MoDOT contract 251017-H03 bid tabulation
JSE0117 - ROUTE 25 - CAPE GIRARDEAU, STODDARD COUNTIES. Let by Missouri DOT on October 17, 2025, Cape Girardeau, Southeast. 3 bids received; low bid $3,728,000 by Pace Construction Company, LLC.
- Owner
- Missouri DOT
- Letting
- 17 OCT 2025
- Pay items
- 45
- Data through
- 16 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Pace Construction Company, LLC | $3,728,000 | Low |
| 2 | Apex Paving Co. | $3,943,990 | +6.0% |
| 3 | Above And Below Contracting, LLC | $4,985,629 | +34% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Pace Construction Company, LLC | 2. Apex Paving Co. | 3. Above And Below Contracting, LLC |
|---|---|---|---|---|---|---|
| 0010 | Signet dbe reporting (1081000) | LS | 1 | $1,000.00 | $1,000.00 | $1,000.00 |
| 0020 | Removal of improvements (2022010) | LS | 1 | $7,393.15 | $3,200.00 | $5,912.84 |
| 0030 | Misc.modifed shaping slopes; class III (2159910) | 100F | 6 | $1,400.00 | $1,400.00 | $1,726.60 |
| 0040 | Misc.permanent aggregate edge treatment (3049910) | TON | 5,349.70 | $34.90 | $34.00 | $46.73 |
| 0050 | Gravel (A) or crushed stone (B) (3105002) | TON | 234 | $21.75 | $34.00 | $62.85 |
| 0060 | Bituminous pavement mixture PG64-22, (BP-2) (4011211) | TON | 36,293.20 | $72.50 | $78.25 | $100.31 |
| 0070 | Tack coat (4071005) | GAL | 32,200 | $2.60 | $2.65 | $3.66 |
| 0080 | Emulsified asphalt, seal coat (4091048) | GAL | 321 | $3.00 | $3.00 | $8.54 |
| 0090 | Seal coat aggregate, grade A1 (4094001) | SY | 803 | $5.00 | $1.60 | $14.64 |
| 0100 | Work zone crash cushion (narrow) (6122040) | EACH | 4 | $3,500.00 | $3,500.00 | $4,270.00 |
| 0110 | Work zone crash cushion (narrow) (relocation) (6122041) | EACH | 4 | $3,500.00 | $3,500.00 | $4,270.00 |
| 0120 | Furnishing and placing concrete material for full depth pavement repair (6131010) | SY | 116 | $400.00 | $400.00 | $317.13 |
| 0130 | Subgrade compaction (6 in. depth) (pavement repair) (6131012) | SY | 12 | $10.00 | $10.00 | $61.77 |
| 0140 | Type 1 or 5 aggregate for base (4 in. thick) (pavement repair) (6131013) | SY | 12 | $10.00 | $10.00 | $63.69 |
| 0150 | Full depth pavement repair saw cut (for perimeter and internal saw cuts) (6131014) | LF | 470 | $8.00 | $8.00 | $13.55 |
| 0160 | Dowel bar (drilling, furnishing and installation) for full depth pavement repair (6131015) | EACH | 320 | $12.00 | $12.00 | $8.11 |
| 0170 | Furnishing and placing bituminous material for class B partial depth pavement repair (6133018) | TON | 46.50 | $540.00 | $1,055.03 | $192.79 |
| 0180 | Removal for class B partial depth pavement repair (6133019) | SY | 204.30 | $105.00 | $158.55 | $114.66 |
| 0190 | Construction signs (6161005) | SF | 2,233 | $6.00 | $6.00 | $7.32 |
| 0200 | Channelizer (trim-line) (6161025) | EACH | 135 | $12.00 | $12.00 | $14.64 |
| 0210 | Changeable message sign without communication interface, contractor furnished retained (6161098A) | EACH | 2 | $2,800.00 | $2,800.00 | $3,416.00 |
| 0220 | Work zone traffic signal system (6162000A) | EACH | 1 | $10,000 | $10,000 | $12,200 |
| 0230 | Temporary traffic barrier, contractor furnished retained (6173600D) | LF | 850 | $26.00 | $26.00 | $31.72 |
| 0240 | Relocating temporary traffic barrier (6175010A) | LF | 850 | $22.00 | $22.00 | $26.84 |
| 0250 | Mobilization (6181000) | LS | 1 | $170,000 | $176,155 | $182,275 |
| 0260 | Temporary removable marking tape 4 in., white (6205301B) | LF | 1,700 | $3.00 | $1.85 | $3.66 |
| 0270 | Temporary removable marking tape 4 in., yellow (6205303B) | LF | 4,000 | $3.00 | $1.85 | $3.66 |
| 0280 | Temporary removable marking tape, 24 in., white (6205309) | LF | 48 | $9.00 | $12.00 | $10.98 |
| 0290 | 4 in. white class 1 pavement marking paint (18-mil, type P beads) (6206000D) | LF | 155,572 | $0.13 | $0.13 | $0.16 |
| 0300 | 4 in. yellow class 1 pavement marking paint (18-mil, type P beads) (6206001D) | LF | 31,489 | $0.14 | $0.14 | $0.18 |
| 0310 | Pavement marking removal (6207001) | LF | 1,750 | $2.50 | $2.00 | $3.05 |
| 0320 | Coldmilling bituminous pavement for removal of surfacing (3 in. thick or less) (6221001) | SY | 5,484 | $5.35 | $8.63 | $5.33 |
| 0330 | Modified coldmilling (depth transitions) (6224010) | SY | 5,845 | $7.70 | $4.40 | $12.01 |
| 0340 | Bituminous shoulder rumble strip (6261000A) | STA | 1,444 | $17.00 | $11.25 | $15.86 |
| 0350 | Bituminous centerline rumble strip (6261001) | STA | 772.10 | $26.00 | $11.25 | $24.40 |
| 0360 | MGS guardrail (6061060) | LF | 1,000 | $28.50 | $28.50 | $35.43 |
| 0370 | MGS bridge approach transition (thrie-beam bridge) (6061081) | EACH | 7 | $4,800.00 | $4,800.00 | $6,998.08 |
| 0380 | Type A crashworthy end terminal (MASH) (6063014) | EACH | 7 | $3,850.00 | $3,850.00 | $3,960.63 |
| 0390 | Type C crashworthy end terminal (MASH) (6063020) | EACH | 1 | $36,000 | $36,000 | $38,406 |
| 0400 | Misc.removal of bridge guardrail (thrie beam) (2169903) | LF | 137 | $20.00 | $20.00 | $53.95 |
| 0410 | Half-sole repair (7040104) | SF | 100 | $180.00 | $189.00 | $171.11 |
| 0420 | Bridge guardrail (thrie beam) (7134000) | LF | 135 | $360.00 | $360.00 | $553.78 |
| 0430 | Misc.removal of bridge guardrail (thrie beam) (2169903) | LF | 137 | $20.00 | $20.00 | $53.95 |
| 0440 | Half-sole repair (7040104) | SF | 100 | $180.00 | $189.00 | $171.11 |
| 0450 | Bridge guardrail (thrie beam) (7134000) | LF | 135 | $360.00 | $360.00 | $553.78 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
Every contract let that day: MoDOT letting of October 17, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.