380MGS height and block transition (6061074)EACH12$950.00$700.00$700.00
0390Type A crashworthy end terminal (MASH) (6063014)EACH16$3,172.00$3,000.00$3,000.00
MoDOT contract 251017-C08: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.

Every contract let that day: MoDOT letting of October 17, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy